Slide 1: Lake Erie Works Community Liaison Committee Meeting
Lake Erie Works Community Liaison Committee Meeting 12 June 2019
Slide 2: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 3: Know Your Emergency Exits
Know Your Emergency Exits Review Evacuation Routes of the room you are located in
Slide 4: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 5: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 6: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 7: Site-Specific Standard Order (Particulates): Performance Review – Daily
Site-Specific Standard Order (Particulates): Performance Review – Daily Date Doors Lids Off-takes (% Leaks) (% Leaks) (% Leaks) 2015 Limits 54% 2% NA (July 2 start) 2016 Limits 32% 2% NA 2017-2019 Limits 10% 2% 5% 2020 Limits 5% 1% 4% Mar 1 – May 31, 2019 1.11-9.52% 0 – 1.83% 1.22 – 5.0% Range (6.34
Slide 8: Performance Review – 30 Day Rolling Averages
Site-Specific Standard Order (Particulates): Performance Review – 30 Day Rolling Averages Date Doors Lids Off-takes Charging (% Leaks) (% Leaks) (% Leaks) (sec) (log avg) 2015 Limits 38% 0.8% 25% 12 sec (July 2 start) 2016 Limits 22.5% 0.8% 15% 12 s 2017-2019 Limits 7% 0.8% 4.2% 12 s 2020 Limits 4%
Slide 9: Performance Review – Daily Observations – Pushing Emissions
Site-Specific Standard Order (Particulates): Performance Review – Daily Observations – Pushing Emissions Date Pushing Emission (opacity %) 2015 Limit (July 2 start) ≥ 50% 2016 – 2018 ≥ 50% 2019 ≥ 40% 2020 ≥ 30% Mar 1 – May 31, 2019 Range 0 - 66% (Average) (10.95%) Mar 1 – May 31, 2019 Operational Ad
Slide 10: Performance Review – Additional Items
Site-Specific Standard Order (Particulates): Performance Review – Additional Items • There were no community complaints for the period of Mar 1 to May 31, 2019 • MECP to provide verbal comments
Slide 11: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 12: Cokemaking Update
Cokemaking Update 12 June 2019 Pete Schiestel, Division Manager, Cokemaking
Slide 13: Add Text Here
11:57:54 AM 06/1
Slide 14: STELCO
STELCO
Slide 15: STELCO
STELCO *
Slide 16: STELCO
STELCO *
Slide 17: Biz pers
= 7 be " . . Biz 2 pers
Slide 18: Thank You.
Thank You. stelcocanada.com
Slide 19: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 20: Lake Erie Works Coal Field Dust Management
Lake Erie Works Coal Field Dust Management 12 June 2019 Barry Stefureak, Area Manager, Blast Furnace and Dock
Slide 21: Dust Management Plan 2019
Dust Management Plan 2019 Research Reviewed dust control plan from prior years and identified opportunities for improvement. Plan • Seal unused north side of coal field with sealant. • Utilize Water Tankers during the day and night for dust suppression. • Conducted meetings with all crews to discuss
Slide 22: Dust Management Plan 2019
Dust Management Plan 2019 Plan • Integrate detailed weather forecast information which allows us to be proactive in using our coal dust suppression tools effectively. Tools • Envirobind ET Sealant on Coal piles • Internet – Weather Forecast Website. Allows operators to be proactive in using dust con
Slide 23: Dust Management Plan 2019 Sprinkler System
Dust Management Plan 2019 Sprinkler System History • In 2016 we developed a sprinkler system for our coal field with input from community stakeholders • Sprinkler system consisted of 3 towers. One per coal pile. Today • Our 2019 sprinkler system consists of 7 towers and is controlled via a computer
Slide 24: Thank You.
Thank You. stelcocanada.com
Slide 25: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 26: Dust and Emission Control: Lake Erie Works Baghouses
Dust and Emission Control Lake Erie Works Baghouses June 12th, 2019 Garret Urie, Area Manager Primary Utilities
Slide 27: Lake Erie Works Baghouses
Agenda Slide Lake Erie Works Baghouses 1) Baghouse Basics • Forced Air Vs. Induced (Pulled) Air • General Baghouse Layout 2) Primary • Cast House Baghouse • Stock House Baghouse 3) Steelmaking • Secondary Ventilation System (SVS) Baghouse • Dedust (Flux and Ladle Additive Control) Baghouse • Ladle T
Slide 28: Forced Air Vs. Induced Air
Forced Air Vs. Induced Air CHBH Forced Air Over Temperature Stack System Dirty Air Fan Dampers Spark Arrestor E-12
Slide 29: Forced Air Vs. Induced Air
Forced Air Vs. Induced Air Stock House Baghouse Flow Layout SHBH Induced Air System Clean Air Outlet Clean Air Stack Dirty Air Inlet Waste Dust
Slide 30: General Baghouse Cast House Layout
General Baghouse Cast HouseLayout Baghouse Flow Layout Clean Air (99% Removal Efficient) CELL #1 CELL #2 CELL #3 CELL #4 CELL #5 CELL #6 CELL #7 Dirty Air Flow Waste Dust Waste Dust Lake Erie Works – Primary Utilities By: Tyler Deighton
Slide 31: Ironmaking Operations & Raw Material Handling
Ironmaking Operations & Raw Material Handling SHBH (StockHouse BagHouse) • 9 Cells each with --- 252 Filter Bags
Slide 32: Ironmaking Operations & Raw Material Handling
Ironmaking Operations & Raw Material Handling CHBH (CastHouse BagHouse) • 7 Cells each with 348 Filter Bags
Slide 33: Steelmaking & Continuous Casting
Steelmaking & Continuous Casting SVS Baghouse (Secondary Ventilation System) • Removing dust particulates and hot gas fumes in the BOF(Basic Oxygen Furnace) shop which will be generated during the charging of the vessel with hot metal and scrap. • 6 Collection Hoods: Charging Side of each Vessel, Em
Slide 34: Steelmaking & Continuous Casting
Steelmaking & Continuous Casting Dedust Baghouse (Flux and Ladle Additive Control) • Removing dust generated by material handling at the Ladle Additive Bins and Trippers and all Feeder and Conveyor transfer points and all Weigh Hoppers. • There are 41 points in the BOF that collect dust particles. •
Slide 35: Steelmaking & Continuous Casting
Steelmaking & Continuous Casting RHOB Baghouse (Ruhrstahl Heraeus Oxygen Blowing) • Removing dust generated by material handling at the RHOB storage bins • There are 17 points in the RHOB that collect dust particles • 4 module, pulse air type baghouse containing 288 bags Powder Blowing Baghouses • F
Slide 36: Thank You.
Thank You. stelcocanada.com
Slide 37: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 38: 2019 CLC Meeting Dates
2019 CLC Meeting Dates Thurs. March 21 Wed. June 12 Wed. Sept. 18 Wed. Dec. 11
Slide 39: Agenda
Agenda 1. Welcome and Safety Contact 2. Review and Approval of Agenda 3. Review and Approval of Minutes of 21 March 2019 Meeting 4. Performance under O.Reg. 419/05 Site Specific Standard Order – Particulates 5. Cokemaking Update 6. Dust management – Coalfields 7. Examples of Emissions Control at LEW
Slide 40: Thank You.
Thank You. stelcocanada.com