Slide 1: Pre-Feasibility Study Results Announcement
INVESTMENT HIGHLIGHTS Pre-Feasibility Study Results Announcement Advancing the world-class Haib Cu Project in Namibia Low risk, low cost, long life. Simple, scalable, near term. TSXV: KRY Heye Daun : President & CEO 17 November 2026
Slide 2: Forward Looking Statements & Disclaimer
FORWARD LOOKING STATEMENTS & DISCLAIMER This document has been prepared by Koryx Copper S.A. (“Koryx Copper” or the “Company”) solely for the use in the presentation being given in connection with the recipient’s evaluation of the Company which is defined and outlined further herein. This documentat
Slide 3: Investment Highlights
INVESTMENT HIGHLIGHTS 1. Credible Leadership team with proven track record: Since mid 2024 new Namibian leadership & technical team in place. Proven track record of repeated, successful Namibian mine development & shareholder value creation. 2. Excellent Haib Open-Pit Cu Project: Excellent pedigree,
Slide 4: Haib Copper Project: November 2026 PFS Highlights
HAIB COPPER PROJECT: NOVEMBER 2026 PFS HIGHLIGHTS ➢ Single open pit with conventional milling & flotation concentrator process ➢ 48mtpa ROM feed, 36mtpa flotation after 25% CPF/CGR rejection ➢ US$5.00/lb Cu price assumption and 8% discount rate ➢ World-class, long life, low cost, low risk, scalable
Slide 5: Haib Benchmarking – Low-Grade Producing Copper Mines
HAIB BENCHMARKING – LOW-GRADE PRODUCING COPPER MINES PRODUCTION(1) (Cu ktpa) COPPER FEED GRADE (1) (2) (% Cu) 0.33% 0.24% 0.42% 0.34% 0.40% 0.32% 0.33% 0.33% 0.24% 0.15% 0.37% 0.22% 0.25% 0.31% 0.27% 391 313 135 127 125 120 91 85 83 51 51 44 44 42 24 (3) Cerro Morenci Haib Highland Bingham La Carida
Slide 6: Positioning on Cu Industry Cost Curve (AISC)
KORYX BENCHMARKING: HAIB CU PROJECT: POSITIONING ON CU INDUSTRY COST CURVE (AISC) $7.00 $5.00 Haib AISC $3.00 (first 10 years): US$2.07/lb AISC (US$/lb) $1.00 ($1.00) 25% 50% 75% ($3.00) ($5.00) Paid Copper (mm lbs Cu) Source: Wood Mackenzie 2026E Copper Cost Curve Notes: AISC is C1 cash cost (net o
Slide 7: Haib Benchmarking – Capital Intensity
HAIB BENCHMARKING – CAPITAL INTENSITY (MAJOR AND NON-MAJOR CONTROLLED PROJECTS) LOM CAPITAL INTENSITY (US$k/t p.a. Cu) $60.4 Connection to a Major $48.5 $36.2 $34.0 $34.5 $30.1 $30.3 $28.5 $29.1 $28.0 $24.8 $24.9 $25.5 $24.2 $21.4 $22.1 $19.6 $19.7 $20.0 $16.8 $16.0 $11.1 - Los Andes - Koryx Copper
Slide 8: Indicative Development Schedule
INDICATIVE DEVELOPMENT SCHEDULE ➢ Upsized PFS & significant further de-risking by end 2026 ➢ Permitting, DFS, project financing to commence post PFS in 2027 until early 2028 ➢ Review of strategic options once major permitting concluded around mid 2027 2026 2027 2028 PRE- F E AS IB IL IT Y FEASI BI L
Slide 9: 2026 / 2027 Technical Strategy
2026 / 2027 TECHNICAL STRATEGY 1. Right-sizing & Optimizing: ✓ Complete intensive infill drill program ✓ Fix process route by reverting back to conventional sulfide flotation concentrator ✓ Investigate viable, novel processing techniques to enhance process flowsheet ✓ Improve Cu grade & model Au/Mo/
Slide 10: Koryx Trades at Major Valuation Discount to Cu Developer Peers
KORYX TRADES AT MAJOR VALUATION DISCOUNT TO CU DEVELOPER PEERS PRICE / NAV x 1.14x Intermediate Copper Producers 0.92x 0.88x Junior Copper Producers 0.83x 0.80x Copper Developers 0.75x 0.71x 0.62x 0.51x 0.48x 0.50x 0.42x 0.42x 0.33x 0.34x 0.31x 0.27x 0.28x 0.29x 0.25x 0.20x 0.16x 0.13x 0.12x 0.12x 0
Slide 11: Valuation Discount to Peers With Reserves (EV / 2030E EBITDA)
KORYX TRADES AT MAJOR VALUATION DISCOUNT TO CU DEVELOPER PEERS WITH RESERVES EV / 2030E EBITDA – NEAR-TERM PRODUCTION PROJECTS – US$5.00/lb LT Cu PEA PFS 4.56x DFS 4.07x 4.15x 3.45x 1.88x 1.33x 0.33x Koryx Sonoran Marimaca Faraday Ivanhoe FireFly SolGold Electric Arizona Source: Company filings, Fac
Slide 12: Koryx Trades at Major Valuation Discount (EV / Reserve)
KORYX TRADES AT MAJOR VALUATION DISCOUNT GIVEN EV PFS STAGE, / RESERVE WORLD-CLASS TECHNICAL ATTRIBUTES, ADVANTAGEOUS JURISDICTION & FAST-TRACKED (USȼ/lb Cu) PERMITTING TO CONSTRUCTION EV / RESERVE USc/lb Cu PFS ¢32.2 DFS ¢29.9 ¢25.7 ¢26.1 ¢18.2 ¢12.7 ¢4.2 ¢4.2 ¢5.6 ¢2.7 Western Ivanhoe Sonoran Tril
Slide 13: Experienced Leadership & Technical Team
EXPERIENCED LEADERSHIP & TECHNICAL TEAM Executive Leadership Team: Decades of experience with multi-national mining or engineering firms. Overall DFS Study Manager Lionel Coetzee Namibia Country Manager PEASite Study Manager && Tailings Infrastructure Heye Daun Charles Creasy Steve Burks Coordinatin
Slide 14: A Proven Track Record of Success in Namibia
A PROVEN TRACK RECORD OF SUCCESS IN NAMIBIA Completed 2011 Completed 2024 In Progress ….. • $180m sale to B2Gold in • $390m cash sale to Yintai1 • Change in management 2011 in 2024 control in early 2024 • Founded in 2009. Acquired • Founded 2016 • CAD 100m working project for US$28m capital raised s
Slide 15: Capital Structure
CAPITAL STRUCTURE CAPITAL STRUCTURE SHAREHOLDER OVERVIEW SIGNIFICANT SHAREHOLDERS Share Price (Nov 17, 2026) C$3.45 Institutions, 52-Week Trading Range C$0.85 – 3.90 Strategics, Ross Beaty & HNW Basic Shares Outstanding 121.5m (est.) 26% Options Outstanding 0.62m RSUs Outstanding 9.19m 121.5m Warran
Slide 16: Namibia – A World-Class Mining Jurisdiction
NAMIBIA – A WORLD-CLASS MINING JURISDICTION STABLE & MINING FRIENDLY ▪ Stable democracy, independent judiciary, diverse economy. ▪ Transparent system of mineral & surface title ▪ Strong political and social support of mining with stated ambition to develop mineral resources. EXCELLENT INFRASTRUCTURE
Slide 17: Namibia – Tectono-Stratigraphic Setting
NAMIBIA – TECTONO-STRATIGRAPHIC SETTING ➢ Haib is a large, world-class, advanced open-pit Cu/Mo/Au/Ag porphyry deposit with a long history of exploration & project development ➢ One of a few Paleoproterozoic porphyry copper deposit in the world (two in Namibia). Excellent pedigree (Falconbridge, Rio
Slide 18: Haib Copper Project: Aerial View Looking East
HAIB COPPER PROJECT: AERIAL VIEW LOOKING EAST Approximate Future Open Pit Outline TSXV:KRY 18
Slide 19: Latest Drill Results (September 2026)
LATEST DRILL RESULTS (SEPTEMBER 2026): CuEq% BASIS HM178 HM124 318m @ 0.49% 94m @ 0.42% HMRC001 Including Including HM130 220m @ 0.40% 16m @ 0.75% 16m @ 0.66% HM199 132m @ 0.41% Including 224m @ 0.51% Including 8m @ 0.60% Including 18m @ 0.53% 26m @ 0.70% HM137 162m @ 0.46% Including 6m @ 1.47% HM19
Slide 20: PFS Mineral Resource and Reserve Estimate
PFS MINERAL RESOURCE AND RESERVE ESTIMATE (November 2026, 0.15% Cu cut-off) Mineral Resource Estimate CuEq % Cu kt Cu Mo Au CuEq Cu Mo Cu Mo Au Tonnes Category Type Grade Grade Grade Grade Content Content Content Content Content (Mt) (%) (ppm) (g/t) (%) (Mlbs) (Mlbs) (kt) (kt) (koz) High Grade (>0.2
Slide 21: Mine Production Schedule
TSXV:KRY 21 Year 33 Year 32 Year 25 Year 31 Produced Metal - Cu - Oxide & Transitional Year 24 Year 30 PB3 Year 29 Year 23 Year 28 Year 22 Year 27 PB2 PB5 Year 21 Year 26 Year 20 Year 25 Year 24 Year 19 PB1 PB4 Year 23 Year 18 Year 22 Year 17 Year 21 Year 16 Year 20 Year 19 Year 15 Total Copper Tonn
Slide 22: Mine Planning
TSXV:KRY 22 Pushback 5 Pushback 4 Year 33 Pushback 3 Year 32 Year 31 Year 30 Year 29 Year 28 Year 27 Year 26 Year 25 Produced Metal - Cu - Oxide & Transitional Year 24 Year 23 Year 22 Year 21 Pushback 2 Year 20 Year 19 Year 18 Year 17 Year 16 Year 15 Year 14 Total Copper Tonnes Produced Year 13 Year
Slide 23: Mine Layout
MINE LAYOUT Low Grade Sulphide Stockpiles Run-of Mine (ROM) Pad Area Open Pit Oxides and Transitional Stockpiles Waste Rock Dump Low Grade Sulphide Stockpiles TSXV:KRY 23
Slide 24: PFS Process Flowsheet
PFS PROCESS FLOWSHEET (OPTIMIZED MILLING & FLOTATION CONCENTRATOR) ➢ Low-risk 48 Mtpa crushing & milling process incl HPGRs ➢ Coarse particle flotation rejects 25% of ROM ore in coarse (> 150 µm) tailings at similar Cu grade as fine tailings from the main flotation circuit. ➢ 36 Mtpa after CPF is mi
Slide 25: Site Layout Optimised
SITE LAYOUT OPTIMISED SITE & INFRASTRUCTURE LAYOUT IN IDEAL LOCATION TSXV:KRY 25
Slide 26: Optimised Site & Infrastructure Layout in Ideal Location
OPTIMISED SITE & INFRASTRUCTURE LAYOUT IN IDEAL LOCATION • Existing 132kV overhead line to be upgraded to 220kV (1). • Baseload supply through Southern African Power 1 Pool from N Cape in RSA. • 50% PV/BESS capacity 3 augmentation approved • Permitting underway • 20m m3 pa water demand. • Water supp
Slide 27: The Namibian Permitting Process
THE NAMIBIAN PERMITTING PROCESS 1 2 3 4 5 Namibia’s Screening Scoping EIA Decision Appeal environmental Based on project, Scoping report and Specialist baseline Registered I&APs permitting Ministry decides if a public participation studies, impact notified; 14 days process full EIA is required set t
Slide 28: Responsible Mining Is Good Business
RESPONSIBLE MINING IS GOOD BUSINESS Developing a sustainability plan and implementation roadmap that is materiality-driven and considers compliance, risk, stakeholder and investor expectations, best practices and business strategy Responsible Mining Commitments Guiding frameworks and standards a. Et
Slide 29: How Is Haib Differentiated From Other Copper Projects?
KORYX BENCHMARKING: HOW IS HAIB DIFFERENTIATED FROM OTHER COPPER PROJECTS? HAIB CHARACTERISTIC WHY IT IS BENEFICIAL? Positions Haib as a globally relevant copper project, with 1 Meaningful scale: ~135ktpa Cu in the first 10 years cash flow at a scale that has historically attracted M&A 2 Large, cont
Slide 30: Haib Benchmarking – Key Characteristics
HAIB BENCHMARKING – KEY CHARACTERISTICS 130kt+ CuEq CuEq Capital Production avg. annual Intensity Altitude <1km Market Cap. potential by production <$15,000 / t AISC <$2.10 / lb Saleable by- Strip ratio <1.1x above sea (US$ millions) Company Project Location 2030 2029 (first 10 years) (first 10 year
Slide 31: Investment Highlights
INVESTMENT HIGHLIGHTS 1. Credible Leadership team with proven track record: Since mid 2024 new Namibian leadership & technical team in place. Proven track record of repeated, successful Namibian mine development & shareholder value creation. 2. Excellent Haib Open-Pit Cu Project: Excellent pedigree,
Slide 32: Appendix
APPENDIX Approximate Future Open Pit Outline TSXV:KRY 32
Slide 33: 2026 PFS Process Design Optimisation Since 2025 PEA
2026 PFS PROCESS DESIGN OPTIMISATION SINCE 2025 PEA Oct-25 PEA Final Throughput Increase Sorting & CPF PFS Debottlenecking Oct- Mar May Aug- 25 -26 -26 26 TSXV:KRY 33
Slide 34: Coarse Particle Flotation
COARSE PARTICLE FLOTATION A complementary, flotation-based approach to reject waste earlier thereby increase processed grade, maintain copper recovery and optimize the size and cost of the downstream flotation circuit. Various available technology suppliers, such as Eriez or FLS. CPF vendor referenc
Slide 35: Coarse Gangue Rejection at Haib
COARSE GANGUE REJECTION AT HAIB 1 Standard Ball Mill Circuit Cyclone Overflow Jameson Flotation Section Fresh feed 48 MTPY | 0.35% Cu 48 MTPY | 0.35% Cu Ball mill Hydrocyclone nest Cyclone underflow: 120 MTPY 250% of fresh feed 2 Coarse Gangue Rejection CGR Cyclone Overflow Jameson Flotation Section
Slide 36: Power Supply: NamPower Grid Plus ~45% Solar PV and BESS
POWER SUPPLY: NAMPOWER GRID PLUS ~45% SOLAR PV AND BESS MINE ELECTRICAL LOAD NamPower Grid 55% Solar PV + BESS 45% Deep connection to existing Maximum renewable integration 1,650 261 NamPower’s Harib substation and upgrading overhead lines. to ensure lowest overall cost of electricity GWh per annum
Slide 37: Mine Water Supply
MINE WATER SUPPLY Water Requirement Water system: Orange River to process plant 2 km pipeline 10 km pipeline 20 million Orange River Store water in off-channel Process m³ per annum intake during storage dam to cater for plant surplus flow seasonal river flow Site layout showing bulk water options Ex
Slide 38: Precedent Copper Transactions
PRECEDENT COPPER TRANSACTIONS INCLUDES TRANSACTIONS IN THE LAST 10 YEARS INVOLVING TARGETS WITH 100+ KTPA ACTUAL OR EXPECTED COPPER PRODUCTION Ann. Date Acquirer Target Target Stage of Development Enterprise Value (US$ mm) 10-Mar-26 Lundin Mining 5% Caserones & 31% Los Helados (JX Nippon) Resource E
Slide 39: PFS Cashflow Schedule
PFS CASHFLOW SCHEDULE PFS CASHFLOW MODEL Units Total/Avg. -2 -1 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 Mining Pre-strip Pre-strip Ore Tonnes Mined Mt 1,119 6.6 22.2 88.7 92.7 85.8 95.5 97.2 105.9 78.8 45.6 42.0 46.3 72.6 87.4 81.0 58.0 12.1 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Slide 40: Haib Copper Project: Six Decades From First Drill Holes to Pre-Feasibility
H A IB C O P P ER P R O JEC T · S O U T H ER N N A M IBIA Six decades from first drill holes to pre-feasibility Falconbridge 1964 · First m o d ern exp lo ratio n p ro g ram m e o n a d ep o sit kno wn Fro m 1964 since the 1950s Rio Tinto 1975 · 50,000+ m d rilled with Falco nb rid g e; then ab o ut
Slide 41: Contacts