Synthesis Energy Systems Inc · OTC:SYNE
Synthesis Energy Systems — Gasification Technologies Conference 2013
10 slides from Synthesis Energy Systems's conference presentation, Oct 11, 2013
Slide 1: Synthesis Energy Systems: Projects & Technology Initiatives
ST] SYNTHESIS ENERGY SYSTEMS Projects & Technology Initiatives Presented by Robert Rigdon, President & CEO GASIFICATION TECHNOLOGIES CONFERENCE COLORADO SPRINGS, COLORADO OCTOBER 14, 2013
Slide 2: Forward Looking Statements
Forward Looking Statements This presentation includes "forward-looking statements” within the meaning of Section 27A of the Securities Act of 1933, as amended, and Section 21E of the Securities Exchange Act of 1934, as amended. All statements other than statements of historical fact are forward-look
Slide 3: Yima Joint Venture Plant
Yima Joint Venture Plant ‘ima Henan Province Location Henan Province, China Design 2 Op +1 Spare 10 barg Pressure Coal Rate 2,400 mtpd Sub-bitum inou: High Ash Co. Partner Yima Coal Industry Group JV Agreement Sept 2009 Ownership 75% Yima 25% SES 50/50 D/E Capital Cost Phl ~$250 mm ~$850mm Add’ Phas
Slide 4: System Status
Yima Joint Venture System Status Sta: Plant Coal Feed Rates Achieved (Peak)! Single Gasifier Dual Gasifier Coal Ash Gasifier Pressure Longest Single Train Ops Longest Dual Train Ops System Efficiency Peak Raw Mc0H Production Refined McOH Production Maximum Capacity % Achieved Single Dual Raw MeoH Re
Slide 5: Shutdowns During Start-up Phase
Yima Joint Venture Plant Shutd owns During Start-up Phase’ 7 ~+ Boiler +Instrumentation Gasification & Coal Feed + Ash Disposal ~Operator Errors Misc (1) Approximate allocation of startup & commissioning phase unit shutdowns
Slide 6: What Worked Well and Challenges
Yima Joint Venture Plant What Worked Well Achieving Approvals JV Agreements 100% Debt Guarantee Go-Fast Mentality Low Cost Mentality Managing Local Suppliers/Contractors Managing Local Site Issues Successive Multi-Project Opportunities Exist Challenges Minority Partner has Limited Influence Global F
Slide 7: Gasification System
Yima Joint Venture Plant f all asd cation System
Slide 8: Zao Zhuang Commercial Facility and Restart
Operated from 2007-2011 (3.5 yrs) Zao Zhuang sory. om : ——__ Shut down due to offtaker financial difficulty Zao Zhuang Commercial Facility & New Gas Platform for Technology Performance | restart Now Underway Demonstration & Company JV Innovation Demonstrated performance on coal Project up to 55% wt
Slide 9: A Vision for Growing Gasification
A Vision for Industry = Growth Growing Gasification The Worlds Most Abundant Energy Resource SES’ COAL APPROACH Vital part of the world’s energymix Market place is evolving Half of the world’s coal is low quality Solutions for market verticals Gasification is a proven, responsible Lower cost, simpli
Slide 10: Summary and Next Steps
Summary and Next Steps @ Cal oS 2 Se Significant progress made with 2 operating plants (ZZ & Yima) Complete Yima startup & focus on financial performance Restart ZZ in 2013 Partner to add biomass and expand ZZ for additional products Deploy technology in unique market verticals with partners Create
Synthesis Energy Systems — Gasification Technologies Conference 2013 on 6ix