  1. Slide 1: Eldorado Gold Corporation

    Eldorado Gold Corporation April p 2010 www.eldoradogold.com 1

  2. Slide 2: Forward-Looking Statements

    Forward-Looking g Statements Certain of the statements made in this Presentation may contain forward-looking statements within the meaning of the United States Private Securities Litigation Reform Act of 1995 and forward-looking information within the meaning of applicable Canadian securities law. T

  3. Slide 3: Where we operate

    Where we operate p Eldorado Gold is a Canadian gold producer with 4 operating mines, 2 mines under construction,, 1 late stage g development p p project j and an extensive exploration p p program g with 125,000 meters of drilling planned for 2010. We operate in China, Turkey, Brazil, Greece and surr

  4. Slide 4: 2009 Financial and Operating Highlights

    2009 Financial and Operating Highlights ƒ Earnings of $0.26 per share ƒ Cash flow of $0.38 per share ƒ Gold sales increased by 29% ƒ Strong year-end balance sheet with $315 M in cash ƒ Increased P+P reserves by approximately 95% to 15.1 M oz of gold ƒ Increased M+I resources to 21.3 M oz of gold ƒ P

  5. Slide 5: Production, cost and resources overview

    Lowest Q Quartile of Production Cost Forecast Annual Gold Production (in ounces) Expanding Margins (in $/oz) 1 200 1,200 $500 Perama Hill $1,200 $995 Eastern Dragon Gold Production (x1,000 oz) Cash Operatingg Cost ($/oz) 1,000 $400 $876 $1,000 Efemçukuru 800 $674 Margins $800 $300 $609 White Mountai

  6. Slide 6: Superior Shareholder Performance

    Superior p Shareholder Performance Return on Shareholders Equity Share Price Performance $9,000 400% ELD Increased Return on C$14.92 $ Share Capital: market 328% 345% Issued capitalization C$2.3 by C$8.2 (38% Market 300% $6,000 annualized) millions billion billion Capitalization in shares 200% Amex

  7. Slide 7: Objectives

    Objectives j 2010 ƒ Production of 550,000 - 600,000 oz of gold from 4 mines at a cash operating cost of $385 - $400/oz ƒ p Complete expansion p p plan at Kişladağ ş ğ ƒ Complete construction of Efemçukuru and Eastern Dragon mines ƒ Submit EIA for Perama Hill mine project ƒ Execute a $35 M exploratio

  8. Slide 8: Kişladağ Mine, Turkey

    Kişladağ ş ğ Mine,, Turkeyy ƒ Kişladağ is an open pit heap leach gold mine located in Uşak Province, Turkey that began commercial production in July 2006 ƒ In 2010, ore production is planned to be 10MT/year at a 1.03 g/t with a strip ratio of 1 21 1 1.21:1 ƒ P+P gold reserves increased by 23% to 6.8

  9. Slide 9: Jinfeng Mine, China

    Jinfeng g Mine,, China ƒ Jinfeng is an open pit and underground gold mine located in Guizhou Province, China that began commercial production in September 2007 ƒ Eldorado owns an 82% interest with local joint- venture t partner t G Guizhou i h Lannigou L i Gold G ld Mine Mi Limited holding the remai

  10. Slide 10: Tanjianshan Mine, China

    Tanjianshan j Mine,, China ƒ Tanjianshan (TJS) is an open pit, float-roast-CIL operation located in Qinghai Province, China that began commercial production in February 2007 ƒ TJS consists of two pits: QLT and JLG ƒ Partners in TJS are Q Qinghai g Number One Geological Brigade (5%) and the Dachaidan

  11. Slide 11: White Mountain Mine, China

    White Mountain Mine,, China ƒ White Mountain is an underground mine using a sub sub-level level and cut cut-and-fill and fill stoping mining method located in Jilin Province, China that commenced commercial production in January 2009 ƒ Eldorado Eld d owns a 95% interest i t t with ith jjoint- i t ve

  12. Slide 12: Efemçukuru Project, Turkey

    Efemçukuru ç Project, j , Turkeyy ƒ Efemçukuru is a high grade epithermal gold deposit ssuited deposit, ited for underground ndergro nd mechani mechanized ed mining, located in Izmir Province, Turkey ƒ Feasibility study was completed in 2007 with operatingg and capital estimates updated in October 2

  13. Slide 13: Eastern Dragon Project, China

    Eastern Dragon g Project, j , China ƒ Eastern Dragon is a high-grade, low- s lphidation epithermal sulphidation, epithermal, gold gold-silver sil er vein ein deposit located in Heilongjiang Province, China ƒ Eldorado has a 95% equity interest with a private joint venture partner holding 5% ƒ The Env

  14. Slide 14: Perama Hill Project, Greece

    Perama Hill Project, j , Greece ƒ Perama Hill is a shallow, high sulphidation, non-refractory non refractory oxide gold deposit with a low strip ratio ƒ Pre-Environmental Impact Assessment (PEIA) has been submitted in October 2009 ƒ Environmental Impact Assessment (EIA) to be submitted in the second

  15. Slide 15: Strategy

    Strategy gy ƒ Long life, low cost assets ƒ Lowest quartile of production cost ƒ Strong balance sheet ƒ No hedge positions ƒ Regional exploration with excellent development projects for internal growth ƒ Explore, develop and operate to high standards www.eldoradogold.com 15

  16. Slide 16: Thank you

    Thank you y Eldorado Gold Corporation TSX: ELD NYSE: EGO ASX: EAU Shares Outstanding (as of December 31, 2009): 537.1 M Investor Relations: Nancy Woo (604) 601-6650 nancyw@eldoradogold.com www.eldoradogold.com 16

  17. Slide 17: Appendix I: China Operations

    Appendix pp I: China Operations p Eastern Dragon project Heilongjiang Province White Mountain mine Jilin Province Tanjianshan mine Qinghai Province Jinfeng mine Guizhou Province www.eldoradogold.com 17

  18. Slide 18: China - Facts and Fallacies

    China - Facts and Fallacies Fallacy Fact The refining and selling of gold is tightly There is a choice of refineries (including Metalor) and the producer controlled and the producer receives a discount is free to negotiate with the preferred refinery. Terms and to the spot price. conditions are simi

  19. Slide 19: China - Facts and Fallacies

    China - Facts and Fallacies Fallacy Fact Gold mining is in the “prohibited” category, and The Foreign Investment Catalogue places investment in the gold the size of deposit available to foreign companies sector in the “restricted” category. The restricted category simply is limited. means that there

  20. Slide 20: The Big 4 Government Agencies

    “The Big g 4” Government Agencies g ƒ National Development and Reform Commission (NDRC) ƒ The main agency that directs the “planned economy” ƒ Mainly responsible for the Foreign Investment Catalogue ƒ Approves the final Chinese Feasibility Study for gold mining operations ƒ Ministry of Land and Reso

  21. Slide 21: Typical Flow Chart for Mine Permitting of a Sino-Foreign JV

    Typical Flow Chart for Mine Permitting of a Sino-Foreign Sino Foreign JV ƒ Assume an existing Exploration License (EL) with drilled resources Set up JV and obtain Business License Approval by MOFCOM Transfer EL into the JV Approval by MOLAR Approval by NDRC and Chinese Feasibilityy Studyy and EIA En

  22. Slide 22: History in China

    Historyy in China 2003 Signed an agreement with the China National Gold Group Corporation (“CNGC”) for the exclusive right i h to review i their h i portfolio f li off operating i mines, i d development l projects j and d exploration l i projects j for a period of 5 months that was later expanded to

  23. Slide 23: Appendix II: 2010 Exploration Overview

    Appendix II: 2010 Exploration Overview ƒ 2010 exploration budget of $35.4 M ƒ Drill to discover: 125,000 metres drilling planned on >20 properties ƒ Blend of minesite, advanced stage, early stage, and generative exploration programs for f long-term l t organic i growth th ƒ Commitment to building st

  24. Slide 24: Reserve Growth Strategy

    Reserve Growth Strategy gy 1. Generative initiatives: ƒ Property identification and acquisition ƒ China ƒ Turkey ƒ Brazil ƒ New business opportunities 2. Early stage exploration projects: ƒ Target definition and testing ƒ China, Turkey, Nevada, Brazil ƒ Drilling planned on >16 projects in 2010 3. Re

  25. Slide 25: China Exploration Budget

    China Exploration p Budget g Generative Exploration: $1.0 M • Project generation and acquisition Eastern Dragon District: $2.4 M • Lode 5 stepo stepoutt drilling • EL53 new targets • Sanjianfeng JV Tanjianshan District: $3.8 M White Mountain District: $2.5 M • Resource drilling at • WM stepout drill

  26. Slide 26: China Exploration Organization

    China Exploration p Organization g (Vancouver) V.P. Exploration Peter Lewis Director of Geology gy and New Projects, China Yumin Qiu Exploration p Exploration Exploration Exploration Exploration Manager, Manager, Manager, Manager, Manager, Generative Jinfeng White Mountain Eastern Dragon Tanjianshan

  27. Slide 27: Jinfeng District

    Jinfeng g District ƒ Sediment-hosted, Sediment hosted Carlin style gold deposits ƒ Active multi-million ounce mines (Jinfeng, Zimudang, Shuiyindong, Yata) ƒ Potential for high grades ƒ Shuiyindong y g ~ 16 ggm/t / www.eldoradogold.com 27

  28. Slide 28: Jinfeng Deposit Model

    Jinfeng g Deposit p Model Fault Controlled Ore Stratabound Ore www.eldoradogold.com 28

  29. Slide 29: Jinfeng District

    Jinfeng g District ƒ Jinfeng District Exploration 2010 Budget: $2.5 $ M ƒ Jinfengg JV ƒ 3 exploration licenses, 1 mining license ƒ Drill-testingg numerous structurallyy controlled, high grade targets (2.25m @ 19.24 gm/t in trenches) ƒ Jindu JV ƒ 3 exploration licenses (53 km2) ƒ Drill testing target

  30. Slide 30: White Mountain District

    White Mountain District www.eldoradogold.com 30

  31. Slide 31: White Mountain District

    White Mountain District ƒ White Mountain District Exploration 2010 Budget: $2.5M ƒ White Mountain Minesite Exploration ƒ Infill and stepout drilling: deposit remains open down-dip and along strike to northeast ƒ Dadongpo Exploration License (29 km2) ƒ Target definition: geophysical, geological progr

  32. Slide 32: Eastern Dragon District

    Eastern Dragon g District ƒ Eastern Dragon District E Exploration ploration 2010 Budget: $2.4 M ƒ 2 exploration licenses (~100 km2) ƒ Numerous high grade, epithermal Au+Ag veins with very little previous exploration ƒ Ore grades common in surface trenches 153.5g/t Au / 1340 g/t Ag 119.0g/t Au /743 g

  33. Slide 33: Eastern Dragon Exploration

    Eastern Dragon g Exploration p 26.8 gpt Au EL 53 N1-2s Eastern Dragon 15 0 gpt Au 15.0 selected trench and grab sample results 4.5 gpt Au jy 5.7 gpt Au Lode5 jy v? Si 5.1 gpt Au tf 9.6 gpt Au 7.7 gpt Au 0 1000m Mining License Lower Pleistocene Basalt N1-2s Tertiary sandy conglomerate 92.1 gpt Au ? j

  34. Slide 34: Tanjianshan District

    Tanjianshan j District ƒ Tanjianshan District Exploration 2010 Budget: $3.8M ƒ 323 zone resource definition drilling 323 Discovery Section: 15.5m ƒ QLT deeps resource definition drilling @15.8 g/t Au (QD-143) ƒ Target generation programs: ƒ Mapping ƒ RAB drilling programs www.eldoradogold.com 34

  35. Slide 35: China Generative Exploration

    China Generative Exploration p Distribution of gold deposits in China Bakyrchik Altay Shan Eastern Dragon Tianshan orogenic HLJ-Jilin low-S &pporphyry p y y Au epithermal & breccia Kumtor pipe/porphyry Au Muruntau White Mountain Tanjianshan Pulang orogenic & porphyry Au-Cu Jinfeng Golden Triangle Ca

  36. Slide 36: Turkey Exploration Budget

    Turkeyy Exploration p Budget g Generative Exploration: $1.7 M • Project j generation g and acquisition q Kişladağ: $4 M AS porphyry target: $0.9 M • Resource expansion • Geophysical surveys d illi g drilling • Drilling Efemçukuru: $1.5 M • Stepout, new vein targets drilling MH project: j t $2.0 $2 0

  37. Slide 37: Kişladağ Resource Drilling

    Kişladağ ş ğ Resource Drilling g ƒ Kişladağ Exploration 2010 Budget: $4.0 M ƒ Continuation of successful 2009 program of defining additional resources contiguous ti with ith presentt reserve ƒ 2009 resource growth: 32% increase in Measured and Indicated ounces www.eldoradogold.com 37

  38. Slide 38: Efemçukuru Exploration

    Efemçukuru ç Exploration p NW stepout ƒ Efemçukuru Exploration 2010 target Budget: $1.5 M ƒ Kestane Beleni northwest NOS stepout MOS ƒ Kokarpinar vein ƒ Preliminary drill test 2009: 3.7m @ 11.1 gm/t Au SOS ƒ N th ore shoot North h t iinfill fill d drilling illi www.eldoradogold.com 38

  39. Slide 39: Advanced Stage Porphyry Targets

    Advanced Stage g Porphyry p y y Targets g ƒ 2010 Exploration Budget: $1.8 M ƒ AS: mapping, geophysics target definition + drilling ƒ Sayaçik: drilling geophysical/geological targets defined in 2009 exploration program AS Au-Cu Porphyry Sayaçik www.eldoradogold.com 39

  40. Slide 40: Early-stage Exploration Programs

    Early-stage y g Exploration p Programs g ƒ 2010 Exploration Budget: $2.7 M ƒ MH IOCG prospect ƒ Detailed mapping ƒ Drilling of four targets defined by 2009 geophysical / geochemical / geological programs ƒ Konya-Sizma ƒ Phyllite-hosted y Au anomalyy ƒ Drill testing two target areas K Konya-Sizma Si

  41. Slide 41: Brazil Exploration

    Brazil Exploration p ƒ 2010 Exploration p Budget: g $4.1 M ƒ Tocantinzinho ƒ Six month program to test target areas outside of main deposit ƒ 4000 di 4000m diamond dddrilling illi ttargeting ti geochemical, h i l geophysical h i l anomalies li ƒ Reconnaissance mapping, sampling of artisanal workings

  42. Slide 42: Nevada Exploration Budget

    Nevada Exploration p Budget g ƒ Nevada Exploration p 2010 Budget: g $3.5 M ƒ Early stage stage, Carlin-style Carlin style gold targets Richmond ƒ Option agreements Mtn. Buffalo Cathedral Canyon. Well Green Monster www.eldoradogold.com 42

  43. Slide 43: Nevada Exploration

    Nevada Exploration p ƒ Drill-testing 4 grassroots projects through option agreements ƒ AuEx Ventures properties Buffalo Canyon Green Monster ƒ Bronco Creek properties Richmond Mountain Cathedral Well Buffalo Canyon Cathedral Well www.eldoradogold.com 43