  1. Slide 1: Contract Development update

    Contract Development update

  2. Slide 2: Agenda

    Agenda  STOR  Reactive  Constraint Management Service  Firm Frequency Response / Fast Reserve  Improvements to contract transparency  Constraints  Commercial Frequency Response  Balancing Mechanism System Replacement

  3. Slide 3: STOR Annual Review

    STOR Annual Review  General STOR Standard Contracts Terms Review  Develop longer-term services in STOR - meet future reserve requirement - promote competition - enhance efficiency

  4. Slide 4: STOR Annual Review

    STOR Annual Review  Key Areas of Review - timescale of the longer-term services - use of indexation for utilisation payments - dealing with uncertain future STOR windows

  5. Slide 5: STOR Annual Review

    STOR Annual Review Indicative Timetable of the Review  June - August 08 Develop the proposal of STOR longer-term services  September - October 08 Invite the industry to comment on the proposal  November - December 08 Consider the feedback, finalise and publish the Standard Contract Terms  We wou

  6. Slide 6: Agenda

    Agenda  STOR  Reactive  Constraint Management Service  Firm Frequency Response / Fast Reserve  Improvements to contract transparency  Constraints  Commercial Frequency Response  Balancing Mechanism System Replacement

  7. Slide 7: Reactive Power Market Review

    Reactive Power Market Review  Reasons for review:  Low and decreasing number of participants 100% 80% 60% Declined to tender 40% Unsuccessful 20% tenders 0% Successful 1 2 3 4 5 6 7 8 9 101112131415161718192021 tenders Tender round

  8. Slide 8: Reactive Power Review

    Reactive Power Review  Reasons for review:  Low and decreasing number of participants  Comments received regarding long lead times between submission of tenders and commencement of Market Agreement  Minimal participation in Enhanced Reactive service  Complex and onerous assessment process

  9. Slide 9: Reactive Power Review (Cont.)

    Reactive Power Review (Cont.)  Scope of Review:  Tender process – timescales, frequency  Simplification of tender process  Simplification of assessment process  Consider use of Framework Agreements

  10. Slide 10: Reactive Power Review (Cont.)

    Reactive Power Review (Cont.)  Indicative Timescales:  June - August 08: Develop proposals for Reactive Power market  September - October 08: Seek feedback from industry on proposals  November 08 - January 09: Raise CUSC Amendment Proposal  Feedback  We would welcome further feedback on the cu

  11. Slide 11: Agenda

    Agenda  STOR  Reactive  Constraint Management Service  Firm Frequency Response / Fast Reserve  Improvements to contract transparency  Constraints  Commercial Frequency Response  Balancing Mechanism System Replacement

  12. Slide 12: Constraint Management Service: Update

    Constraint Management Service: Update  Keen to encourage participation in the service  Feedback suggests potential service modifications: ‘BMU level’ rather than ‘station level’ Standardised fuel efficiency factors Would allow tenders for a proportion of Would allow greater transparency of price

  13. Slide 13: Agenda

    Agenda  STOR  Reactive  Constraint Management Service  Firm Frequency Response / Fast Reserve  Improvements to contract transparency  Constraints  Commercial Frequency Response  Balancing Mechanism System Replacement

  14. Slide 14: Review to date

    Review to date Fast Reserve  New Standard Terms and Conditions Posted on the website for comment October 2007  Specified tender months for longer-term tenders  Additional flexibility for providers who need to invest Firm Frequency Response  New Standard Terms and Conditions Posted on the website

  15. Slide 15: Comments received

    Comments received Fast Reserve  The ability to tender more frequently for longer-term tenders  Timing of multi month tenders should be five days earlier  For longer-term tenders indexation should be considered (RPI or market index) Firm Frequency Response  The ability to tender more frequently f

  16. Slide 16: FFR/Fast Reserve Review 2008

    FFR/Fast Reserve Review 2008  Way Forward  More work required to establish revised terms  Partnership between Fast Reserve and FFR review to ensure consistency  Working Group 4th July, in Warwick to debate relevant enhancements to both services  Please direct queries / request place on working

  17. Slide 17: Agenda

    Agenda  STOR  Reactive  Constraint Management Service  Firm Frequency Response / Fast Reserve  Improvements to contract transparency  Constraints  Commercial Frequency Response  Balancing Mechanism System Replacement

  18. Slide 18: Improvements to contract transparency

    Improvements to contract transparency  Industry feedback to improve transparency but  Need to balance between commercial confidentiality and transparency  Less interest to offer services due to sensitive information being shared  Failure to agree amendments to existing agreements Balanced agains

  19. Slide 19: Improvements to contract transparency

    Improvements to contract transparency  Need to ensure data items that may be published are specified in agreement  Limit data items to those necessary and only to better facilitate licence conditions  efficient, economic and facilitate competition  Two areas presently being reviewed  Constraint

  20. Slide 20: Proposal to publish constraints data

    Proposal to publish constraints data  Constraints data published monthly on the National Grid website  Data based on Settlement data  Data published within 2 weeks of receipt of Settlement data, or 6 weeks after end of month

  21. Slide 21: Proposal to publish constraints data

    Proposal to publish constraints data  Data will be aggregated into  Within Scotland  ‘Cheviot’ Scotland – England boundary  Within England & Wales (broken down as necessary)  Data will be separated into import and export constraints  Separate tables will be provided for  BM actions  Trades 

  22. Slide 22: Proposal to publish constraints data

    Proposal to publish constraints data  BM actions and Trade data will cover  Energy Costs  Constrained Volume  Average Price of Action  Average Energy Replacement Price  Total Direct Cost  Sterilised Headroom Costs  Margin Replaced  Average Margin Replacement Price  Average Energy Reference

  23. Slide 23: Proposal to publish constraints data

    Proposal to publish constraints data  Constraint Contract data  Constrained Volume  Time and dates active  Cost  Intertrip data  No of times armed  Arming hours  Availability payments  Cost

  24. Slide 24: Commercial Frequency Response – What is it?

    Commercial Frequency Response – What is it?  Established prior to CAP047  Allows providers to offer an alternative more cost effective frequency service  Where the cost of providing the mandatory service was prohibitively high, a lesser more cost effective service could be offered  If plant was

  25. Slide 25: Commercial Frequency Response – Why Change?

    Commercial Frequency Response – Why Change?  CAP047 introduced to provide a competitive market for Mandatory Service  It established a mechanism to allow monthly price changes and publication of these prices and capabilities  Transparency allows providers to adjust their prices in response to mar

  26. Slide 26: Commercial Frequency Response – Why Change?

    Commercial Frequency Response – Why Change?  Feedback from service participants  Unable to see prices and capabilities of Commercial Frequency Response  Further transparency will lead to more efficient pricing and facilitate better competition

  27. Slide 27: Commercial Frequency Response – What Changes are required?

    Commercial Frequency Response – What Changes are required?  Commercial Frequency Response clauses in the providers agreements will need to be changed to:-  Limit price changes to once a month with a cut-off date co-incident with the closure of the FRPS system  To allow publication of the prices a

  28. Slide 28: Next Steps

    Next Steps  Further feedback is requested before moving forward with any changes  Are we proposing to publish too much / too little data?  Do you feel this will better facilitate our licence objectives?  Do you feel this will impact service provision?  Please direct feedback to David Smith on 0

  29. Slide 29: Agenda

    Agenda  STOR  Reactive  Constraint Management Service  Firm Frequency Response / Fast Reserve  Improvements to contract transparency  Constraints  Commercial Frequency Response  Balancing Mechanism System Replacement

  30. Slide 30: National Grid Balancing Mechanism (BM) System Replacement

    National Grid Balancing Mechanism (BM) System Replacement Current BM System • BM system is the tool used by the System Operator for the real-time management of supply and demand • It interfaces with market participant systems and settlement systems, and delivers data to the BMRS • Current system com

  31. Slide 31: National Grid BM System Replacement (cont.) Industry views

    National Grid BM System Replacement (cont.) Industry views • A number of significant industry changes on the horizon • National Grid wishes to gain an understanding of what this means for industry participants in terms of what the BM system needs to achieve • Industry views will enable us to more fu

  32. Slide 32: National Grid BM System Replacement (cont.) Industry Engagement Process

    National Grid BM System Replacement (cont.) Industry Engagement Process • Initiate industry engagement process – June ’08 Ops Forum • Industry workshop – July ‘08 • Issue consultation – August ‘08

National Grid — Operational Forum June 2008 on 6ix