Resolute Mining Limited · ASX:RSG

Resolute Mining — Q1 2024 Earnings Presentation

14 slides from Resolute Mining's earnings presentation, May 1, 2024

  1. Slide 1: Q1 2024 Activities Report

    30 April 2024 Q1 2024 Activities Report ASX/LSE - RSG 1

  2. Slide 2: Disclaimer

    This presentation contains information about Resolute Mining This presentation includes certain forward-looking statements, ‘Maiden Mineral Resource at Tomboronkoto’ announced on 24 Limited (Resolute or the Company) and its activities that is including statements regarding our intent, belief or curr

  3. Slide 3: Resolute Overview

    Resolute Overview Multi-asset gold producer with near-term organic growth potential  Two producing gold mines, the Syama Gold Mine in Mali and the Mako Resources Production Gold Mine in Senegal 11.2Moz 345-365koz  Attractive exploration portfolio (Group) (2024 guidance)  Listed on ASX and LSE, ap

  4. Slide 4: Q1 2024 Highlights

    Q1 2024 Highlights Continued healthy cash flows drive net cash position further Operations AISC Cash Flow Group AISC1 of $1,487/oz despite the lower Q1 operating cash flow after working Production of 76,351oz, 5% lower QoQ, due expected gold production capital changes of $62m (Q4 2023: $30m) to sche

  5. Slide 5: Production and AISC Positioned for Substantial Improvements

    Production and AISC Positioned for Substantial Improvements AISC expected to continue to decrease across all operations Production Growth Focus: Mako Syama Guinea Areas for Organic  Near-term: Syama Phase I Oxide Plant Production Growth Conversion & Mako mine life extension 700 2000  Medium to lon

  6. Slide 6: Operational Overview

    Operational Overview 6

  7. Slide 7: Syama Operational Highlights

    Syama Operational Highlights Scheduled maintenance meant a softer Quarter was expected Sulphide Operation March December March  Ore mined was 3% lower than the prior Quarter but at a 5% higher grade as Summary Units 2024 2023 Change 2023 production stopes were in higher-grade zones that had started

  8. Slide 8: Mako Operational Highlights

    Mako Operational Highlights Stable Q1 with production to strengthen over subsequent quarters Operational Highlights March December March Summary Units 2024 2023 Change 2023  Ore tonnes mined and mined grade was slightly below the prior Quarter Quarter Quarter Quarter and in line with expectations 

  9. Slide 9: Senegal Exploration Update

    Senegal Exploration Update Drilling ramped up at Tomboronkoto and set to commence at Bantaco Tomboronkoto (16km east of Mako):  On 24 January 2024 an initial Inferred MRE of 264koz grading 2.2g/t Au (at a 1 g/t cut-off) or 403koz grading 1.2 g/t (at a 0.5 g/t cut-off) was announced with a majority

  10. Slide 10: Guinea Exploration Update

    Guinea Exploration Update An initial MRE for Mansala expected in H2 2024 Resolute has five permits in Guinea located along the margin of the Siguiri Basin  Diamond and Reverse Circulation drilling continued at the Mansala Prospect throughout Q1  A program of RC drilling was carried out in conjunct

  11. Slide 11: Financials

    Financials See

  12. Slide 12: Financial Results

    Financial Results Strong cash flow generation with more to come in 2024 Quarterly Production and AISC Q1 Financial Highlights Ounces AISC $/oz  Quarterly gold sales of 69,000oz (vs 79,480oz in Q4 2023) at an 100,000 1,600 average sales price of $1,950/oz (vs $1,954/oz in Q4 2023) as 90,000 84,372 1

  13. Slide 13: Financial Highlights

    Financial Highlights Another Quarter of strong cash flows, net cash position increasing Cash Flow Waterfall Resolute is now fully un-hedged  During the March Quarter Net Cash increased by approximately $20m to $34m (Q4 2023: $14m)  Final $25m repayment made on the Term Loan Facility leaving Resolu

  14. Slide 14: www.rml.com.au

    Resolute www.rmi.com.au