Slide 1: Annual General Meeting
GOLD CORP Annual General Meeting June 21st 2018
Slide 2: Forward Looking Statements
FORWARD LOOKING STATEMENTS This presentation contains forward-looking information under Canadian securities legislation. Forward-looking information includes, but is not limited to, statements with respect to completion of any financings; Harte Gold’s development potential and timetable of its opera
Slide 3: Company Snapshot
COMPANY SNAPSHOT CORPORATE STRUCTURE INSTITUTIONAL SUPPORT Headquartered: Analyst Following: Toronto, Ontario, Canada Symbol: HRT: TSX H4O: FRANKFURT HRTFF: OTC Major Shareholders1: 19.9% Market Cap: 7.2% C$210 million (C$0.37 June 19th) 2.1% 0.9% Shares Outstanding: 575 million (Basic) Debt Financi
Slide 4: Experienced Management Team
EXPERIENCED MANAGEMENT TEAM Stephen G. Roman Roger J. Emdin Rein Lehari George Flach Chairman, President & CEO; Vice President, Operations; Chief Financial Officer; Independent Consultant; BA P.Eng. CPA, CA B.Sc. P.Geo. 35+ years 30+ years 30+ years 30+ years Discovered Gold Eagle, Senior manage
Slide 5: Experienced Management Team (Cont'd)
EXPERIENCED MANAGEMENT TEAM (Cont’d) Tim Campbell Shawn Howarth Steve Ball Bob Kusins Vice President & Secretary; Vice President, Corporate General Manager, Sugar Resource Geologist; BA Hons. Development; MBA, B.Eng. Zone Mine; P.Eng. P.Geo. 20+ years 15+ years 30+ years 35+ years Government & Per
Slide 6: Milestones Achieved During 2018
MILESTONES ACHIEVED DURING 2018 HARTE GOLD HAS DELIVERED ON ALL TARGETS TO-DATE Resource update: tripled resource Comprehensive debt financing package for up to US$70 million PEA: $425 million pre-tax NPV5% at US$1,350/oz, 60% pre-tax IRR1 IBA signed with Pic Mobert First Nation (PMFN) Fin
Slide 7: Fully Funded to Production
FULLY FUNDED TO PRODUCTION DEBT FINANCING PACKAGE WITH SPROTT AND APPIAN Benefits Flexible principal and interest schedule supports ramp-up of operations Sufficient liquidity to protect against unforeseen downturn in commodity prices No equity commitment No hedging, no cashflow sweeps and no deb
Slide 8: Phased Mine Plan Increasing to 1,400 tpd
PHASED MINE PLAN INCREASING TO 1,400 TPD PROVIDES EARLY CASH FLOW AND LONGER TERM GROWTH Today Phase 1: 540 tpd Low risk ramp-up to commercial production (2018 - 2019) H2 2018 H2 2019 Phase 2: Existing surface and underground mining infrastructure is sufficient to support 800 tpd increased throu
Slide 9: Production Profile to +100,000 Oz/Year
PRODUCTION PROFILE TO +100,000 Oz/Year SCALABLE MINE PLAN DESIGNED TO MATCH UNDERGROUND DEVELOPMENT Throughput and Grade 600 10.0 Throughput (ktpa) Grade (g/t Au) 450 7.5 300 5.0 150 2.5 0.0 2018 2020 2022 2024 2026 2028 Phase 1 & 2 (800 tpd) Phase 3 (1,400 tpd) Diluted Head Grade Production Forecas
Slide 10: First Quartile Cash Cost Producer
FIRST QUARTILE CASH COST PRODUCER AISC CASH COST OF US$708/OZ OVER LIFE OF MINE AISC Curve Illustrating Sugar Zone Vs. Other Selected High Grade Canadian Underground Mines Eagle River, Wesdome Sugar Zone, Harte Gold* Macassa, Kirkland Lake $3,000 Island Gold, Alamos Hope Bay, TMAC Hemlo, Barrick $2,
Slide 11: NPV and IRR Summary
NPV AND IRR SUMMARY Gold Price Sensitivities Unit US$1,150/oz PEA Pricing US$1,350/oz Macro Parameters Gold Price US$/oz $1,150 $1,250 $1,350 Exchange Rate CAD:USD 0.80 0.80 0.80 Pre-Tax NPV and IRR NPV @ 5% M C$ $263 $344 $425 IRR % 40% 50% 60% Post-Tax NPV and IRR NPV @ 5% M C$ $189 $244 $299 IRR
Slide 12: Opportunities to Enhance Value
OPPORTUNITIES TO ENHANCE VALUE Increase drill density to improve overall grade Improve head grade Infill drilling to date has returned very positive results +500,000 ounces currently not factored into mine plan Add resources to mine plan Incorporate results from Wolf Zone and Footwall Zo
Slide 13: Opportunities to Enhance Value: Near Mine Drilling Areas
OPPORTUNITIES TO ENHANCE VALUE AREAS TARGETED FOR NEAR MINE DRILLING “LOW HANGING FRUIT” Sugar Zone Middle Zone 2 Indicated Resources Sugar Zone Inferred Resources Footwall 2 Middle 3 Zone Footwall Middle 1 Zone Infill Sugar Zone Infill 13 TSX: HRT
Slide 14: Sugar Zone Deep Infill Results
SUGAR ZONE DEEP INFILL RESULTS POSITIVE DRILLING TO IMPROVE RESOURCE GRADE AND ADD OUNCES TO THE MINE PLAN 14 TSX: HRT
Slide 15: Footwall Zone Discovery
FOOTWALL ZONE DISCOVERY ENTIRELY NEW ZONE OF MINERALIZATION THAT COULD POTENTIALLY ADD SIGNIFICANT OUNCES SE Sugar Zone Deposit Middle Zone Wolf Zone NW 0m FW 10.75pt Au/1.58m FW 6.42gpt Au gpt 100 FW 10.98gpt Au/4.23m 250 m 10 Au/1.43m FW 5.41gpt Au/7.66m 500 m 3 0 750 m FW 38.06gpt Au/2.29m Curren
Slide 16: Middle Zone Infill Results
MIDDLE ZONE INFILL RESULTS CONTINUED GROWTH OF HIGH GRADE AREA 16 TSX: HRT
Slide 17: Wolf Zone
WOLF ZONE NEW AREA OF MINERALIZATION, CONTINUES TO EXPAND 17 TSX: HRT
Slide 18: Enhancing Project Value
ENHANCING PROJECT VALUE SEVERAL OPPORTUNTIIES NOT CAPTURED IN THE PEA $750 mining dilution, lower mineable mining costs resource by ? 534,000 ounces Pre-Tax NPV5% ($ Millions) $600 ? head grade: 7.0 – 8.0 g/t ? $450 $425 ? ? $344 $300 $150 US$1,250/oz US$1,350/oz Improve Head Upgrade Mine Plan
Slide 19: Near-Mine and Property-Wide Exploration
NEAR-MINE AND PROPERTY-WIDE EXPLORATION Increased overall land position to 83,850 hectares Wolf Zone 35 Km strike length to be Fisher Zone Middle Zone explored Eagle Zone ` Near-mine targets Sugar, Sugar Zone Middle and Wolf Zones EM Targets Several regional exploration Lynx Zone targets identified
Slide 20: Construction and Permitting Update
CONSTRUCTION AND PERMITTING UPDATE Construction Update Mill construction substantially complete Grid connection scheduled for end of July Underground development to support commercial production is underway Permitting IBA signed with proximal First Nation Band Crown consultation nearing co
Slide 21: Key Takeaways
KEY TAKEAWAYS Fully funded to production Scalable mine plan: 1,400 tpd, +100,000 ounces of annual production Simple mine design, well understood orebody. 100,000 tonnes mined to-date AISC US$708/oz – first quartile cash cost producer $425 million pre-tax NPV5% at US$1,350/oz gold Several