First Quantum Minerals Ltd. · TSX:FM

First Quantum Minerals — Investor Presentation (December 2012)

26 slides from First Quantum Minerals's investor presentation, Dec 12, 2012

  1. Slide 1: Kevitsa Operation

    FQM Kevitsa Mining Kevitsa Operation Dec 12, 2012 Finlands Newest Cu/Ni Producer

  2. Slide 2: Overview of the site

    Overview of the site FQM Kevitsa Mining

  3. Slide 3: Kevitsa Snapshot

    Kevitsa Snapshot Key Data Ramp up to Commercial Production Capital Cost ~ US$480M Weathered Ore Initial feed with lower Employees ~ 290 by end 2013 recoveries Mine Life ~20yrs @ 7.5Mtpa Face Shovel PC5500, PC8000 mid 2013 Production Design levels in 2013 Haul Trucks CAT 793 (6) CAT 795 (2) LOM Grade

  4. Slide 4: Kevitsa

    Kevitsa Commissioning Ramp - up Operations Product Opportunities • Safety Vision in • Producing 300tpd of • Increasing truck road • Projects/Ops • Primary crusher capacity possible place Ni/Cu Con’s personnel worked issues initially well together • Rail options to Port • Weathered ore • 15 – 20 truc

  5. Slide 5: Kevitsa – milestones

    Kevitsa – milestones 2013 Expansion Permit to 10 Mtpa ‘First Concrete June 2010’

  6. Slide 6: Kevitsa – hitting the milestones

    Kevitsa – hitting the milestones 2013 Expansion Permit to 10 Mtpa ‘Commissioning during Winter Successful’

  7. Slide 7: Kevitsa – milestones

    Kevitsa – milestones 2013 Expansion Permit to 10 Mtpa ‘Quality construction contributed to smooth start up’

  8. Slide 8: Kevitsa – milestones

    Kevitsa – milestones 2013 Expansion Permit to 10 Mtpa ‘Commercial production declared Aug 18, 2012’

  9. Slide 9: Kevitsa – hitting the milestones

    Kevitsa – hitting the milestones 2013 Expansion Permit to 10 Mtpa

  10. Slide 10: Kevitsa – milestones

    Kevitsa – milestones 2013 Expansion Permit to 10 Mtpa

  11. Slide 11: Environment

    Environment Expansion Permit up to 10Mtpa Expect authorities to Expansion Permit publish application submitted for 30 days Collated info to respond to questions Authorities make decision Q4 (11) Q1 (12) Q2 (12) Q3 (12) Q4 (12) Q1 (13) Possibility to respond to Received list of public concerns if nee

  12. Slide 12: Effluent Waste Water Analysis

    Effluent Waste Water Analysis Nickel [µg/l] Copper [µg/l] 600 350 500 300 400 250 200 300 150 200 100 100 50 0 0 15/8/12 29/8/12 12/9/12 26/9/12 Nickel Limit value for flow-weighted monthly average Copper Limit value for flow-weighted monthly average

  13. Slide 13: Mining Production

    Mining Production Total Material Mined and Strip Ratio • Mining Production improved in Oct with improved blast fragmentation of ore 1000 1.80 1.60 800 1.40 • Mobile equipment trainer making 1.20 difference 600 1.00 0.80 400 0.60 200 0.40 0.20 0 0.00 Ore (kt) Waste (kt) Strip Ratio

  14. Slide 14: Pit Development 2013 - 2017

    Pit Development 2013 - 2017 FQM Kevitsa Mining

  15. Slide 15: Processing Production

    Processing Production Ore Milled & Grade Processed 600 0.40 • Mill throughput proven capable of 7Mt/a 0.35 500 • Feed grades varying significantly in the 0.30 400 0.25 weathered zones 300 0.20 • Crusher throughput rates to be improved 0.15 200 0.10 100 0.05 0 0.00 Milling Actual (kt) Milling Forecas

  16. Slide 16: Reagent Usage – in line with expectations

    Reagent Usage – in line with expectations METHYL ISOBUTYL CARBINOL 120 100 80 60 g/t 40 20 0 SODIUM ETHYL XANTHATE 350 300 250 200 g/t 150 100 50 0

  17. Slide 17: Stakeholders

    Stakeholders Government & Community Programs Municipality Investment in Local Sports Hall and Cultural Events Corporate Citizenship Positive Good on Social Impact 1. Environmental impacts do not pose any unacceptable risks; Local Communities 2. Communications are transparent and effective; 3. Mine i

  18. Slide 18: Key Priorities

    Key Priorities • Successfully completed important maintenance works, improving plant productivity and currently implementing a series of technical improvements • Expect an slight improvement in head grade during H1 2013 • Improve understanding of cost drivers after transition from projects to ops

  19. Slide 19: Kevitsa Operation

    Kevitsa Operation FQM Kevitsa Mining

  20. Slide 20: Mining

    Mining • Conventional open pit mining & blasting • Owner Operator – Contract maintenance • Future trolley assist system to reduce Opex Costs • 1 x PC 5500 Excavator • 1 x PC 8000 Excavator May 2013 • 6 x 250t trucks • 2 x 345t AC drive trucks • Substantial investment in training with €1.5M simulator

  21. Slide 21: Mining stages 1 – 4: 7.5 Mtpa

    Mining stages 1 – 4: 7.5 Mtpa Starter Pit Stage 2 Stage 3 Stage 4 Kaivostarkastus 9.12.11/JB

  22. Slide 22: TROLLEYTRUCKS CAT 795F

    TROLLEYTRUCKS CAT 795F Kaivostarkastus 9.12.11/JB

  23. Slide 23: CRUSHING AND MILLING

    CRUSHING AND MILLING Ore to crusher Primary mills Double deck screen To flotation Secondary crusher Secondary mill

  24. Slide 24: FLOTATION & CONCENTRATE FILTRATION

    FLOTATION & CONCENTRATE FILTRATION COPPER FLOTATION NICKEL FLOTATION SULPHUR FLOTATION From Milling Low sulphur tailings to TSF A Sulphur tailings to TSF B Copper filtration Nickel filtration Copper concentrate Nickel concentrate

  25. Slide 25: The Process in Summary

    The Process in Summary Ore from Mine Crushing  Milling Concentration by Flotation Concentrate ready for shipping.

  26. Slide 26: Thank you

    Thank you & FQM Kevitsa Mining