Sandfire Resources Ltd · ASX:SFR

Sandfire Resources — Diggers & Dealers 2012

30 slides from Sandfire Resources's conference presentation, Aug 6, 2012

  1. Slide 1: A new chapter: Australia's newest copper producer

    For personal use only A new chapter Australia’s newest copper producer Diggers & Dealers – August 2012

  2. Slide 2: Important Information and Disclaimer

    Important Information and Disclaimer Forward-looking statements and Competent Person’s Statement Competent Person’s Statement • The information in this public presentation that relates to Exploration Results and Mineral Resources is based on information compiled by Mr John Evans who is a Fellow of F

  3. Slide 3: Sandfire – Our Vision

    Sandfire – Our Vision A mining company focused on shareholder returns • Deliver superior returns to our owners from the premier high- For personal use only grade DeGrussa VMS copper-gold mine • Discover additional VMS deposits within the emerging Doolgunna mineral field • Explore for, develop and mi

  4. Slide 4: Sandfire – Snapshot

    Sandfire – Snapshot A position of strength and opportunity • Discovery to production: less than 3 years (2009 to 2012) For personal use only • Delivery of project milestones on time and on budget • Open pit operations and DSO shipments underway • Construction and development approaching completion:

  5. Slide 5: Corporate Snapshot

    Corporate Snapshot Australia’s newest copper producer For personal use only Issued Capital 151.6M Shares, 9.3M options Board Derek La Ferla Non-executive Chairman Karl Simich Managing Director / CEO Market Capitalisation ~$1 billion W. John Evans Executive Technical Director Key Projects DeGrussa (D

  6. Slide 6: Sandfire – the Strategy

    Sandfire – the Strategy A multi-pronged approach to building a leading diversified mining company For personal use only • DeGrussa Project • Targeting additional • Zinc-lead: NT • Copper-gold • Targeting quality • 77ktpa Cu, VMS deposits/ • IOCG Cu-Au: QLD, exploration in Chile, assets which can 36o

  7. Slide 7: Sandfire – the Strategy

    Sandfire – the Strategy A multi-pronged approach to building a leading diversified mining company For personal use only • DeGrussa Project • Targeting additional • Zinc-lead: NT • Copper-gold • Targeting quality • 77ktpa Cu, VMS deposits/ • IOCG Cu-Au: QLD, exploration in Chile, assets which can 36o

  8. Slide 8: Project – Key Facts

    DeGrussa Project – Key Facts Mining operation taking shape For personal use only Mining: Open pit + underground Mine Life: +7 years Processing: +1.5Mtpa on-site concentrator 10.72Mt @ 5% Cu, 1.7g/t Au Production: 541kt Cu, 599koz Au Open pit DSO 38kt Cu (25.6%), 12koz Au (2.5g/t) contained Ore Reser

  9. Slide 9: Hitting the milestones – April 2011

    DeGrussa – hitting the milestones Discovery to production in three years… • April 2011 For personal use only Underground and open pit mine development commenced Page: 9

  10. Slide 10: Hitting the milestones – June 2011

    DeGrussa – hitting the milestones Discovery to production in three years… • June 2011 For personal use only Definitive Feasibility Study delivered Page: 10

  11. Slide 11: Hitting the milestones – September 2011

    DeGrussa – hitting the milestones Discovery to production in three years… • September 2011 For personal use only $390M Project Loan Facility Page: 11

  12. Slide 12: Hitting the milestones – November 2011

    DeGrussa – hitting the milestones Discovery to production in three years… • November 2011 For personal use only First DSO sales contract signed Page: 12

  13. Slide 13: Hitting the milestones – February 2012

    DeGrussa – hitting the milestones Discovery to production in three years… • February 2012 For personal use only First DSO and underground ore mined Page: 13

  14. Slide 14: Hitting the milestones – May 2012

    DeGrussa – hitting the milestones Discovery to production in three years… • May 2012 For personal use only First shipment of DSO Page: 14

  15. Slide 15: Hitting the milestones – July 2012

    DeGrussa – hitting the milestones Discovery to production in three years… • July 2012 For personal use only First copper concentrate sales contract signed Page: 15

  16. Slide 16: Hitting the milestones – September 2012

    DeGrussa – hitting the milestones Discovery to production in three years… • September 2012 For personal use only Concentrator commissioning Page: 16

  17. Slide 17: Growth Potential

    DeGrussa – Growth Potential Targeting first production from Oxide Copper Ore Reserves by mid-CY 2013 For personal use only • Maiden Oxide Copper Ore Reserve (Proved + Probable) for DeGrussa open pit • 1.04Mt @ 2.3% Cu (23kt contained copper) • Suitable processing route developed • Design studies and

  18. Slide 18: Sandfire – the Strategy

    Sandfire – the Strategy A multi-pronged approach to building a leading diversified mining company For personal use only • DeGrussa Project • Targeting additional repeat • Zinc-lead: NT • Copper-gold • Targeting quality • 77ktpa Cu, VMS deposits/ lenses • IOCG Cu-Au: QLD, exploration in Chile, assets

  19. Slide 19: Corridor of Riches

    DeGrussa – “Corridor of Riches” Minimal exploration conducted along +30km prospective corridor For personal use only • VMS mineralising environment confirmed over +30km long, 1.2km wide corridor • Minimal exploration below 100m: host sequence at depth still to be explored • DeGrussa deposit extends

  20. Slide 20: Exploration

    DeGrussa Exploration Focus on discovering additional high-value VMS copper-gold deposits at Doolgunna • +$20M exploration budget over next 12 months For personal use only • Systematic and scientific approach • Extensive regional drilling to define prospective VMS sequences • Re-logging and spectral

  21. Slide 21: Sandfire – the Strategy

    Sandfire – the Strategy A multi-pronged approach to building a leading diversified mining company For personal use only • DeGrussa Project • Targeting additional • Zinc-lead: NT • Copper-gold • Targeting quality • 77ktpa Cu, VMS deposits/ • IOCG Cu-Au: QLD, exploration in Chile, assets which can 36o

  22. Slide 22: Australian Regional Exploration

    Australian Regional Exploration Extensive portfolio with a focus on discovering Tier One deposits • Reviewing high-quality, asset-driven exploration For personal use only opportunities in Australia • Focus outside Doolgunna is on IOCG copper-gold, porphyry-style copper-gold and lead-zinc-silver • $5

  23. Slide 23: Sandfire – the Strategy

    Sandfire – the Strategy A multi-pronged approach to building a leading diversified mining company For personal use only • DeGrussa Project • Targeting additional • Zinc-lead: NT • Copper-gold • Targeting quality • 77ktpa Cu, VMS deposits/ • IOCG Cu-Au: QLD, exploration in Chile, assets which can 36o

  24. Slide 24: International Exploration and Business Development

    International Exploration and Business Development Focused team seeking opportunities globally • Targeting high quality, asset-driven opportunities For personal use only • Projects with genuine potential to add value • Strong focus in South America • Copper-gold, gold, base metals • In-house Busines

  25. Slide 25: Sandfire Summary

    Sandfire Summary Australia’s newest copper producer entering its next chapter of growth For personal use only • DeGrussa development nearing completion: Q3 2012 • Concentrator commissioning: Q3 2012 • High-margin production profile • Exceptional cash flow • Exploration to establish a VMS copper-gold

  26. Slide 26: A new chapter: Australia's newest copper producer

    For personal use only A new chapter Australia’s newest copper producer Diggers & Dealers – August 2012

  27. Slide 27: Appendix: Competent Person's Statements

    Appendix: Competent Person’s Statements Competent Person’s Statement – Mineral Resources • The information in this report that relates to Mineral Resources (except the Indicated Resource of Supergene Chalcocite) is based on information compiled by Diederik Speijers who is a Fellow of the Australasia

  28. Slide 28: Appendix – DeGrussa: Mineral Resources

    Appendix – DeGrussa: Mineral Resources Table 1: DeGrussa Copper-Gold Project – Mineral Resource Statement as at 31 March 2012 For personal use only Resource Tonnes Copper Contained Contained Competent Gold (g/t) Zone - in situ Category (mt) (%) Copper (t) Gold (oz) Person Au Laterite Measured 0.04 0

  29. Slide 29: Appendix – DeGrussa: Ore Reserves

    Appendix – DeGrussa: Ore Reserves Table 2: DeGrussa Copper-Gold Project – 31 March 2011 Ore Reserve Statement For personal use only Reserve Treatment Deposit Tonnes Copper Gold Contained Contained Classification Destination Material (Mt) (%) (g/t) Copper (t) Gold (oz) Proved Ore Sale Laterite Gold 0

  30. Slide 30: Appendix – DeGrussa: Ore Reserves

    Appendix – DeGrussa: Ore Reserves Table 3: DeGrussa Copper-Gold Project – Ore Reserve Statement as at 31 March 2012 For personal use only Tonnes Copper Gold Contained Contained Deposit Reserve Category Mining Method (Mt) (%) (g/t) Copper (t) Gold (oz) Laterite Gold Proved Open Pit 0.10 - 3.0 - 9,000

Sandfire Resources — Diggers & Dealers 2012 on 6ix