  1. Slide 1: Developing Brazil's Next Copper Mine

    Sy Lara \, exploration Developing Brazil’s Next Copper Mine October 2025 TSXV: LRA

  2. Slide 2: Forward-Looking Statement-1

    Forward-Looking Statement-1 Except for statements of historical fact relating to the Company, certain information contained herein constitutes forward-looking statements. Forward-looking statements are frequently characterized by words such as “plan”, “expect”, “project”, “intend”, “believe”, “antic

  3. Slide 3: Forward-Looking Statement-2

    Forward-Looking Statement-2 Note-3. The . 43.101 Planalto PEA News release Lara Reports Results of Preliminary Economic Assessment for its Planalto Copper-Gold Project, 21/10/2025. contains Non IFRS Financial Performance Measures “All-in Sustaining Costs”, “Total Site Costs”, “Total Adjusted Operati

  4. Slide 4: Flagship Project - Planalto

    Liberdade Itaituba — e Fofoca South —@ ;— Celesta Fertec Alli Allpa P o Kenita ——e ‘aa! s & Planalto Picha Bifox 4d Copper-Gold Mine Development in Brazil Mining-Friendly Jurisdiction Well-established mining district with supportive local authorities. Proven mine-permitting record New mines- Ero Cop

  5. Slide 5: Why Para, Brazil?

    Why Para, Brazil? Planalto * Agriculture and mining dominate the local economy. * Politically supportive of mining, with the revenues shared locally (State, Municipality and Landowners). * Clear and proven permitting process with state level project approvals. ° Secretariat of Environment and Sustai

  6. Slide 6: Carajas Infrastructure

    Carajas Infrastructure BRAZIL * World class mining district, home to Vale’s main iron ore operations, in addition to copper, gold, nickel and manganese production. Belém Port * Vale, BHP and Ero Copper operate the four existing { [esi or} Ane ~ z tox 4 _A| Baracarena Port significant copper mines, b

  7. Slide 7: Project Location

    Project Location coum PS Serra Norte (Fe) . 36% Fe (Resources) oOo >) CA Celesta BRAZIC 2 (cuau) / Curionépolis L— © carsjés Parauapebas ‘Substation Airport 6 Neo Antas North . — Highway BRAZIL (cuAu) Ne -@- High Tension Power line \S @ Mine / Deposit C~ Planalto Deposit 2 (cuau) $11D (Fe) 6% Fe (Re

  8. Slide 8: Deposits and Targets Map

    Planalto Deposits and Targets Map =» / © Drillholes 28,273m in 92 DH HE Cu in soil (>284ppm) DIVISA PLANALTO [J Licenses total 4,211.87 Ha TARGET a me DEPOSIT [) Targets/Deposits ) “> Power line = z ~, — Highway r : ‘ Gravel road HIGHWAY WwW TARGET — HIGHWAY E ~~ = TARGET @ Planalto Deposit tas au)

  9. Slide 9: PEA Pit

    Planalto PEA Pit (Stable design) i — [1.5,ceEILinc) ‘Sy Lara exploration LARA EXPLORATION | TSXV: LRA PLANALTO PRESENTATION \,

  10. Slide 10: Long Section

    Planalto Long Section Section 636986 E hia (0.15,0.2) (0.2,0.25) (0.25,0.3) 304 406) ps1 100m “55 Long section S-N looking W, showing Block Model cells >0.16% CuEq| ‘Sy Lara exploration 10 LARA EXPLORATION | TSXV: LRA PLANALTO PRESENTATION &

  11. Slide 11: Mining

    Planalto Mining SIMPLE MINING “t Pre-strip - 16.2 Mt. RoM + Silica Cap - 5m benches, 40t trucks, 3.7 m3 excavators. Waste - 10m bench, 100t trucks, 15 m3 excavators. Dilution - 7% dilution (0.16% CuEq), 2% mining loss. Low Grade Stockpile - 13mt (0.18-0.19% CuEq), processed at end. Strip Ratio - 2es

  12. Slide 12: Metallurgy

    Planalto Metallurgy SIMPLE PROCESSING “2 + Crush - 8 Mtpa, Hard Ore 18.5-20.0 kWhi/t. + Grind — SAG Mill + 2x Ball Mill (P80 of 75 um). + Float. - Chalcopyrite + Gold. Regrind section. + Pyrite - Option to recover pyrite to separate stream. + Recovery - Cu- 90.9% Au 51.1%. QUALITY CHALCOPYRITE CONCE

  13. Slide 13: Process Flowsheet

    Planalto Process Flowsheet ROM «Uh As Needed- Pyrite Cleaner | Scavenger cleaner-scavenger | Fidat x2 Tiries Grind-SAG Grind-Ball Mills x2 SIMPLE FLOWSHEET + Industry Standard - Recovering only chalcopyrite, diverting pyrite to tails. + OEM Equipment - Major equipment specification and design. Metso

  14. Slide 14: PEA: General Layout

    Planalto PEA: General Layout \ We || iting power ines 2308 LE Proposed 1380 power ne (PEA option 2) DS00KV, Licenses Mining infrastructure — Existing power tines ==" Proposed power line a) * ‘aungoum > ec) INFRASTRUCTURE BENEFITS 4km from highway and power lines Flat-lying, with year-round access 10

  15. Slide 15: Tailings

    Planalto Tailings TAILINGS STORAGE FACILITY OPTIONS *2 + Studies - 2x studies, various options. a ‘South Central Discharge ‘Storage Volume Total | 91.1 Nim’ Paddock Storage 645m? Volume (Thickened ‘Slurry Talings) ETD Storage Volume | 26.6 Nim? (Paste Thickened ‘alings) Embankment Volume | 13.5 Nim?

  16. Slide 16: Production

    Planalto Production 40 45 0.40% 0.43% 0.42% LoM: Cu- 560 kt (1.2B Ib) * Au- 111 koz 30 120kt pa concentrate 28% Process LG stockpile 2 25 = s 45% 0.46% 0.50% 0.46% | a6 3696 042% 0 aise 5 Yr.1-6: Cu 36 ktpa (79M Ib) S 2% 0 E 3 g Au- 7.2 koz pa = os0x C2) 0.46% 0.49% £ 15 Et Concentrate trucked 680 k

  17. Slide 17: CAPEX & OPEX

    Planalto CAPEX & OPEX CALara OPEX *2 Description Unit Cost CAPEX 72 Initial Sustaining| Total Mining USS/t ex-pit 3.04 (uss) (US$) (uss) Mining USS/t processed 8.34 Mining Pre-Strip 28.5 = 28.5 Processing USS/t processed 7.66 Processing Plant 238.5 85.9 324.4 Tailings USS$/t processed 0.13 Tailing M

  18. Slide 18: PEA Financial

    Planalto PEA Financia *2- Planalto PEA , Lara news release 21/10/2025 *3 Non IFRS financial performance measures See note 3 18 ORATION | TSXV: LRA PLANALTO PRESEN 2) Key Unit Costs *? Discount Unit NPV 8% Pos Tax Sensitivity Total site costs*? 2.14 Rate to Discount Rate *? Government royalties USS/I

  19. Slide 19: Recent Milestones & Path to Production

    19 Recent Milestones & Path to Production Acquire Fi Construction Atlantica Submit | File mining | concession — : 4G Mining Advancement _ extension , Geass concession __ LI Submission Permitting Initial Production Hire CLAM for Finish EIA/RIMA and EIA/RIMA Mining Application start prep LP Concession

  20. Slide 20: Exploration Opportunities

    Exploration Opportunities - DIVISA PLANALTO " Oo /¢ TARGET oa ) we DEPOSIT | MAIN PIT HOMESTEAD HIGHWAY W aa! SODRE TARGET TARGET — HIGHWAY E TARGET 3 _|siuica Po DEPOSIT VILA. PLANALTO In and Near Pit Exploration + Measured and Indicated Resources — Infill drilling to increase resource confidence.

  21. Slide 21: Outstanding Development Attributes

    Outstanding Development Attributes This project has all the characteristics necessary for successful development Located in the Carajas, a well-established mining district, building new mines. Supportive government that is pro foreign investment/mining. Permitting track record Favourable fiscal and

  22. Slide 22: Shareholder Capital

    Shareholder Capital Common Shares Management and Directors 19.2% Share Price (Close Oct 20, 2025) c$ 2.59 29.8% Cash (2 2025 filing) C$M 3.80 Shares O/S M 50.50 Options M 2.70 Market Cap C$M 130.80 Adrian Day Asset. Management 19.5% Family Offices 22.7% EuroPacific Gold Fund 8.9% and Directors own 1

  23. Slide 23: Management Team

    Management Team MILES THOMPSON (CHAIRMAN) Lara Exploration founder with +30 years in global mineral exploration. Co-Founder and Chairman of Reservoir Minerals. Prior to Lara, was Manager Business Development for Gold Fields Exploration, working on acquisitions and JVs in South America, E. Europe, th

  24. Slide 24: Cukaru Peki - Discovery in Serbia

    Cukaru Peki Discovery in Serbia << <<< CO-FOUNDED RESERVOIR MINERALS. Simon, Miles, and Chris co-founded Reservoir Minerals (TSXV: RMC), listed January 2011 at C$0.65 per share with a ~C$13M Market Cap. COPPER-GOLD DISCOVERY MADE The Cukaru Peki copper-gold discovery made with JV funding from Freepo

  25. Slide 25: Global Copper Discoveries

    Global Copper Discoveries Copper Discoveries & Exploration Budgets (1990-2023) Lara Team Discovery & Liberdade Lara Team Discovery 180 5,000 & Cukaru Peki March 2013 ; 197m @ 0.72% CuEq soo Lara Team Discovery 160 July 2012 : mz 266m @ 1.23% CuEq > Celesta 140 Production 2021 4,000 “hume 2015 56m @

  26. Slide 26: Largest Copper Discoveries, 2014 - 2023

    10 largest Copper Discoveries, 2014 - 2023 Discovery Year” Discovered by Country Sha past production (metre tons) Kamoa-Kakula (Kakula) 2014 Ivanhoe Mines DRC 19.30.47 (ls Western Foreland 2017 Ivanhoe Mines DRC 4,959,000 J) Encierro 2014 Antofagasta PLC Chile 3,400,000 Cachorro 2015 Antofagasta PLC

  27. Slide 27: Copper

    Copper Record Size Structural Deficits Fast Approaching kt 36000 === Refined copper supply 34000 === Copper demand 30000 SST er Projected deficit 28000 ©,©' in 2035: 9.9mt! 26000 a iin Potential for Planalto to Deliver Feasibility, Permitting, Financing > into Projected Copper Deficit 22000 Definiti

  28. Slide 28: Resource Estimate

    Planalto Resource Estimate Main Indicated 47.7 0.53 0.06 0.56 253 557 92 Mineralization —_|nferred 77.7 0.51 0.06 0.54 396 874 150 Host Rock | Inferred 76.3 02 0.03 0.22 153 336 74 Mineralization rota jinicstea | 47.70.68] 0.06] ose] 289] 587/92 jinfered | 1540) 0.36) 0.04) one] sao) 1210) 223.5) No

  29. Slide 29: For more information please contact

    Sy Lara \, exploration —Tsxv: LRA For more information please contact: Christopher Macintyre Vice President, Corporate Development Suite 414, 100 Richmond Street West Toronto, Ontario M5H 3K6, Canada Phone: +1 416-703-0010 Fax: +1 416-964-0823 Or visit us online at: www.laraexploration.com

  30. Slide 30: Level plan view

    Leve 80 120m Below Surface Planalto 4) 200m Plan view, showing Block Model cells >0.16% CuEq ‘Sy Lara exploration 30 LARA EXPLORATION | TSXV: LRA PLANALTO PRESENTATION &