Slide 1: Nyngan Solar Plant Community Consultative Committee
Nyngan Solar 1 Plant Community Consultative Committee 4 February 2015
Slide 2: Agenda
2 Agenda 1 Welcome February CCC 2 Review previous minutes 3 Overview of project status (AGL and First Solar) 4 Employment / local spending / information sharing / community matters 5 Project planning 6 Construction community fund 7 Next meeting and close > Nyngan Solar Project > AGL Energy > 4 Febru
Slide 3: Review of previous minutes (all)
3 Review of previous minutes (all) > Presentation title > Author > Date (Verdana 10pt)
Slide 4: Review actions from previous meeting
4 2. Review actions from previous meeting Action item CCC Status Who meeting 1 AGL to progress the shopfront display. Waiting on April 2014 Open HO Bogan Shire Council to progress shop front letting agreements. 2 AGL to work in consultation with the community April 2014 Open HO/ about ways to revege
Slide 5: Review actions from previous meeting
5 2. Review actions from previous meeting Action item CCC Status Who meeting 6 AGL to coordinate with First Solar the CCC site October Closed HO / BS visit on 6 December 2014. 2014 7 AGL to progress the community open day at October Open HO / the project’s completion. 2014 AGM 8 AGL to provide an up
Slide 6: Confirmation of December 2015 minutes
6 2. Confirmation of December 2015 minutes › Any comments on the December minutes? › Accept as accurate record of meeting? > Nyngan Solar Project > AGL Energy > 4 February2015
Slide 7: Overview of project status
7 Overview of project status •Adam Mackett (AGL) •Bruce Smith (First Solar) > Presentation title > Author > Date (Verdana 10pt)
Slide 8: AGL overview of project status
8 3. AGL overview of project status Current status on the Nyngan Solar Plant: › Electrical work on site progressing › Work finalised for generation accreditation » Australian Energy Market Operator » Clean Energy Regulatory Authority › Project on track for completion in June 2015 > Nyngan Solar Proj
Slide 9: AGL overview of project status
9 3. AGL overview of project status Nyngan Solar Plant connection: › Connection work, still working through practical completion minor details: » 132kV transmission line (Essential Energy) » 132kV Switchyard (Essential Energy) » 132kV Substation (AGL) › First generation from Block 1 » Coordination b
Slide 10: AGL overview of project status
10 3. AGL overview of project status 132kV transmission line 132kV transmission line energisation (EE asset) energisation (EE asset) > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 11: First Solar overview of project status
11 3. First Solar overview of project status Nyngan Solar Plant progress › 100% of the 140,000 steel posts have been installed › 100% of the 140,000 tilt brackets have been installed › 63,000 tables installed with 5,000 remaining › 1,230,000 of the 1,350,000 panels have been delivered › 670,000 pane
Slide 12: First Solar overview of project status
12 3. First Solar overview of project status Last power conversion station Recent wet weather install (January 2015) > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 13: First Solar overview of project status
13 3. First Solar overview of project status 33kV AC feeder cables in Section 3 Module installation in Section 1 > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 14: First Solar overview of project status
14 3. First Solar overview of project status > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 15: Employment, Local spending, Information sharing, Community matters
15 Employment Local spending Information sharing Community matters •Bruce Smith (First Solar) > Presentation title > Author > Date (Verdana 10pt)
Slide 16: Employment update
16 4. Employment update Project labour Headcount reducing due to project nearing completion Currently have 180 people employed on the project Nuts and Bolts Workshop at CWA hall All assembly work was completed by the workshop staff in January > Nyngan Solar Plant > AGL Energy > 4 February 2015
Slide 17: Local spending
17 4. Local spending Monthly spending in Nyngan FKG - camp and dining facilities $155,000 First Solar - local businesses $ 33,000 WBHO – services and supplies $ 70,000 First Solar – accommodation $156,000 Monthly spend $524,000 > Nyngan Solar Plant > AGL Energy > 4 February 2015
Slide 18: Information sharing, community matters
18 4. Information sharing, community matters Site visits CCC and friends: December 2014 Regional Emergency Response Committee February 2015 ARENA representatives: February and March 2015 Bogan Shire Council: March / April 2015 (TBC) > Nyngan Solar Plant > AGL Energy > 4 February 2015
Slide 19: First Solar project contact details
19 4. First Solar project contact details Bruce Smith Michael Law Project Manager Construction Manager Mob: 0428 199 241 Mob: 0417 369 921 E: bruce.smith@firstsolar.com E: michael.law@firstsolar.com > Nyngan Solar Plant > AGL Energy > 4 February 2015
Slide 20: Project planning
20 Project planning •Adam Mackett / Helena Orel AGL > Presentation title > Author > Date (Verdana 10pt)
Slide 21: Project planning
21 5. Project planning Community planting Landscaping work timing around second quarter 2015 Community open day Proposed September 2015 Nyngan Ag Expo AGL principle sponsor for next three years Solar plant tourism during operation Ongoing discussion about opportunities Community feedback Any comment
Slide 22: Landscape plan
22 5. Landscape plan > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 23: Landscaping work
23 5. Landscaping work Timing: › Landscaping timing – Q2 2015 Groups to involve: › Nyngan Local Aboriginal Land Council › Local Land Services Central West › Community Hub › Direct neighbours › Local schools: » Nyngan Public school » Nyngan High School » St Josephs School » Girilambone Public School
Slide 24: Construction Community fund
24 Construction Community fund •Helena Orel (AGL)
Slide 25: Community fund
25 6. Community fund Next round of funding open for applications Advertise in April 2015 (four weeks) Cheque handover around May / June > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 26: Other business, next meeting and close
26 Other business, next meeting and close
Slide 27: Any other business
27 7. Any other business › Questions? > Nyngan Solar Project > AGL Energy > 4 February 2015
Slide 28: Next meeting
28 7. Next meeting › Agenda – is there anything that you would like to discuss? › Next meeting: Wednesday 1 April › Time: 6pm – 8pm › Venue: CWA Hall > Nyngan Solar Project > AGL Energy > 4 February 2015