Iluka Resources Limited · ASX:ILU

Iluka Resources — TZMI virtual congress 2021

26 slides from Iluka Resources's conference presentation, Nov 10, 2021

  1. Slide 1: Iluka: Disciplined and Proactive

    1 Iluka: Disciplined and Proactive TZMI virtual congress 2021 Matthew Blackwell, Head of Major Projects and Marketing

  2. Slide 2: Disclaimer and compliance statement

    Disclaimer and compliance statement 2 This presentation has been prepared by Iluka Resources Limited (Iluka). By accessing this presentation you acknowledge that you have read and understood the following statement. This document provides an indicative outlook for the Iluka business in the 2021 fina

  3. Slide 3: 2021 – Industry challenges continue

    2021 – Industry challenges continue 3 A combination of both existing and emerging challenges continue to impact our industry • Covid pandemic • Logistics challenges • Climate change and severe weather • Escalating sovereign risks • Declining grades at existing mines • New projects delayed

  4. Slide 4: Iluka's commitment to sustainability

    Iluka’s commitment to sustainability 4 Key pillars of Iluka’s sustainability approach 1.7 TRIFR 43% Health and safety (H1 2020: 3.2) female representation Executive and Board (Total Recordable Injury Frequency Rate) Our people Our communities Environmental stewardship 26% Zero Indigenous employment

  5. Slide 5: Jacinth-Ambrosia - hybrid power evolution

    Jacinth-Ambrosia - hybrid power evolution Iluka commissioned its first solar farm at Jacinth-Ambrosia in Q3 2021 with the plant expected to produce power from Q4 2021. The project is now being used as a template for future developments across Iluka’s sites 3.5MW 1460MW hours Forecast production for

  6. Slide 6: Operational settings

    Operational settings Cataby / South West Jacinth-Ambrosia / Mid West Eneabba Sierra Leone Large chloride ilmenite rich mine, Jacinth-Ambrosia is one of the world’s Processing and sale of monazite World’s largest rutile mine, operating since commissioned in 2019. Ilmenite feeds largest zircon mines,

  7. Slide 7: Mineral sands markets

    » —_— Pa "fi LF P uJ wot Mineral sands markets

  8. Slide 8: Zircon: Key Features

    Zircon 8 Key Features Iluka annual zircon production • Q3 21 YTD sales 266kt (Q3 20 YTD: 142kt) Zircon (kt) 400 Result – Q3 sales of 89kt (+40% YoY) after Q2 sales of 91kt 300 Average 314kt • Demand in key markets reflecting a return to pre-pandemic production levels 200 • Q3 21 YTD weighted average

  9. Slide 9: Zircon market – long term market outlook

    Zircon market – long term market outlook 9 kt Zircon supply by U+Th levels 1,600 Decreasing supply of low uranium and thorium (U+Th) zircon 1,400 • Natural zircon contains uranium (U) and thorium (T) in varying quantities 1,200 • China’s strict enforcement of radiation limits is impacting some suppl

  10. Slide 10: High-grade titanium feedstocks: Key Features

    High-grade titanium feedstocks 10 Key Features • Q3 21 YTD sales 410kt (Q3 20 YTD: 209kt) Rutile net realised FOB price US$/t Result – Q3 sales of 129kt after Q2 sales of 152kt • Demand in all regions outpacing supply US$/t 1600 • Q3 21 rutile price up 1.5% to US$1,242/t1 Pricing • Pigment pricing m

  11. Slide 11: High-grade titanium feedstock - long term market outlook

    High-grade titanium feedstock - long term market outlook 11 Key Features High grade feedstocks essential to pigment and welding industries Inputs required and waste produced per tonne of titanium • Used to increase capacity utilisation of pigment plants and is an essential input to the pigment for v

  12. Slide 12: Rare earths markets

    Rare earths markets 12

  13. Slide 13: Rare earths – increasing global demand

    Rare earths – increasing global demand 13 By volume Battery alloys By value Battery Alloys Catalysts Catalysts 2019 rare earth use Ceramics, pigments, glazes Ceramics, pigments, glazes • By volume permanent magnets accounted for nearly 40% of global consumption in 2019 Glass Glass Permanent Metals,

  14. Slide 14: Rare earths – global magnet supply chain

    Rare earths – global magnet supply chain 14 MAGNET IN COMPONENTS EXPLORATION, RE ORE PRODUCTION OF NdFeB MAGNET AND FINAL OXIDE METALS DEVELOPMENT, PRODUCTION PRODUCT BENEFICIATION SEPARATION MINING CHINA CHINA CHINA CHINA CHINA CHINA AUSTRALIA MALAYSIA MALAYSIA VIETNAM JAPAN JAPAN USA AUSTRALIA EST

  15. Slide 15: Projects

    Projects Eucla Basin, South Australia

  16. Slide 16: Project pipeline

    Project pipeline 16 The company develops and progressively gates projects towards execution subject to: improving confidence and satisfaction with the risk-return attributes; continued strategic alignment; and sequencing to take advantage of economic and market outlook ASSESS SELECT DEVELOP EXECUTE

  17. Slide 17: Rare earths

    Rare earths

  18. Slide 18: Superior rare earth feedstock

    Superior rare earth feedstock 18 Iluka’s Eneabba project in Western Australia, is the world’s highest grade operational rare earths deposit and is capable of providing direct feed to a rare earths refinery • Monazite is a natural mineral sand product and a low cost output from Iluka’s current operat

  19. Slide 19: Eneabba development – A phased approach

    Eneabba development – A phased approach CRACKING & Eneabba Phase 3 EXPLORATION, CONCENTRATING LEACHING - METALLISATION COMPONENT DEVELOPMENT, SEPARATION & MANUFACTURING A fully integrated rare earths MINING FINISHING refinery INDIVIDUAL RARE EARTH ORE MONAZITE PERMANENT ✓ Domestic production of rare

  20. Slide 20: Diversified supply of rare earths

    Diversified supply of rare earths 20 Iluka’s Australian refinery would eliminate the need to send concentrate elsewhere for final processing, streamlining the supply of these critical minerals • Continued government support for Iluka’s mineral supply and downstream processing capabilities • Process

  21. Slide 21: Mineral sands

    Mineral sands Cataby, Western Australia

  22. Slide 22: Synthetic Rutile Kiln (SR1) restart, Western Australia – execute decision

    Synthetic Rutile Kiln 1 (SR1) restart, Western Australia – execute decision 22 A capital efficient, incremental synthetic rutile production response, to deliver increased high grade titanium dioxide feedstock in supply constrained market Project overview Parameters • SR1 kiln is located at Capel, We

  23. Slide 23: Balranald, New South Wales – definitive feasibility study decision

    Balranald, New South Wales – definitive feasibility study decision 23 Third technology trial completed and confirmed effectiveness of the underground mining method; definitive feasibility study (DFS) approved Project overview DFS parameters and basis of design West Balranald is a rutile-rich deposit

  24. Slide 24: Wimmera, Victoria – move to larger-scale piloting

    Wimmera, Victoria – move to larger-scale piloting 24 Wimmera is a large-scale deposit with the potential to produce ceramic-grade zircon and rare earth products. Project work is focussed on finding a processing solution to remove impurities from the zircon Project overview The Wimmera project involv

  25. Slide 25: Iluka – disciplined and proactive

    Iluka – disciplined and proactive 25 Iluka has remained focused and steadfast throughout this challenging environment: • Prioritising the health and well being of our employees • Matching production to genuine demand in 2020 and ramping up assets to meet increasing demand through 2021 • Continuing t

  26. Slide 26: Jacinth-Ambrosia, South Australia

    Jacinth-Ambrosia, South Australia

Iluka Resources — TZMI virtual congress 2021 on 6ix