  1. Slide 1: Enabling India's Energy Transition

    GE T&D India Limited ENABLING INDIA’S ENERGY TRANSITION Analyst Presentation Q2 Financial Year 2021-22

  2. Slide 2: Disclaimer

    DISCLAIMER This presentation has been prepared solely for the use at analyst/ investor presentation. By attending the meeting where this presentation is made, or by reading the presentation slides, you agree to be bound by the following limitations- • The forward-looking information and statements c

  3. Slide 3: Changes to Board

    Changes to Board Mr. Rajendra Sheshadri Mr. Sushil Kumar Iyer appointed as the appointed as Whole-time Director with effect from Director and CFO with October 1, 2021 effect from January 1, 2022 Mr Emanuel Bertolini and Mr Gaurav Negi ceased to be directors of the company with effect from October 1,

  4. Slide 4: Executive Summary

    Executive Summary • Q2 FY 21-22 Orders booking at 6.3 BINR vs 5.4 BINR in Q2 FY 20-21, up 18% yoy • Q2 FY 21-22 Sales at 8.5 BINR vs 8.7 BINR in Q2 FY 20- 21, down 2% yoy • Q2 FY 21-22 Loss After Tax at 77 MINR vs Profit After Tax of 86 MINR in Q2 FY 20-21 • Continuous Focus on operational excellenc

  5. Slide 5: Creating the Grid of Future | Key Commissioning

    Creating the Grid of Future | Key Commissioning 5x220kV AIS Bays, 3x33kV Switchboards 2x765kV AIS Extension Bays with 7x 1 Bay along with line successfully 8x400kV bays, 4x220kV, 5x132kV GIS with 3x125 MVA Transformers for 80MVAr Line Reactors charged charged for Doosan at Obra Bays, 2x500 MVA ICTs

  6. Slide 6: Making In India for the World

    Making In India for the World Factory Spotlight : Pallavaram • Pallavaram Site since 1958 : Pioneer in Grid Automation and Protection Controls • One of the largest relay manufacturing and panel integration facility in Asia. • Making in India for the World – Exports to more than 60 countries • 20 mil

  7. Slide 7: Lean Week

    LEAN WEEK President Kaizen Event • HVS team at Padappai introduced Flow Line for ME4 drives in to cater to global requirements for meeting the $ 3M top line • 15 Kaizens including ergonomics - 90% reduction in Manufacturing Lead times , product & people travel distance reduction by 13 % and 30% resp

  8. Slide 8: Order Intake

    ORDER INTAKE Q2 & H1’ FY 2021-22 Key Orders booked during Q2, FY 21-22 (₹ in millions) • Multiple contracts by Bhutan Power Corporation 11,064 (BPC), to build four Gas-Insulated Substations (GIS) in Bhutan on a turnkey basis. 9,821 • 500 MVA 765KV Power Transformers from PowerGrid Corporation of Ind

  9. Slide 9: Financial Data

    Financial Data Q2 & H1 FY 2021-22 (₹ in millions) Q2 Q2 H1 H1 Change Change 2021-22 2020-21 2021-22 2020-21 Sales 8,517 8,709 -2.2% 14,898 15,137 -1.6% EBITDA 199 428 -53.6% 213 431 -50.6% % of Sales 2.3% 4.9% -2.6 pts 1.4% 2.8% -1.4 pts Profit Before Tax (96) 132 -173.4% (349) (131) -167.1% % of Sa

  10. Slide 10: Orders, Sales and Backlog Details

    Orders, Sales and Backlog Details (₹ in millions) Q2 Orders H1 Orders Domestic Domestic Order in Hand 3027, 48% 4717, 43% Exports Exports 3314, 52% 6347, 57% 7905, 19% Private State Utilities Central Utilities & PSU 7665, 18% 25933, 63% Q2 Sales H1 Sales Domestic 3439, 23% 2130, 25% Exports Domestic

  11. Slide 11: Thank You

    THANK YOU Contact us: Suneel Mishra Investor Relations Officer suneel.mishra@ge.com Anshul Madaan Head – Communications & PR anshul.madaan@ge.com http://www.ge.com/in/ge-td-india-limited