Anax Metals Limited · ASX:ANX
Anax Metals — EPC Mining Summit 2026
14 slides from Anax Metals's conference presentation, Nov 19, 2026
Slide 1: How an Integrated Project Team can turn owner-held risk into shareholder value at Whim Creek
How an Integrated Project Team (IPT) can turn owner-held risk into shareholder value at Whim Creek Geoff Laing Managing Director, Anax Metals Limited ASX:ANX EPC Mining Summit 2026 | Perth | 19–20 November 2026
Slide 2: Disclaimer
DISCLAIMER This presentation has been prepared by Anax Metals Limited (the Company) based on information from its own and FORWARD LOOKING INFORMATION third-party sources and is not a disclosure document. No party other than the Company has authorised or caused the This presentation contains forward-
Slide 3: Disclaimer
DISCLAIMER NO NEW INFORMATION – EXPLORATION RESULTS, MINERAL RESOURCES COPPER EQUIVALENT — FORECAST PRODUCTION Forecast copper equivalent (CuEq) production is calculated using recovered, saleable metals in copper, zinc and To the extent that this presentation contains references to prior exploration
Slide 4: Whim Creek Copper Project Summary
WHIM CREEK COPPER PROJECT SUMMARY Near Term Copper Production – Fully Permitted with Existing Infrastructure FULLY PERMITTED DEVELOPMENT STUDIES Mining leases in good standing Planned production of metal over Environmental approvals in an initial 10-year life. NPV $501M place Construction ready. / I
Slide 5: Whim Creek: A Brownfield Copper Hub
WHIM CREEK: A BROWNFIELD COPPER HUB Small capex, high return: delivery costs are highly visible to shareholders A$77M A$501M Pre-tax NPV₇, base case1 Pre-production capex (A$91M incl. working capital) 98% ~13kt IRR, with 14-month payback CuEq per year, first 8 years Refer to slide 3 for the forecast
Slide 6: The Proposed IPT Sits Between EPC and EPCM
THE Proposed IPT SITS BETWEEN EPC AND EPCM Each model trades cost, certainty and control differently More risk transferred to contractor (reflected in price) More risk retained by owner (managed in-house) EPC (lump sum) IPT (Anax model) EPCM (reimbursable) Who holds delivery risk Who holds delivery
Slide 7: Proposed Whim Creek IPT Structure
PROPOSED WHIM CREEK IPT STRUCTURE Owner-led team with an embedded (E)PCM partner, contracting packages directly INTEGRATED PROJECT TEAM Design & Supply: crushing & ore sorting D&S Owner: Anax Design & Supply: polymetallic concentrator D&S COO / Project Director (Owner's Rep) + key owner hires Bulk e
Slide 8: Modularising the Plant to Shrink Site Risk
MODULARISING THE PLANT TO SHRINK SITE RISK Design & Supply contractors deliver preassembled modules; the IPT integrates them on site Key packages: Design & Supply: concentrator Design & Supply: crushing & ore sorting SMPEIC construction Integrated switchrooms Existing crushing plant, refurbished New
Slide 9: The Risks We Keep, and How We Manage Them
THE RISKS WE KEEP, AND HOW WE MANAGE THEM Being honest about owner exposure is the starting point Interface risk Cost overrun Schedule integration Gaps between packages No lump-sum wrap Owner sets the critical path How we manage it How we manage it How we manage it Defined battery limits, one Packag
Slide 10: The Deciding Factor: The Right People
THE DECIDING FACTOR: THE RIGHT PEOPLE The IPT doesn't remove risk; experienced people make it manageable Owner leaders who have built plants Management, engineering, package, construction and commissioning leads with delivery track records Operators hired before they're needed Mine Manager, Plant Ma
Slide 11: From Retained Risk to Shareholder Value
FROM RETAINED RISK TO SHAREHOLDER VALUE What the IPT can return to shareholders, if it's run well Managed by the right Risk retained Value kept by shareholders Interfaces, schedule, cost contingency, people Potential for lower capex, less dilution, grade & recovery Experienced owner team + embedded
Slide 12: Proposed Path to Production
PROPOSED PATH TO PRODUCTION1 About 6 months FEED to FID, then about 18 months FID to first production (indicative) H2 2026 H1 2027 H2 2027 H1 2028 H2 2028 FEED 4 mths Investment approval 2 mths Detailed design 6 mths Procurement & fabrication 14 mths Construction 14 mths Direct Shipping ore circuit
Slide 13: When Does the IPT Make Sense?
WHEN DOES THE IPT MAKE SENSE? 01 02 03 04 Capable owner Modular scope Strong package Aligned board A team that has built and run Work that can move offsite partners Clear risk appetite and plants, and can be recruited into controlled fabrication D&S contractors willing to contingency held by the and
Slide 14: Thank you. Questions?
Geoff Laing / Managing Director Thank you. Questions? anaxmetals.com.au