Origin Energy Limited · ASX:ORG

Origin Energy — Technical Presentation (May 2014)

67 slides from Origin Energy's technical presentation, May 29, 2014

  1. Slide 1: Origin-APLNG Operational Review and Asset Visit

    Origin-APLNG Operational Review and Asset Visit David Baldwin, Chief Executive Officer LNG 29 & 30 May 2014

  2. Slide 2: Important Notice

    Important Notice Forward looking statements This presentation contains forward looking statements, including statements of current intention, statements of opinion and predictions as to possible future events. Such statements are not statements of fact and there can be no certainty of outcome in rel

  3. Slide 3: Safety is our first priority

    Safety is our first priority LNG TRIFR LNG TRIFR 8 2,500 7.3 7 2,000 6 Recordable Injuries / TRIFR Man Hours (x1,000) 5 1,500 4.7 4 1,000 3 2 500 1 0 Total Man Hours LNG TRIFR (Rolling 12 Months) 3|

  4. Slide 4: Operational Review and Asset Visit

    Operational Review and Asset Visit CONDABRI - Day 1 Site Tour: - Flyover of gas operations - Bus tour Condabri Central construction area - Wellhead - Water treatment - Gas facilities - Flyover of Curtis Island, Gladstone Presentations: Condabri Central - water and brine ponds, February 2014 - Upstre

  5. Slide 5: Australia Pacific LNG has world leading operators

    Australia Pacific LNG has world leading operators UPSTREAM – 71% complete DOWNSTREAM – 70% complete • Operated by Origin • Operated by ConocoPhillips • Over 16 years’ CSG production experience in • Over 40 years’ LNG production experience Australia • Using ConocoPhillips’ Optimised Cascade® technolo

  6. Slide 6: Upstream Project Delivery

    O origin Upstream Project Delivery

  7. Slide 7: APLNG is progressing in line with budget and on track for first LNG in mid-2015

    APLNG is progressing in line with budget and is on track for first LNG in mid-2015 … 2,000 Demand demand 1,800 Production 1,600 • Demand includes domestic 1,400 contracts, committed ramp Gas Production Rate, TJ/d gas sales and LNG contracts 1,200 • Opportunity exists to use 1,000 some or all product

  8. Slide 8: Upstream Project Goals

    Upstream Project Goals 1 • Health and Safety • Zero Harm 2 • Environment and Land • Honour our Commitments 3 • Safe & Operable Production System • Automation from central control room 4 • Project within schedule and budget • On track to support LNG trains 5 • Team effectiveness • Operations team rea

  9. Slide 9: Upstream Project progress - 71% complete and on track

    Upstream Project progress - 71% complete and on track at 30 April 2014 Upstream Operated Goals FY2014 Plan Actual Progress to 30 April 2014 First gas and water production from Reedy Q3 Accomplished May 2014 Creek (western area) Main pipelines complete Q3 Accomplished Condabri Central Train 1 commiss

  10. Slide 10: Upstream development land, environmental and stakeholder management is progressing

    Upstream development land, environmental and stakeholder management is progressing 1200 1000 18 330 397 800 Lease acquisition 600 969 400 766 700 Drilling and completion 200 Gas and water gathering 0 Approvals Gathering Drilling (well equivalent) Fully approved Compensation Arrangements Agreed Gathe

  11. Slide 11: Upstream development implementation – Phase 1 operated well progress

    Upstream development implementation – Phase 1 operated well progress – April 2014 • Western Fields • Eastern Fields Spring Gully Combabula / Reedy Creek Condabri Talinga / Orana 11 |

  12. Slide 12: Upstream development implementation - Drilling and Completion

    Upstream development implementation - Drilling and Completion Progress Update (30 April 2014): • 700 Phase 1 operated wells drilled • 587 Phase 1 wells completed • 11 drilling rigs • 7 completion rigs • 3 flush-by rigs Drilling Completions 12 |

  13. Slide 13: Well head technology

    Well head technology Key features that enable a wellhead separator to operate under a wide range of operating conditions include the following: 1. Automated Control System – includes instrumentation, communication/Telemetry to a 3D Model of APLNG Phase 1 Wellhead Separator central control room to en

  14. Slide 14: Upstream development implementation - Gathering

    Upstream development implementation - Gathering Progress Update (30 April 2014) • 791 drilling lease preps • 452 diameter-kilometres of flow lines installed (766 equivalent wells) • Installation of cable, gas and water High Density Polyethylene (HDPE) pipe to wells through trenching operations WHS S

  15. Slide 15: Upstream development implementation – Gas and Water Facilities

    Upstream development implementation – Gas and Water Facilities • All 15 compressor trains and modules in Queensland • Construction under way on all gas processing and water treatment facilities • First production wells in Condabri Central commissioned in August 2013, with gas flowing into gathering

  16. Slide 16: Upstream development implementation - Pipeline

    Upstream development implementation - Pipeline • Pipeline design features: 360 km 42-inch main trunk line and 160 km lateral pipelines to gas fields with 50 year design life • The main pipeline construction is complete including hydrotest • First gas (for commissioning) to Curtis Island expected 4Q

  17. Slide 17: Upstream development implementation - Electrification

    Upstream development implementation - Electrification • Power available in the East • Western region progressing supported by temporary power stations 275kV/132 kV Network Power Stations: “Wandoan South to Eurombah Transmission Project” EC 1 (27 MW) – equipment deliveries Forecast first transmission

  18. Slide 18: Upstream development implementation - Water

    Upstream development implementation - Water • Eastern water management systems are in place and operating, – Produced water connections between Condabri, Talinga, Orana and QGC Kenya facility completed – Treated water connection between Talinga and Condabri completed with Monreagh storage and Fairym

  19. Slide 19: Commissioning and Operational Readiness

    Commissioning and Operational Readiness

  20. Slide 20: Well Commissioning Overview

    Well Commissioning Overview 1. Well Commissioning Team resourced to meet 2 well/day capability • East/West development split now established with resources in place across both fields. Technical Lead and Delivery Manager roles now appointed and operational. 2. Well Delivery status (as at 9 May 2014)

  21. Slide 21: Gas Facilities Commissioning Overview

    Gas Facilities Commissioning Overview Eastern Region 1. Condabri a) Full commissioning team in place for Train 1 Condabri Central b) 100% of process systems achieved mechanical completion; instrumentation loop testing >97% complete c) Utilities fully commissioned 2. Orana a) Partial commissioning te

  22. Slide 22: Pipelines Commissioning Overview

    Pipelines Commissioning Overview 1. Pipelines a) Wet commissioning completed on Condabri Talinga water pipeline b) Orana Talinga water pipeline pre-commissioned c) Condabri Talinga high pressure gas pipeline hydrocarbon packed d) Condabri Lateral North pipeline pre-commissioned e) Woleebee receiver

  23. Slide 23: Operations Readiness Key Focus Areas

    Operations Readiness Key Focus Areas Current Focus Areas • Safe Start Up of Condabri Central with Pre-Start Up Safety Review scheduled end of May • Brisbane Control Room ready to commission increasing number of wells and facilities • Safety Management Plan implementation across new assets • Critical

  24. Slide 24: Field Performance / Key Exploration & Appraisal Areas of Focus

    Field Performance / Key Exploration & Appraisal Areas of Focus

  25. Slide 25: Origin has over 16 years of CSG production experience

    Origin has over 16 years of CSG production experience APLNG tenure in the Surat and Bowen basins at 30 April 2014 APLNG has prime acreage in both “sweet spots” in Queensland, with 2P reserves more than sufficient to cover gas requirements for all domestic contracts, as well as off-takes from both LN

  26. Slide 26: APLNG has significant remaining development in high confidence areas

    Looking ahead, APLNG has significant remaining development in high confidence areas with proven success … Gilbert Gully … followed by development expanding into greenfield areas ( ) 26 |

  27. Slide 27: Maximum well deliverability considerably higher than current production levels

    Maximum well deliverability considerably higher than current production levels indicate … • The operated wells to be drilled for Phase 1 are expected to produce around 1,200 TJ/d1, with an additional 200 TJ/d1 from non-operated assets • The observed maximum average well deliverability2 across operat

  28. Slide 28: Typical Phase 1 Well Forecast

    Typical Phase 1 Well Forecast Dewatering Stable Production Stage Stage Decline Stage • Typical phase 1 well forecast to have: Production Rate – peak gas rate 1-2 TJ/d Gas – peak water rate 500-1000 bbl/d – approx 50-70% of well’s Water reserves produced within first 5 years Time Spring Gully (pre-LN

  29. Slide 29: Spring Gully Production Performance

    Spring Gully Production Performance ... gas performance of new Phase 1 wells tracking well Spring Spring Gully Gully Phase Phase 1 – 1Average Gas RateWell Comparison Performance 1400 • Chart shows average performance Actual Gas Average (GJ/d) per well for the online duration of each well 1200 • Rate

  30. Slide 30: Condabri Production Performance

    Condabri Production Performance ... gas performance ramping up towards targeted rates Condabri –Condabri AverageGas Well Performance Rate • Chart shows average performance 900 per well for the online duration of Actual Gas Average (GJ/d) each well 800 • Actual production has been turned Adjusted Gas

  31. Slide 31: Condabri Outlook

    Condabri Outlook ... water performance lower than Talinga (as expected) but still very productive, expect gas performance to grow with time Condabri field ~6 months production Talinga field~5 years production Condabri Gas and Water Production Talinga Gas and Water Production 5000 5000 5000 5000 Maxi

  32. Slide 32: Combabula/Reedy Creek early water rates

    Combabula/Reedy Creek ...early water rates are in line with expectations Chart shows water Flow Test Results production rate More Productive observed during Water Rate (bbl/d) tested by completion rig completion operation This provides an indication of ultimate well performance Talinga wells produce

  33. Slide 33: CSG Water – Update on Brine Solutions

    CSG Water – Update on Brine Solutions  Base case strategy for brine management  Going forward, the focus is on the base (outlined in the EIS) is holding brine in case and Brine Injection ponds prior to storage in a mixed salt  Optimization studies show that storage facility construction of a limi

  34. Slide 34: Bowen E&A programme CY14/15

    Bowen E&A Northern Bowen – programme CY14/15 Multi-well vertical pilots underway. Frac Pilots and Horizontal well pilots planned. • Looking forward, Exploration & Appraisal is focused on areas outside the core high confidence development areas • Objectives are to Spring Gully Flank prove up – Good r

  35. Slide 35: Surat E&A programme CY14/15

    Surat E&A Exploration programme Upside – Deep Conventional Test CY14/15 Walloons Low Perm – encouraging pilot results. Frac Condabri South – Pilots underway. Prove up reserves & secure tenure as PL 35 |

  36. Slide 36: Sustain Phase

    O origin Sustain Phase

  37. Slide 37: Drilling continues in the Walloons and Spring Gully areas through to 2020

    Drilling continues in the Walloons and Spring Gully areas through to 2020 … Development focused on Walloons and Spring Gully in period to 2020: • Moving out from, and infill drilling in, initial development areas • ~75% of wells in the Walloons • Low percentage of fracced wells • Focus on reducing d

  38. Slide 38: Optimisation of Drill Complete Connect costs

    A key focus of the sustain phase is optimisation of current Drill Complete Connect costs of approximately $3 million per well Opportunities for reducing Drill Complete Connect costs: • Process improvement • Contracting strategy • Technology and Innovations: • Horizontal drilling and other new well d

  39. Slide 39: Extracting scale benefits to drive operating cost reductions

    Extracting scale benefits, utilising new technologies and maximising productivity to drive operating cost reductions As more wells come online expect to realise scale benefits, driving down operating costs, with specific areas of focus to optimise activities: • Labour and associated costs $/GJ Decre

  40. Slide 40: Metrics

    O origin Metrics

  41. Slide 41: First full year of earnings and cash flows from both APLNG trains expected FY2017

    The first full year of earnings and cash flows from both APLNG trains is expected to be FY2017… • With the phased start up of Train 1 and Train 2, APLNG’s FY2016 financial results will be subject to the following factors: • The rate at which LNG production ramps up from ready for start up to full pr

  42. Slide 42: APLNG Reference Information - Sales

    APLNG Reference Information Reference information in respect of the APLNG project and operations Sales Reference Metric Source LNG Train Capacity 9.0 mtpa FID2 Presentation 4 July 2012 Contract LNG Export Volumes 8.6 mtpa FID2 Presentation 4 July 2012 LNG Export Contracts Terms 20 year contracted of

  43. Slide 43: APLNG Reference Information - Opex and Project Finance

    APLNG Reference Information Operating Expenditure Reference Metric Source Operating expenditure Key components comprise This presentation • Downstream liquefaction costs • Upstream operating expenditure includes: • Upstream well & facilities maintenance and reliability • Upstream field power costs R

  44. Slide 44: APLNG Reference Information - Sustaining Capex

    APLNG Reference Information Upstream Sustaining Capital Expenditure Reference Metric Source Upstream sustaining capital • Expect around 300 operated wells drilled This presentation expenditure per year in near term • Drill, complete, connect cost approximately $3m per operated well, with cost reduct

  45. Slide 45: Downstream Project Delivery

    Downstream Project Delivery

  46. Slide 46: Curtis Island designated as an LNG precinct

    Curtis Island has been designated as an LNG precinct by the State and Federal governments 46 |

  47. Slide 47: APLNG Downstream Facilities

    APLNG Downstream Facilities Liquefaction of natural gas is an established technology. The project utilises the Optimised Cascade Technology similar to the Darwin LNG project which has operated since 2006 • Two trains of 4.5 mtpa capacity, consisting of: – 6 General Electric (GE) Model LM 2500+ G4 dr

  48. Slide 48: Optimized Cascade Process

    Optimized Cascade Process 48 |

  49. Slide 49: Downstream Project progress - 70% complete and on track

    Downstream Project progress - 70% complete and on track at 30 April 2014 FY2014 Downstream Operated Goals Actual Progress to 30 April 2014 Plan First cryo modules set Q3 Accomplished: Feb 2014 Last Train 2 refrigeration compressor set Q3 Accomplished: Mar 2014 Complete loading platform for LNG jetty

  50. Slide 50: Project Highlights

    Project Highlights • Downstream project is on schedule – Engineering is effectively complete with no holds for construction remaining – Procurement is in line with plan. All major equipment has now been delivered and set. Minor critical items are expedited as necessary – All dredging is now complete

  51. Slide 51: Downstream project current status - Construction

    Downstream project current status - Construction LNG TRAINS MARINE FACILITIES • Train 1 construction approaching 60% • Piling has been completed. The loading arms complete. All equipment has been set. One have been installed module remaining (due to be set early June). • The jetty is expected to be

  52. Slide 52: Downstream project current status - Construction

    Downstream project current status - Construction Train 2 Cold Boxes loaded out for shipment Module 101DA delivered to site 52 |

  53. Slide 53: Full operations

    Full operations • Key data • 4.5mmtpa per train • ~730TJ/day gas rate per train • ~30,000m3/day of LNG per train • ~6 days to fill a Tank when one train running ~3 days to fill a tank when two trains running • Ship every 6 days with one train & 3 days with two trains • <12-14hrs to fill a ship (165,

  54. Slide 54: Fishermans Landing Northern Expansion (FLNE) Bund Wall

    Fishermans Landing Northern Expansion (FLNE) Bund Wall 54 |

  55. Slide 55: Port of Gladstone Overview

    Port of Gladstone Overview 55 |

  56. Slide 56: Curtis Island Site – May 2014

    Curtis Island Site – May 2014 Construction Facilities Accommodation Village RO/RO Control & Ramp Utilities Maintenance Ferry & Rock Causeway Train 2 Train 1 MOF Tank B Tank A LNG Jetty 56 |

  57. Slide 57: Trains 1 & 2 Outside Battery Limits (OSBL) – May 2014

    Trains 1 & 2 Outside Battery Limits (OSBL) – May 2014 57 |

  58. Slide 58: Trains 1 & 2 Inside Battery Limits (ISBL) – May 2014

    Trains 1 & 2 Inside Battery Limits (ISBL) – May 2014 58 |

  59. Slide 59: Train 1 – May 2014

    Train 1 – May 2014 Hot Oil Heater/Incinerator Area – Piping Installation Propane Refrigeration Area – Setting “Candy Cane” on Propane Suction Drum 59 |

  60. Slide 60: Train 2 Area – May 2014

    Train 2 Area – May 2014 60 |

  61. Slide 61: Train 2 – May 2014

    Train 2 – May 2014 Propane Suction Drums Set Compressor Substation being moved into position 61 |

  62. Slide 62: LNG Tanks – May 2014

    LNG Tanks – May 2014 62 |

  63. Slide 63: Permanent Buildings – May 2014

    Permanent Buildings – May 2014 63 |

  64. Slide 64: LNG Jetty – May 2014

    LNG Jetty – May 2014 Loading Platform & Trestle Loading Arms installed on Platform 64 |

  65. Slide 65: Module Yard – April / May 2014

    Module Yard – April / May 2014 Final Train 1 Module (Propane Chiller 101JA) & First Train 2 Module (Sub-Cooler 202 NE) shipped on 22 April Propane Condenser 202ND shipped 13 May 65

  66. Slide 66: Curtis Island - May 2014

    Curtis Island - May 2014 66

  67. Slide 67: Thank you

    Thank you

Origin Energy — Technical Presentation (May 2014) on 6ix