Regenx Tech Corp · CSE:RGX
Regenx Tech — Mineworx Technologies — Corporate Update (February 2022)
10 slides from Regenx Tech's corporate update, February 2022
Slide 1: Corporate Update
FEBRUARY 2022 www.mineworx.net CORPORATE UPDATE TSX-V: MWX I OTCQB: MWXRF I FSE:YRS Greg Pendura 101 Lafleur Drive St. Albert, AB President & CEO T8N 7M8
Slide 2: Dear Shareholders
DEAR SHAREHOLDERS 2022 promises to be a significant year as we reach key milestones and formulate our new corporate identity. Positioning ourselves strongly in the Clean Tech space will be extremely beneficial for the Company in the future and will allow us better access to institutional investors.
Slide 3: Cehegin Iron Ore Newco
CEHEGIN IRON ORE NEWCO We have mentioned our intention to spin off our Spanish Cehegin iron ore concession into a newly formed public company. We are well on our way to finalizing the structure and the relevant documents for our upcoming shareholder Special Meeting, including the preparation of the
Slide 4: Spain drill program update
The drill program in Spain is moving very slowly due to terrain conditions and the lack of availability of additional drill equipment and experienced drill operators in Spain at this time. There is pent up demand worldwide for these services resulting in lengthy delays in many projects. We are in ou
Slide 5: Small scale production facility approval process
The approval process for the small scale 100,000 t/year production facility is going well. All relevant people and departments have verbally agreed with the project, including the environmental department. The last submission is an engineering report being completed on dewatering the large reservoir
Slide 6: Rebranding - a Clean Tech Company
MINEWORX Rebranding- a Clean Tech Company The rationale behind the spin out of our iron ore asset is not only to enhance shareholder value, but also the start of a rebranding program for Mineworx which will include a name change. Moving forward we wish to identify ourselves as a Clean Tech company d
Slide 7: Pilot Plant Commissioning
Pilot Plant Commissioning The pilot plant in Tennessee is about to begin operations. We have had unfortunate delays primarily due to changing the location from our JV partner’s location to a different building close to their main operation. This triggered permitting issues for both the equipment in
Slide 8: Pilot plant and joint venture partner update
Installing the pilot plant in a larger space will allow us to build a large scale, fully operational lab. This will allow for more extensive operational testing as well as for future development opportunities when the commercial plant is operational. In the future the pilot plant will be used to det
Slide 9: Davis Recycling comments and commercial plant timeline
Ben Davis, President of Davis Recycling Inc. stated “I have been frustrated by the bureaucratic delays created by the city but have been extremely impressed by the team Mineworx has assembled and the work they have been accomplishing in the time they have been onsite in Tennessee. PGM Renewal is goi
Slide 10: Shareholder inquiries
Shareholder inquiries: Greg Pendura President & CEO Mineworx Technologies P: 780-800-0726
Mineworx Technologies — Corporate Update (February 2022) on 6ix