  1. Slide 1: 2015 Full Year Financial Results

    2015 Full Year Financial Results 17 August 2015 Sandeep Biswas Managing Director and Chief Executive Officer Gerard Bond Finance Director and Chief Financial Officer

  2. Slide 2: Disclaimer – Forward Looking Statements

    Disclaimer Forward Looking Statements These materials include forward looking statements. Often, but not always, forward looking statements can generally be identified by the use of forward looking words such as “may”, “will”, “expect”, “intend”, “plan”, “estimate”, “anticipate”, “continue”, “outloo

  3. Slide 3: Disclaimer – Competent Person's Statement

    Disclaimer Competent Person’s Statement The information in this presentation that relates to Exploration Targets, Exploration Results, Mineral Resources and Ore Reserves, is based on information compiled by Mr C. Moorhead. Mr Moorhead is the Executive General Manager Minerals and a full-time employe

  4. Slide 4: Overview

    Overview Slides Cadia underground Financial Year 2015 Summary 5 – 12 Review by operation 13 – 18 Financial results 19 – 28 Update on key assets 29 – 39 Growth 40 – 42 Summary 43 Q&A and Appendices 44 – 52 4

  5. Slide 5: Safety & environment

    Safety & environment Lost Time Injury Frequency Rate per million hours • 2 fatalities in FY15 0.65 – Hidden Valley (Dec 2014) 0.36 0.42 – Telfer (May 2015) • 1 fatality in FY16 FY13 FY14 FY15 – Hidden Valley (July 2015) Total Recordable Injury Frequency Rate • NewSafe program launched per million ho

  6. Slide 6: Financial Year 2015 summary

    Financial Year 2015 summary Good financial results • All-In Sustaining Cost1 of USD 789/oz2 • USD net debt reduction of USD 819m • Statutory profit of AUD 546m • Underlying profit of AUD 515m • Free cash flow of AUD 1,086m • Edge program cash benefit of ~AUD 390m to date • Nine consecutive quarters

  7. Slide 7: Looking ahead

    Looking ahead Update on key asset reviews • Lihir Pit Optimisation Study – potential for lower development costs • Telfer Future Options Review – asset retained and initial cutbacks approved • Cadia continued ramp-up – Panel Cave 2 recommenced Positioning for growth • New Chief Development Officer a

  8. Slide 8: Newcrest maintains leading cost position

    Newcrest maintains leading cost position 1 1250 AngloGold Barrick Gold Fields 1150 USD AISC3 + Interest Expense per ounce1 1050 950 Kinross Newcrest 850 Goldcorp Newmont 750 Note: Width of bubble size represents relative size of gold reserves 650 0 5 10 15 20 25 30 35 40 Indicative Reserve life year

  9. Slide 9: Edge program delivering cash and cultural change

    Edge program delivering cash and cultural change • Newcrest’s Edge program has delivered cash benefits1 of ~AUD 390m to date • Value delivered from improvement in operational performance, costs, working capital and overhead • Key focus areas continue to be: – safety – operational discipline – cash g

  10. Slide 10: Edge example – Gosowong delivering results

    Edge example – Gosowong delivering results • Overhaul equipment and rebuild components on site – delivering value of USD 3.5m per annum • Resin injection and expanding foam to mine and manage fall of ground and voids – injecting resin to fill the voids allowing stabilisation of ground to mine high g

  11. Slide 11: Performance against key objectives

    Performance against key objectives Financial objective1 Outcomes Deliver on production and cost  Nine consecutive quarters delivered of meeting or exceeding guidance guidance  AISC2 A$ million spend was below lower end of guidance range Low cost curve position  Group USD 789 AISC/oz, 12% lower th

  12. Slide 12: New senior leadership appointments and accountabilities

    New senior leadership appointments and accountabilities Michael Nossal Craig Jones Philip Stephenson Craig Jetson Chief Development Officer General Manager Executive General Manager Executive General Manager Commenced July 2015 Reporting to CEO Global exploration Panel Cave Operations Operations Ope

  13. Slide 13: Financial Year 2015 operational overview

    Financial Year 2015 operational overview • Gold production of 2,422,568 ounces up 1% on FY14 • Copper production of 96,816 tonnes up 12% on FY14 • Group AISC1 of USD 789/oz down 12% on FY14 • Group AISC margin increased to USD 447/oz • Cadia – Ridgeway & Panel Cave 1 both outperformed expectations •

  14. Slide 14: Cadia - continues its ramp-up

    Cadia - continues its ramp-up All-In Sustaining Cost 1 Operational overview per ounce • Gold production 13% higher than FY14 AUD AISC USD AISC • Copper production 22% higher than FY14 • Full year free cash flow of AUD 606m • Panel Cave 2 (PC2) development work recommenced during Q4 2015 FY13 FY14 FY

  15. Slide 15: Lihir – focused on operational improvements

    Lihir – focused on operational improvements All-In Sustaining Cost 1 Operational overview per ounce • FY15 gold production down 5% on 9% lower grade compared to FY14 AUD AISC USD AISC • USD AISC per ounce up 1% compared to FY14 • Key levers remain plant uptime and intensity improvements • Full year

  16. Slide 16: Telfer – Future Options Review progressed

    Telfer – Future Options Review progressed All-In Sustaining Cost1 Operational overview per ounce • Telfer Future Options Review – maximum value by retaining asset AUD AISC USD AISC • Fatality in May 2015 • Fourth quarter FY15 impacted by: – underground mine operations restricted from mid May to Augu

  17. Slide 17: Overview of other operations

    Overview of other operations Bonikro Gosowong Hidden Valley per ounce AUD AISC USD AISC AUD AISC USD AISC AUD AISC USD AISC 1,751 1,799 2,407 2,472 1,4841,369 1,961 AISC1 1,627 1,501 1,4911,331 1,536 992 907 1,132 1,011 742 990 913 897 801 833 652 1,205 1,102 581 664 682 683 625 FY13 FY14 FY14 FY15

  18. Slide 18: Financial Year 2016 production guidance

    Financial Year 2016 production guidance1 Operation Gold Production Operation Copper Production Cadia 650 – 700 koz Cadia Valley ~ 65 kt Lihir 770 – 850 koz Telfer ~ 20 kt Telfer 470 – 520 koz Group 80 – 90 kt Gosowong 300 – 350 koz Operation Silver Production Hidden Valley (50%) 80 – 100 koz Group 2

  19. Slide 19: 2015 Full Year Financial Results

    2015 Full Year Financial Results

  20. Slide 20: 2015 Full Year financial highlights

    2015 Full Year financial highlights Cadia Profitability • FY15 Statutory profit of AUD 546m (FY14 Statutory loss of AUD 2,221m) • Underlying profit up 19% to AUD 515m 1 • EBITDA of AUD 1.7bn • EBITDA margin 39% 1 • Improved AISC margin Cash Flow • Cash flow from operating activities of AUD 1.6bn • F

  21. Slide 21: Disciplined cost management underpins performance

    Disciplined cost management underpins performance All In Sustaining Cost1 margin FY15 Performance overview USD/oz • Financial performance driven by: 1,030 – Edge program 447 433 67 512 484 (192) – increased production of higher margin ounces from Cadia – net effect of lower AUD • Lower production st

  22. Slide 22: Group underlying profit

    Group underlying profit 1 Underlying profit up 19% to AUD 515m compared to corresponding period • Increased contributions from higher margin production at Cadia East • Weakening of the AUD against the USD increased AUD gold and copper price • Site production costs adversely impacted by higher USD de

  23. Slide 23: Increased free cash flow

    Increased free cash flow 1 Free cash flow by site (AUDm) 1,086 606 53 271 154 192 (15) (175) 2 Other Hidden Valley Bonikro Lihir Gosowong Telfer Cadia Group Free cash flow reconciliation FY14 to FY15 552 1,086 (AUDm) 17 105 53 108 118 133 FY14 Production stripping Sustaining capex Major projects Exp

  24. Slide 24: A strong balance sheet remains a priority

    A strong balance sheet remains a priority Strong FY15 result = strengthened Newcrest balance sheet Updated financial policy parameters targeting: Metric Target 30 June 2015 30 June 2014 Leverage ratio Less than 2.0x 2.2x 2.6x (Net debt/EBITDA) Gearing Ratio Less than 25% 29% 34% Credit rating Aim to

  25. Slide 25: Long-dated debt maturity profile

    Long-dated debt maturity profile Maturity profile as at 30 June 20151,2 USDm $1,400 US Private Placement Rule 144A Bonds $1,200 Bilateral Loan Facilities - Drawn Bilateral Loan Facilities - Undrawn $1,000 $800 $600 $400 $200 $0 FY16 FY17 FY18 FY19 FY20 FY21 FY22 FY23 FY24 FY25 FY42 1 Assuming longes

  26. Slide 26: Financial covenants comfortably satisfied

    Financial covenants comfortably satisfied Financial covenants 1 Minimum Total Net EBITDA & Assets 1 Drawn 30 EBITDA Tangible Liabilities of Borrower & Provider of June 2015 Interest Net to Tangible Guarantors as a Average debt funds USDm Coverage Worth Net Worth % of group interest rate 13 Banks 975

  27. Slide 27: Gearing ratio impacts of currency translation

    Gearing ratio impacts of currency translation Debt FX translation & other 30 June reduction Profit after Net 30 June AUDm 2014 and cash Net debt Total equity tax movement 2015 increase Net debt 3,935 (1,070) 896 (174) 3,761 Total equity 7,707 806 546 1,352 9,059 Gearing 33.8% (5.7)% 4.7% (2.1)% (1.4

  28. Slide 28: Significant items (after tax and non-controlling interests)

    Significant items (after tax and non-controlling interests) Item AUDm Driver • Strong operating and financial performance during 2015 • Increased value of future developments per the Telfer Future Options Review Telfer 376 • Favourable impact of AUD currency depreciation against the USD • Partly off

  29. Slide 29: Update on key assets and growth

    Update on key assets and growth

  30. Slide 30: Lihir Pit Optimisation Study – a work in progress

    Lihir Pit Optimisation Study – a work in progress Lihir • Targeting completion of Pre Feasibility Study by end of December 2015 • Pre Feasibility Study is looking to a) optimise the mine plan, and b) review seepage barrier options to ensure: – cash flow maximisation – capital efficiency – risk mitig

  31. Slide 31: Lihir Pit Optimisation Study – orebody profile

    Lihir Pit Optimisation Study – orebody profile 1 km Pacific Ocean Low grade stockpile Minifie stockpile Inner harbour Kapit North low grade stockpile Grade Mineralisation1 Stockpile Kapit >1 g/t Au Kapit stockpile Lienetz Minifie 2-3 g/t Au Low grade >3 g/t Au stockpile Integrated mining sequence Th

  32. Slide 32: Integrated mining sequence possibility being examined

    Integrated mining sequence possibility being examined N Kapit stockpile Stage 1&2a Minifie SP Stage 1&2a Stage 2b Stages 1 1-2g/t & 2a 2-3g/t N >3g/t Stage 3 Resource shell3 Lienetz Minifie Ore reserve design3 Kapit Ore Ore A potential scenario for Lihir being examined: Timing Tonnes to Ex-pit Tonne

  33. Slide 33: Three seepage barrier options being studied (continued)

    Three seepage barrier options being studied (continued) Low grade stockpile Stage 1&2a Existing harbour 1. Coffer Dam Wall Stage 1&2a Coffer Dam waste platform  Potentially not required until Pit wall N Ocean 2030+ 1,2  Capital cost ~USD 625m Engineered Resource shell2  Current reserve case mater

  34. Slide 34: Three seepage barrier options being studied (continued)

    Three seepage barrier options being studied (continued) Low grade stockpile Low grade stockpiles Existing harbour 3. Clay infill using clay waste Stage 1&2a Stage 1&2a waste platform  Compacted clay seepage barrier Ocean Pit wall  Option needs testing Compacted clay infill  Current focus of study

  35. Slide 35: Potential scenario for pit optimisation sequence employing a Near Shore Cut-off Wall

    Potential scenario for pit optimisation sequence employing a Near Shore Cut-off Wall Pit animation NOT TO SCALE. The images are illustrative only. Subject to further study, investment approval, receipt of all necessary permits and approvals and are subject to changes in market and operating conditio

  36. Slide 36: Potential scenario for pit optimisation sequence employing a Near Shore Cut-off Wall

    Potential scenario for pit optimisation sequence employing a Near Shore Cut-off Wall Pit animation NOT TO SCALE. The images are illustrative only. Subject to further study, investment approval, receipt of all necessary permits and approvals and are subject to changes in market and operating conditio

  37. Slide 37: Cadia – Panel Cave 2 seismic event update

    Cadia – Panel Cave 2 seismic event update • Feb 2015 seismic event caused localised damage – in drawbell and extraction drives – required rework and some design tuning • Cave establishment and propagation process requires stress redistribution and release • Seismicity occurs as stress releases and i

  38. Slide 38: Cadia – Panel Cave 2 moving to advanced undercut method

    Cadia – Panel Cave 2 moving to advanced undercut method Post undercut method: Advanced undercut method: • Stress taken by extraction level (EXL) • Stress shadow created on extraction level, providing greater • Faster and more efficient, as material from undercut protection for permanent infrastructu

  39. Slide 39: Telfer Future Options Review

    Telfer Future Options Review • Decision made to retain Telfer • Initial open pit cutbacks approved – West Dome Stage 2 and Main Dome Stage 6/7 – total capex of approximately AUD 46m – extending open pit to December 2017 • Future open pit cutbacks still subject to study – likely to be staged, progres

  40. Slide 40: Telfer orebody

    Telfer orebody Cutbacks FY16-FY18 Cutbacks FY19+ WD Stg 3 MD Stg 6/7 Final MD Stg 6/7 MD Stg 4 WD Stg 2 Interim WD Stg 2 Final Proposed development of Telfer mining operations1 Total material Timing Total material Open pit ore Open pit Open pit Underground ore Underground Underground moved (years) m

  41. Slide 41: Golpu a world class copper-gold deposit

    Golpu a world class copper-gold deposit • World class ore body with Mineral Resources of 9mt of copper and 20moz of gold (100%)1 • Stage one Feasibility Study scheduled to be completed by December 2015 • Stage two Pre-Feasibility Study scheduled to be completed by December 2015 • Permit for advanced

  42. Slide 42: Global search for new ore bodies – FY16 priorities

    Global search for new ore bodies – FY16 priorities Far East Russia Alaska Eastern Europe West Africa Central America PNG Indonesia  Wamum – Search for new discoveries  Portfolio rebuild  MEJV target generation Côte D’Ivoire Latin America SW Pacific CDI Fiji  Rebuild portfolio - property generati

  43. Slide 43: Seeking value creation through exploration and project entry

    Seeking value creation through exploration and project entry Greenfields – restocking and advancing the portfolio • Mungana JV (Queensland, Australia) – Centred on a metal rich district – targeting Gold-Copper porphyry related mineralisation • Southern Coromandel JV (New Zealand) – located in highly

  44. Slide 44: Summary

    Summary Good financial results 1 2 • All-In Sustaining Cost of USD 789/oz • USD net debt reduction of USD 819m • Free cash flow of AUD 1,086m Clarity on strategy • Lihir Pit Optimisation Study – potential for lower development costs • Telfer Future Options Review – asset retained and initial cutback

  45. Slide 45: Questions & Answers

    7p) , a) = n Cc < fo) n Cc oO — 7p) rab) =) CG

  46. Slide 46: Appendices

    Appendices

  47. Slide 47: Underlying Profit reconciliation

    “Underlying Profit” reconciliation 30 June 2015 30 June 2014 12 months ended AUDm AUDm Statutory Profit 546 (2,221) Research and development tax claim amendment - 120 Asset impairment (reversal)/ Inventory write downs1 (12) 2,499 Restructure costs (after tax) - 34 Gain on disposal of associate (19)

  48. Slide 48: Financial Year 2016 production guidance

    Financial Year 2016 production guidance1 Operation Gold Production Operation Copper Production Cadia 650 – 700 koz Cadia Valley ~ 65 kt Lihir 770 – 850 koz Telfer ~ 20 kt Telfer 470 – 520 koz Group 80 – 90 kt Gosowong 300 – 350 koz Operation Silver Production Hidden Valley (50%) 80 – 100 koz Group 2

  49. Slide 49: 2016 cost and capital guidance

    2016 cost and capital guidance1 Gosowong Hidden Bonikro Corporate Cadia Lihir Telfer (100%) Valley (50%) (100%) & Other Group AUDm AUDm AUDm AUDm AUDm AUDm AUDm AUDm 2,3 All-In Sustaining Cost 240-290 1,050-1,150 680-730 290-330 120-140 190-210 90-100 2,650-2,950 Capital expenditure • Production str

  50. Slide 50: FY16 Foreign Exchange sensitivities and oil hedges

    FY16 Foreign Exchange sensitivities1 and oil hedges Foreign Exchange Full Year Site Parameter Movement EBIT Impact Lihir USD/PGK + PGK 0.10 USD 12 m Hidden Valley USD/PGK + PGK 0.10 USD 2 m Gosowong USD/IDR + IDR 1,000 USD 5 m Group AUD/USD - AUD 0.01 AUD 35 m Oil hedges entered into for FY16 for ap

  51. Slide 51: Long-term metal assumptions used for Reserves and Resources estimates

    Long-term metal assumptions used for Reserves and Resources estimates 1 Long Term Metal Assumptions Newcrest Managed MMJV Managed Mineral Resources Estimates Gold Price USD 1,350/oz USD 1,400/oz Copper Price USD 3.40/lb USD 3.50/lb Silver Price USD 23/oz USD 25/oz Ore Reserves Estimates Gold Price U

  52. Slide 52: Peer comparison reserves and reserve life

    Peer comparison reserves and reserve life Reserves - Gold (Moz)1,2 Reserve Life - Gold (Years)1,2 90 31 86 75 23 54 50 48 17 16 16 15 34 13 1 Reserves reflect proven and probable gold reserves (contained metal) as at 31 December 2014 for all companies, obtained from company statements and adjusted t

  53. Slide 53: Lihir – Operating Strategy

    Lihir – Operating Strategy • Implemented December 2014 • Actively manage autoclave throughput based on sulphur content of feed to maximise gold production • Extent of oxidation is optimised/reduced with limited impact on gold recovery – Microcrystalline pyrite - more reactive with higher gold conten