    Disclaimer This presentation (Presentation) has been prepared by and is the sole responsibility of European Lithium Limited (the Company). It is not a disclosure document and should not be considered as an offer or invitation to subscribe for, or purchase any securities in the Company or as an induc

  3. Slide 3: Capital Structure

    Capital Structure Shares on issue = 361.8 million Cape Lambert Resources Ltd - 13.57% Free float1 = 156 million Exchange Minerals Ltd - 8.53% Unlisted options2 = 208 million Major Shareholders Company owns 100% of European Lithium AT (Investments) Ltd, a BVI company that in turn owns 100% of an Aust

  4. Slide 4: Investment Highlights

    Investment Highlights Central European project Experienced team EU Net importer Robust lithium market ● 100% owned lithium project in ● Directors have considerable ● Apart from small Iberian ● Lithium market has grown from Austria experience in resource project production for local ~71kt LCE in 2002

  5. Slide 5: Board of Directors

    Board of Directors Steve Kesler Tony Sage Paul Lloyd Malcolm Day CEO Non-executive Chairman Non-executive Director Non-executive Director ● Experienced mining ● Executive Chairman of ● Over 25 years of ● Experienced Surveyor executive with over 38 ASX listed Cape commercial experience and Civil Engi

  6. Slide 6: Main Sources of Lithium

    Main Sources of Lithium PROCESSING OPEX CAPEX OTHER Hard rock Mining, crushing, concentration, Typical operating Typically lower Less impurity roasting, leaching and crystallisation costs higher capex/t LCE than variation than to lithium carbonate brine projects brines which is important for battery

  7. Slide 7: Wolfsberg Lithium Project

    Wolfsberg Lithium Project ● Located 270km SW of Vienna, Austria ● The 5 year term of the original exploration ● Good local infrastructure and sources of energy licences was extended by the mining authority nearby to 31 December 2019 and is renewable. The mining licence is held in perpetuity subject

  8. Slide 8: Project History

    Project History 1981 1988 1991 Discovered by Minerex, an Austrian Austrian Government decided BBU was closed by the Austrian government company. Following not to develop the project and government and the Project was sold extensive exploration, technical and Minerex was closed. The Project to Kärntn

  9. Slide 9: Geology

    Geology ● Substantial exploration and development work by ● A JORC Code (2004) compliant measured and previous owners include: indicated resource was declared in 2012. However, because certain primary data and ● 17,000m of drilling / 1,400m of decline, drives and QA/QC protocols were not available f

  10. Slide 10: Project Topography

    Project Topography Lithium Deposit Wolfsberg Area Of Investigation Graphic: A. Pamsl Brandhöhe 1866m 5 1800m ZONE 2 ZONE 1 Adit (1574m asl) Amphibolite Micaschist Pegmatites (proven/estimated) Source: Company, Mine-it representation 9

  11. Slide 11: Project Geology

    Project Geology Section through deposit Mineworkings – plan view Source: The spodumene depost at “Weinebene” Koralpe, Austria • Source: Company, prepared from Minerex data by Dr. Göd. by Dr.Göd, Mineralium Deposita 24, 270-278 (1989). • 10

  12. Slide 12: Geology of Wolfsberg - plan

    Geology of Wolfsberg - plan Source: The spodumene depost at “Weinebene” Koralpe, Austria by Dr. Göd, Mineralium Deposita 24, 270-278 (1989). • 11

  13. Slide 13: Metallurgy

    Metallurgy ● Metallurgical test work in 1982-7 at North Carolina State University ● PFS in 1987 ● Mining licence awarded in 2011 to then owners KMI ● Scoping study by Global Strategic Metals in 2011 ● Two 500 tonne bulk mine samples of each ore type at end 2013 ● Spodumene (lithium) contained in peg

  14. Slide 14: Development Strategy

    Development Strategy ● Verify the Minerex data and upgrade the resource compliant to JORC Code (2012) “opportunities for fast ● Increase resource by drilling down dip track concentrate ● Establish a resource in Zone 2 production” ● Establish the most suitable mining method and maximum production rat

  15. Slide 15: Consultants for Work Programme

    Consultants for Work Programme ● Geology Adviser - Dr Richard Göd (ex Chief Geologist Minerex) (Austria) ● Exploration Management – Technisches Büro für Geologie (Austria) ● Drilling contractor (underground) – Swietelsky (Austria) ● Drilling contractor (surface) – VA Erzberg (Austria) ● Competent pe

  16. Slide 16: Estimated Development Timeline

    Estimated Development Timeline Work Programme Q3 16 Q4 16 Q1 17 Q2 17 H2 17 H1 18 H2 18 2019 2020 Re-listing on ASX PFS DFS Baseline/EIS/Permitting Construction Operations Fast track DMS 15

  17. Slide 17: Material Lithium Projects in Europe

    Material Lithium Projects in Europe 1. Keliber • Finland • In PFS • No guidance on first production 2. Avalonia Lithium (Intl. Lithium & Jiangxi Ganfeng) • Ireland • Exploration 1 • No resource declared 3. SMP • Portugal • For local glass/ceramics 4. European Lithium 2 • Austria • PFS • Target produ

  18. Slide 18: Recent Industry News

    Recent Industry News September European Lithium Limited readmitted to ASX (code: EUR). Capital raising to fund pre-feasibility 2016 study successfully completed. August Sichaan Tianqui lithium hydroxide plant 2016 Tianqui announces plans to build a 24,000tpa lithium hydroxide plant costing A$300m in

  19. Slide 19: Project Photographs

    Project Photographs EUROPEAN 18

  20. Slide 20: Appendices

    Wk + EUROPEAN LITHIUM Appendices

  21. Slide 21: Lithium Applications

    Lithium Applications CURRENT APPLICATIONS NEW MARKETS CHEMICAL TECHNICAL Electric vehicles Batteries Glass Lubricants Ceramics Fixed energy storage with renewables Air Treatment Aerospace Aluminium smelting Li-Al alloys for aircraft Steel and Iron Pharmaceuticals castings 20

  22. Slide 22: LCE in Batteries

    LCE in Batteries SMART PHONE LAPTOP TABLET TOYOTA PRIUS TESLA ROADSTER LONDON BUS 2-3g/battery 30-40g/battery 20-30g/battery 3.6kg/battery 40kg/battery 200kg/battery ● Lithium ion has captured nearly 100% of consumer electronics market ● Tesla aims to build its lithium ion battery ‘gigafactory’ read

  23. Slide 23: World Market - rechargeable lithium batteries

    World Market - rechargeable lithium batteries World Market for rechargeable lithium batteries by end-use 2002-2017 (MWh) Source: Roskill Lithium Market Outlook to 2017 12th Edition 2013 (“Roskill 2013”) 22

  24. Slide 24: Lithium Price

    Lithium Price High forecast Base forecast Historic technical grade lithium price (CIF excl. China) Source: Roskill 2013 ● Pricing off-market ● Pricing determined by product and specification for each consumer ● Pricing typically in LCE ● Battery grade lithium is highest purity and most expensive ● T

  25. Slide 25: Demand

    Demand World Historical and Forecast consumption of lithium by end-use 2002-2017 (t LCE) Optimistic Source: Roskill 2013 ● Majority of lithium continues to be used for lower value industrial applications (glass, ceramics etc.) ● Recent growth largely from rechargeable battery market (e.g. mobile pho

  26. Slide 26: Demand Outlook

    Demand Outlook Source: Roskill 2013 ● Market has grown from ~60,000 tonnes LCE in 2000 to 150,000 tonnes LCE in 2012 and 200,000 tonnes LCE in 2015 ● Growth base rate 9.7% with high of 15.7% if rapid take up of EV’s ● Entire new markets are still at embryonic phase (e.g. fixed energy storage with re

  27. Slide 27: Lithium Supply

    Lithium Supply Production of lithium by country 2000-2012 (LCE) Source: Roskill 2013 ● Lithium supply totalled 168,000 LCE in 2012 ● Global supply is dominated by the “big four” that supply ~82% (Talison Lithium, SQM, Rockwood and FMC) ● Talison (now owned by Tianqui and Albermarle) is now largest s