  1. Slide 1: Emerald to Become +100,000ozpa Gold Producer

    Okvau Gold Project, Cambodia ASX:EMR Emerald to Become +100,000ozpa Gold Producer Investor Presentation January 2020

  2. Slide 2: Presentation Disclaimer

    Presentation Disclaimer Forward Looking Statement This announcement contains certain forward looking statements. These forward-looking statements are not historical facts but rather are based on the Company’s current expectations, estimates and projections about the industry in which Emerald Resourc

  3. Slide 3: Emerald a Short History

    Emerald a Short History  November 2016 - Merger with Renaissance Minerals Limited;  May 2017 - Okvau Definitive Feasibility announced; and  May 2017 - Maiden Ore Reserve of 14.3Mt @ 2.0g/t Au for 907,000oz.  July 2017 - Expansion of its ground holdings in Cambodia (400km² - 1,400km²);  November

  4. Slide 4: Capital Structure, Board & Management

    Board & Management Capital Structure Simon Lee AO, Non-Executive Chairman  Previously Chairman: Equigold NL, Samantha Gold NL, and Great ASX Code EMR Victoria Gold NL;  Previously Board Member of the Australian Trade Commission and Patron Share Price 4.0 cents¹ of the Western Australian Chinese Ch

  5. Slide 5: Debt Funding Overview

    Debt Funding Overview US$60M Okvau Project Facility US$60M investment committee approved Term Sheet (“Okvau Facility”) signed with Sprott Private Resource Lending II L.P. (“Sprott”) for development of the Okvau Gold Project:-  Key terms of the Okvau Facility:-  Facility amount – US$60 million;  T

  6. Slide 6: Cambodia Overview & Project Location

    Cambodia Overview & Project Location First mover advantage in frontier terrain Attractive fiscal regime:  100% ownership;  30% corporate tax rate for mining;  25% for Emerald first 5 years.  3.0% Government Gold royalty (net)³;  Full Import duty exemptions for first 3 years. 1,442km² of under

  7. Slide 7: Cambodia Overview

    Cambodia Overview Attractive Mining Jurisdiction  Pro-development government, focused on economic growth and in supporting an early stage mining industry in order to diversify revenue from its cornerstone textile industry;  Continues to enjoy strong economic growth, averaging 7.7% from 1995 to 201

  8. Slide 8: Mineral Investment Agreement

    Mineral Investment Agreement (“MIA”) Mineral Investment Agreement (“MIA”) Highlights  Fully executed MIA by Minister of Mines & Energy and Minister of Economy & Finance;  MIA provides clarity and stability for the Okvau Gold Project development and operations;  The first of its kind for a large s

  9. Slide 9: Okvau Project Summary

    Okvau Project Summary | Robust & Compelling Economics Economical Robust Project Project DFS Economics of US$1,450/oz Gold (100% Ownership)  JORC Ore Reserve of 14.3Mt @ 2.0g/t Au for Development Capital Costs1 US$91M 907,000oz;  2.0Mtpa plant to produce 106,000oz pa; Mining Contractor Capital & Pr

  10. Slide 10: Low All-in Sustaining Costs

    Low All-in Sustaining Costs | High Margin Mine Site Layout Operating Cost Summary Life of Mine On-Site Mining US$344/oz On-Site Processing US$261/oz On-Site G&A US$48/oz Transport and Refining US$5/oz C1 costs US$658/oz Royalties1 US$65/oz Sustaining Capital & Closure Costs US$31/oz AISC US$754/oz 1

  11. Slide 11: Okvau JORC Reserve

    Okvau JORC Reserve | 2.0g/t Au for 907,000 ounces gold  650 metres of strike by 600 metres width of the JORC Resource (0.7g/t gold cut-off) 1 mineralised vein system; Resource Tonnage Grade Au Gold Classification (Mt) (g/t) (Koz)  Drill spacing of 25m x 25m in the top 120m; Indicated 15.11 2.08 1,

  12. Slide 12: Grade Control Simulation

    Okvau Grade Control Simulation  Infill Grade Control simulation drilling programme 368 holes for 10,100m;  10m x 10m infill pattern to an average vertical depth of 25m;  Results confirm continuity, grade and tonnage estimate of resource model;  Best results of:-  4m @ 22.93g/t gold from 18m (GC

  13. Slide 13: Resource Growth | Southern Depth Extensions

    Okvau Resource Growth | Southern Depth extensions  Some of the highest grade intersections sit beneath open pit floor including:-  17m @ 4.5g/t from 320m (DD11OKV091);  10m @ 9.6g/t from 411m (DD12OKV108);  11m @ 8.4g/t from 399m (DD11OKV091);  6m @ 9.7g/t from 520m (DD16OKV373). Cross-section

  14. Slide 14: Potential Structural Feeder Zone

    Okvau Potential Structural Feeder Zone Selected Okvau feeder zone intersections:-  32m @ 2.75g/t from 59m (DD11OKV086)¹;  7m @ 12.30g/t from 236m (DD11OKV085)¹;  13m @ 7.16g/t from 271m (DD11OKV078)¹;  1m @ 34.90g/t from 228m (DD09OKV026)¹;  4m @ 16.08g/t from 69m (RC16OKV254)¹;  9m @ 9.27g/t

  15. Slide 15: Commenced Construction of Permanent Access Road

    Okvau | Commenced Construction of Permanent Access Road  Okvau Access Road materially complete which includes  35 tonne concrete Prek Te river bridge construction substantial completion of upgrades to the existing materially complete. 50km of dirt roads and current finalisation of the construction

  16. Slide 16: Resettlement

    Okvau – Resettlement  62 local families successfully relocated from the project area;  Process governed by a committee of relevant stakeholders, conducted in a manner consistent with the IFC guidelines and approved Resettlement Action Plan;  Existing housing dismantled and removed;  Provisions m

  17. Slide 17: Grid Power, Fencing & Ranger Hut

    Okvau – Grid Power, Fencing & Ranger Hut  Tower Footings on Okvau PDA.  Okvau PDA Fencing Complete.  Aerial View Powerline Towers &  Ranger Hut provided and Corridor nearing completion, and will be built by Emerald. available well ahead of site requirements. ASX: EMR | www.emeraldresources.com.a

  18. Slide 18: Grade Control Drilling Commenced

    Okvau – Grade Control Drilling Commenced  5m x 5m RC grade control drilling commenced with  Contract awarded for the provision of ongoing UDR650 rig. grade control drilling with a fit for purpose modified 450 Schramm Percussion drilling Rig. ASX: EMR | www.emeraldresources.com.au 18

  19. Slide 19: Regional Potential | New Joint Ventures

    Regional Potential | New Joint Ventures  Dominant land position of ~1,400km² covering a north-west trending zone of granitoid intrusions;  Multiple Gold occurrences with direct associations with intrusions with pathfinder multi-elements (bismuth, arsenic, tellurium). Koan Nheak (Earning 80%) Phnom

  20. Slide 20: Mekong Minerals Snoul Project

    Mekong Minerals Snoul Project  3km, x 1.5km gold in soil anomaly (at Limited historical drilling >10ppb Au); returned best results of :- 4m @ 11.94g/t gold from 4m (SNRC002);  Peak value auger 16m @ 2.93g/t gold form 4m sampling 22.3ppm Au; (SNRC009); 12m @ 1.01g/t gold from 12m (SNRC010);  Peak

  21. Slide 21: Mekong Minerals Phnom Khtong Project

    Mekong Minerals Phnom Khtong Project  Western anomaly 1.3km x 0.4km (at >30ppb Au); and  Central anomaly 1km x 0.4km (at >10ppb Au);  Peak value auger sampling 7.27 ppm Au;  Peak value rock chip 38.3g/t Au;  Geological setting similar to Okvau with mineralisation coincidental with Diorite intru

  22. Slide 22: Angkor JV Koan Nheak Project

    Angkor JV Koan Nheak Project  Two gold in soil anomalies discoveries;  Northern anomaly 0.7km x 0.3km (at >10ppb Au);  Southern anomaly 1.4km x 0.4km (at >10ppb Au);  Peak value EMR rock chip 9.94g/t Au;  Geological setting similar to Okvau on the southern extremity of a Diorite intrusion;  Em

  23. Slide 23: Summary

    Summary  Experienced, well credentialed Board and senior management, well equipped to develop Okvau and other gold projects;  Emerald developing a single pit, 2.0g/t, 907,000 ounce gold reserve at US$754/ounce (AISC);  Resource open with strong potential to expand and convert additional reserves;

  24. Slide 24: Metallurgy & Processing

    Metallurgy & Processing | Extensive test work completed Conventional Flotation & Leaching Coarse primary grind (>106µm) and sulphide flotation Low mass pull (8%), high grade concentrate Fine regrind of concentrate only (no oxidation) Leaching (flotation tails and concentrate) & Elution Gold recoveri

  25. Slide 25: Total Operating Cost Summary

    Okvau Project Summary | Total Operating Cost Summary US$1,450 Gold price assumption. Operating Costs LOM USD/t USD/oz USD (processed) (recovered) Mining 262M 18.37 344 Processing & Maintenance 199M 13.93 261 General & Administration 37M 2.58 48 Refining 3M 0.25 5 Sub Total 501M 35.13 658 Sustaining

  26. Slide 26: Environmental & Social Values

    Environmental & Social Values The Okvau project is to have a (net) positive impact on near-mine environmental and social values via:-  Target strict compliance with corporate governance, international guidelines (IFC PS’s) and Cambodian law;  The introduction of “Environmental Bonding” concept to