  1. Slide 1: Dow's Scope of Work: Building on Your Ideas

    Dow’s Scope of Work: Building on Your Ideas September 22 & 25, 2003 1

  2. Slide 2: Agenda

    Agenda • Introduction • Scope of Work • Interim Actions - Garret Geer • Remedial Investigation - Ben Baker • Ecology Research Update - Prof. Matt Zwiernik • Timeline and Next Steps 2 SRO 9/22/03

  3. Slide 3: Scope of Work - Overview

    Scope of Work - Overview • High-level outline of full RI work plan and immediate interim actions • No standard format; used EPA model • Work in progress - discussion document 3 SRO 9/22/03

  4. Slide 4: Scope of Work - Feedback

    Scope of Work - Feedback • Meetings with MDEQ • MDEQ CAP • Dow CAP • Meetings with Residents & Officials • Public Meetings 4 SRO 9/22/03

  5. Slide 5: Varied Comments

    Varied Comments: Do more vs. don ’t do more soil sampling Dredge Tittabawassee River d u s t u c e Red Reduce exposure in parks Do vs. don’t do health evaluations More information 5 SRO Relocate families 9/22/03

  6. Slide 6: Scope of Work

    Scope of Work • Interim Actions • Remedial Investigation 6 SRO 9/22/03

  7. Slide 7: Interim Response Actions - Overview

    Interim Response Actions - Overview • Driven by MDEQ’s Phase II Report and MDEQ input • For specific areas “known through prior environmental sampling” 7 SRO 9/22/03

  8. Slide 8: Interim Response Actions - Overview

    Interim Response Actions - Overview • Immediate actions to reduce exposure prior to having complete information • Pragmatic approach (timing, property access, public areas) 8 SRO 9/22/03

  9. Slide 9: Riverside Blvd

    Riverside Blvd • Meetings with residents underway 9 SRO 9/22/03

  10. Slide 10: Parks

    Parks • Coordinating with Park Directors on interim solutions 10 SRO 9/22/03

  11. Slide 11: Parks

    Parks • Hand wash stations installed and in use 11 SRO 9/22/03

  12. Slide 12: Parks: Projects under discussion

    Parks: Projects under discussion • Imerman Park riverbank project 12 SRO 9/22/03

  13. Slide 13: Parks: Projects under discussion

    Parks: Projects under discussion • Festival Park wall & deck project 13 SRO 9/22/03

  14. Slide 14: Wild Game

    Wild Game • Sportsmen & women inquiring about consuming wild game • Will conduct study in conjunction with MDEQ, DNR, U.S. Fish & Wildlife, conservation groups & hunt clubs 14 SRO 9/22/03

  15. Slide 15: Wild Game

    Wild Game • Research firm: Entrix, Inc. • Study to include deer, turkey and rabbit • Results to be reported broadly in our community 15 SRO 9/22/03

  16. Slide 16: Mapping

    Mapping • Consolidating maps for everyone 16 SRO 9/22/03

  17. Slide 17: Information Centers

    Information Centers • Coordinating with MDEQ • Working with community leaders to define locations & contents 17 SRO 9/22/03

  18. Slide 18: Scope of Work

    Scope of Work • Interim Actions • Remedial Investigation – The comprehensive scientific evaluation needed to provide the information and data for effective long-term solutions 18 SRO 9/22/03

  19. Slide 19: Remedial Investigation - Overview

    Remedial Investigation - Overview • Comprehensive, mandated regulatory process • Work plans contain full details about how RI will be conducted • Corrective measures based on results 19 SRO 9/22/03

  20. Slide 20: R.I. Requirements

    R.I. Requirements • Identify what is/isn’t known (Current Conditions report) • Prepare methodology, protocol for field investigation • Establish data management process • Prepare detailed implementation plan and schedule • Submit final reports for MDEQ approval 20 SRO 9/22/03

  21. Slide 21: Example - River

    Example - River • Flooding patterns • Deposition patterns • Flow variability of river • Sediment composition, depth and location • Floodplain history and development 21 SRO 9/22/03

  22. Slide 22: Priorities

    Priorities – Health & ecological risk assessments – Exposure pathways – River conditions – Soil characterization – Sediment – Floodplain – Fish and wildlife – Bio availability 22 SRO 9/22/03

  23. Slide 23: Agenda

    Agenda • Introduction • Scope of Work • Interim Actions • Remedial Investigation • Ecology Research Update • Timeline and Next Steps 23 SRO 9/22/03

  24. Slide 24: The MSU Team

    The MSU Team Aquatic Toxicology Laboratory John P. Giesy, Ph.D. Matt Zwiernik, Ph.D. Paul Jones, Ph.D Patrick Bradley, B.S. Jeremy Moore, B.S. Mic Kramer, B.S. Karl Strause, M.S. Arianne Neigh, B.S. 24 SRO 9/22/03

  25. Slide 25: What is the MSU - Aquatic Toxicology Laboratory doing?

    What is the MSU - Aquatic Toxicology Laboratory doing? 25 SRO 9/22/03

  26. Slide 26: Aquatic Exposure Pathways

    Aquatic Exposure Pathways Bald Eagle Kingfisher Mink forage fish predatory fish carp/suckers Benthic invertebrates Sediment 26 SRO 9/22/03

  27. Slide 27: Terrestrial Exposure Pathways

    Terrestrial Exposure Pathways Owls/hawks/foxes American robin/shrews Soil Invertebrates 27 SRO 9/22/03

  28. Slide 28: Preliminary Exposure Pathways

    Preliminary Exposure Pathways GH Owl Kingfisher Great Blue Heron Bald Eagle Mink RT Hawk + Osprey Small mammals Fish + Forage Fish + Crayfish Muskrats Terrestrial insects Benthic insects Terrestrial Aquatic Plants Vegetation Soils Sediments 28 SRO 9/22/03

  29. Slide 29: Fish Collections

    Fish Collections 29 SRO 9/22/03

  30. Slide 30: Small Mammal Sampling

    Small Mammal Sampling 30 SRO 9/22/03

  31. Slide 31: Aquatic Emergent Insect Sampling

    Aquatic Emergent Insect Sampling 31 SRO 9/22/03

  32. Slide 32: Preliminary Exposure Pathways

    Preliminary Exposure Pathways GH Owl Kingfisher Great Blue Heron Bald Eagle Mink RT Hawk + Osprey Small mammals Fish + Forage Fish + Crayfish Muskrats Terrestrial insects Benthic insects Terrestrial Aquatic Plants Vegetation Soils Sediments 32 SRO 9/22/03

  33. Slide 33: Overview of Timing

    Overview of Timing Timeline for Tittabawassee 2003/2004 Sampling: Field sampling Sample Processing Analysis Data QC Data report Sept Oct Nov Dec Jan Feb Mar 2003 2004 33 SRO 9/22/03

  34. Slide 34: 2003 Timeline

    2003 TIMELINE 2003 ID | Task Name Jun | Jul | Aug | Sep | Oct | Nov | Dec | Jan | Feb | Mar 1 Operating License Issued 2 = | Scope of Work Plans Submitted 3 _|Interim Response Actions (IRA) 4 IRA Workplan Development 5 MDEQ Review of IRA VVorkplan 6 Initiate IRA Workplan Activities 7 Soil Sampling i

  35. Slide 35: Expected Path Forward

    Expected Path Forward • MDEQ to end public input Oct. 10 • MDEQ will provide final formal input to Dow • Dow will submit revised SOW to MDEQ for approval • Dow will implement upon MDEQ approval 35 SRO 9/22/03

  36. Slide 36: Thank you.

    Thank you. 36