MARA Holdings, Inc. · NASDAQ:MARA

MARA — Q3 2026 Earnings Presentation

18 slides from MARA's earnings presentation, Nov 9, 2026

  1. Slide 1: Q3 2026 Update

    Q3 2026 UPDATE NASDAQ: MARA MARA.COM NOVEMBER 9, 2026

  2. Slide 2: Disclosure

    Disclosure Investor Notice Forward-Looking Statements Investing in our securities involves a high This presentation contains forward-looking statements within the meaning of the federal securities laws. All degree of risk. Before making an investment statements, other than statements of historical f

  3. Slide 3: Delivering on MARA's Digital Infrastructure Triad

    Delivering on MARA’s Digital Infrastructure Triad AI Training, Inference, Token Factory POWER Owned & Operated Grid Connection Behind The Meter Critical IT Bitcoin Mining Public / Private Cloud Data Centers Digital Assets, Proof-of-Work 3

  4. Slide 4: Driving Higher Margins Through Vertical Integration

    Driving Higher Margins Through Vertical Integration Margin Integration 4

  5. Slide 5: Two Power Sites and a Partner to Deliver Them

    Two Power Sites and a Partner to Deliver Them OHIO TEXAS Long Ridge and Hannibal Matagorda >70% ~200 MW Up to 2 GW Up to $600M of the operating generation asset's of incremental behind-the-meter of potential capacity, subject to aggregate purchase price if all output is contracted under long-term ca

  6. Slide 6: Long Ridge Receives FERC Approval, Materially Expanding MARA's Owned Capacity

    Long Ridge Receives FERC Approval, Materially Expanding MARA’s Owned Capacity LONG RIDGE KEY METRICS $144M Annualized Adjusted EBITDA1 ~6,400 Btu/kWh heat rate 89% Highest capacity factor CCGT in PJM2 ~76% Energy sales hedged +1,600 Acres owned 100 MMcfd Q4 2025A gas supply ~$15 /MWh All-in operatin

  7. Slide 7: Building the Infrastructure Layer: Matagorda 2 GW Site to Anchor 4.8 GW Pipeline

    Building the Infrastructure Layer: Matagorda 2 GW Site to Anchor 4.8 GW Pipeline 1,200+ 2 GW $600M $1.2B+ Thousands ACRES GRID CAPACITY PURCHASE PRICE1 IN TEXAS OF JOBS based on post-closing powered land site by Apr 2028 milestone developments invested to date construction + full-time GRID CAPACITY

  8. Slide 8: Exaion: An Early Proof Point of the Power-to-Compute Model

    Exaion: An Early Proof Point of the Power-to-Compute Model TOTAL CONTRACT VALUE WHAT EXAION ADDS ABOVE THE INFRASTRUCTURE LAYER $79M Private cloud, open-weight models, inference as a service 4 years 100% Control of data, infrastructure and jurisdiction GPU-as-a-service take-or-pay: paid contract whe

  9. Slide 9: Optimizing our Balance Sheet by Turning Bitcoin Into Liquidity & Retiring Debt

    Optimizing our Balance Sheet by Turning Bitcoin Into Liquidity & Retiring Debt DREW SOLD AGGREGATE PROCEEDS FULLY REPAID $750M 13,597 BTC ~$1.1B $750M Bitcoin-collateralized loans drawn in sold after quarter-end at ~$81,0392 in bitcoin sale proceeds Bitcoin-collateralized loans repaid in August, bit

  10. Slide 10: Q3 2026 Financial & Operational Overview

    Q3 2026 Financial & Operational Overview Revenues Energized Hashrate1 BTC Holdings Decreased 35% YoY to $164M Up 18% YoY to 71.2 EH/S Decreased 36% to 34,012* from 52,850* at from 60.4 EH/S the end of Q3 2025 Net Income Total Debt BTC Production $632M, or $1.28/share, compared to Reduction of $1.4 b

  11. Slide 11: Trending BTC Production & Holdings

    Trending BTC Production & Holdings* Q3 2026 Bitcoin Holdings 57% 33% 28% 28% 26% Unrestricted | 14,752 57% Activated Bitcoin 53,822 52,850 Holdings 35,303 35,577 34,012 Pledged as Collateral | 17,852 Loaned | 1,408 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 *Subsequent to quarter-end, we sold 13,597 bi

  12. Slide 12: Q3 2026 Financial Performance

    Q3 2026 Financial Performance $ in millions REVENUES UNRESTRICTED CASH & TOTAL BTC HOLDINGS* $114,068 $252.4 $202.3 $87,498 $83,556 $174.6 $174.9 $164.2 $68,222 $58,524 $3,782.4 $6,848.8 $5,253.2 $2,921.2 53,822 52,850 $2,502.7 35,303 35,577 34,012 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q3 2025 Q4

  13. Slide 13: Building a Scalable Energy Network Through Strategic Site Expansion

    Building a Scalable Energy Network Through Strategic Site Expansion 1.4 GW 1.9 GW ~4.8 GW Operational Capacity Total Current Capacity Total Potential Capacity 1 Central Texas 417 MW 550 MW North Texas 78 MW 180 MW Owned Sites Central Ohio 60 MW 150 MW East Ohio 94 MW 227 MW Central Nebraska 134 MW 1

  14. Slide 14: Appendix

    Appendix

  15. Slide 15: Quarterly Financials: Q3 2026 vs. Q4 2025

    Quarterly Financials: Q3 2026 vs. Q4 2025 SUMMARY BALANCE SHEET (in millions) September 30, 2026 December 31, 2025 CASH & CASH EQUIVALENTS $ 946.5 $ 547.1 RESTRICTED CASH 12.0 12.0 DIGITAL ASSETS, CURRENT PORTION 1.8 2.4 OTHER RECEIVABLES 29.5 18.5 DEPOSITS 38.9 19.5 DERIVATIVE INSTRUMENT, CURRENT P

  16. Slide 16: Non-GAAP Reconciliation

    Non-GAAP Reconciliation (in thousands) UNAUDITED Q3 2026 Q2 2026 Q1 2026 Q4 2025 Q3 2025 RECONCILIATION TO ADJUSTED EBITDA NET INCOME (LOSS) ATTRIBUTABLE TO COMMON STOCKHOLDERS 634,357 (609,685) (1,259,619) (1,709,644) 123,128 NET INCOME (LOSS) ATTRIBUTABLE TO NONCONTROLLING INTERESTS (2,286) (1,632

  17. Slide 17: Historical Long Ridge Financials

    Historical Long Ridge Financials Three Months Ended Three Months Ended ($ thousands) 2025 2H Annualized1 September 30, 2025 December 31, 2025 Net (loss) income attributable to stockholders $ 566$ (45,699) $ (90,266) Equity-Based Compensation Expense - 5,636 11,272 Acquisition and Transaction Expense

  18. Slide 18: Thank You

    Thank You CONTACT US AT IR@MARA.COM