Eldorado Gold Corporation · TSX:ELD

Eldorado Gold — Technical Presentation (October 2012)

20 slides from Eldorado Gold's technical presentation, October 2012

  1. Slide 1: Efemçukuru Operational Review – Investors / Analysts Tour

    Kişladağ mine, Turkey Efemçukuru mine, Turkey Vila Nova iron ore mine, Brazil Jinfeng mine, China Tanjianshan mine, China White Mountain mine, China Efemçukuru Operational Review Investors / Analysts Tour September / October 2012

  2. Slide 2: Investors / Analysts Tour October 2012

    Investors / Analysts Tour October 2012

  3. Slide 3: Efemcukuru - Location Map

    o Efemcukuru - Location Map A) eldoradogold

  4. Slide 4: Efemcukuru Mine Layout

    Efemcukuru Mine Layout eldoradogold

  5. Slide 5: Geology - Local setting

    Geology - Local setting eldoradogold BS 14279000 a2zes00N | azas000N. Hew oc He rrvatie BB serene Be ae : 260 BOO Mea sage Ol ee / "> meters a EFEMCUKURU GEOLOGY LEGEND (i roves Fei StecwonkVeininy | sent is Spilite Phrylie — RA

  6. Slide 6: Geology - Local Setting

    Geology - Local Setting sw LOOKING 340 N 700m 4m @ 2.22 git Au 6.25m @ 29.5 git Au 3.75m @ 13.3 git Ady ™ @ 11-4 git Au 4.2m @ 10.4 git A\ Q .5 m @ 11.2 git Au 3.9m @ 9.8 git Au @10.4 m @ 14.9 git Au 600m 5.3m @9.6 git Au 6.95m @ 9.9 git A 12.5m @ 18.7 git A 9 m @13.0 git Au 1.0m @8.6 git Au m @ 13.

  7. Slide 7: Kestane Beleni longitudinal section

    Efemcukuru |) Kestane Beleni longitudinal section eldoradogold SE NW Middle Ore Shoot | North Ore Shoot North West Ore Shoot South Ore Shoot 1 | | t | South Ore Shoot ~~ YHA sama ] ibe, Drill Targets I: I 260m @6o0grAU] T T Au Grade x Thickness tH a {0 >129/4xm @ Completed Holes | | >50g/txm @ Plann

  8. Slide 8: Kokarpinar longitudinal section

    Efemcukuru |) Kokarpinar longitudinal section eldoradogold BH KV351 Oxy-428 NS! KV-352 B st Kv-041 NsI @ 2012 Assayed Drill Hole EE © = 2012 Assay Pending Drill Hole 200 meters 2010-2011 Drill Hole NSI_No Significant Intercept www.eldoradogold.com

  9. Slide 9: Reserves and Resources

    Reserves and Resources 2008 Res / 2009 Reserves 2012 (FM15.new) Model Tonnes Au g/t Au oz Tonnes Au g/t Au oz Resources 5,540 9.55 1,700 6,424 8.90 1,8 Reserves 5,136 9.12 1,506 Depletion (08/2012) 365 8.71 102 Remaining Reserves 4,771 9.15 1,404 • First operating resource revision has been complete

  10. Slide 10: Mining: 400ktpa rate achieved, Phase 2 development

     400tkpa Feasibility Study production rate has been comfortably achieved  Phase 1 development completed, Phase 2 75% complete by end 2012  Cut and Fill mining employed throughout all ore shoots  Phase 1 – Currently Mining 50% SOS, 50% MOS  Delineation at 10m x 10m centers is working well  SOS

  11. Slide 11: Preparatory development into NOS in 2013

     Preparatory development into NOS in 2013  All key and ancillary capital infrastructure in place in 2012  Tipples, Crushing Station and Conveying, Workshops, Dewatering Station, Magazines, Batch Plant, Refueling Bay  LOM planning exercise in progress to determine expansion capability and value w

  12. Slide 12: Underground infrastructure: offices, crusher, conveyor

    OFFICES CRUSHER CONVEYOR UG PUMP STATION FANS WORKSHOP www.eldoradogold.com 12

  13. Slide 13: www.eldoradogold.com

    2) 2 (e) > Y Cc o oO Cc <x I 00 & & =

  14. Slide 14: Plant nameplate capacity and target recovery achieved

     Plant nameplate capacity (400tkpa) and feasibility target recovery (92.5%) has been achieved and exceeded  2 relines performed in 2012  Availability YTD at 88%, aiming for 90% by year end and 93% in 2013 www.eldoradogold.com 14

  15. Slide 15: Ongoing optimization of grind size and recovery

     Ongoing optimization focused on grind size, sulphur content analysis, mineralogical understanding and gravity recovery improvements  Plant expansion study in progress,  Current bottlenecks are filter presses (tailings and concentrate) www.eldoradogold.com 15

  16. Slide 16: Processing Flowsheet

    o Processing Flowsheet a eldoradogold

  17. Slide 17: Dry stack tailings and waste storage

    • Dry Stack Tailings system Phase 1 near complete • Phase 2 permitted and in use • South waste storage expanded redesign has accommodation for ~ 165% of tailings requirements and ~120% of waste rock requirements for current reserves • Permit requested for additional storage system to North of mine •

  18. Slide 18: Mine planning and plant expansion studies

    • Mine Planning Study identifies no major impediment for +35% production increase • Plant Expansion Study based upon scale up of circuit downstream of mills, aiming for ~65tph • EIA revision sought for 600ktpa www.eldoradogold.com 18

  19. Slide 19: Local employment, education and vineyard project

    Local Employment • 153 permanent local employees in Operations (44% of workforce) • ~120 locals employed in supporting contracts and Vineyard project Education Initiative • 21 High school students • 4 University students Vineyard Project • 10 ha planted in cabernet, merlot, shiraz, chardonnay • 60 h

  20. Slide 20: Permitting

    Permiting Permits • All operational permits are in hand for ongoing production • Revised EIA for expanded footprint will be submitted in October • Minor additional permits are also in due process. (UG explosives, additional forest access) www.eldoradogold.com 20