Goodman Group · ASX:GMG
Goodman — Corporate Update (June 2021)
24 slides from Goodman's corporate update, June 2021
Slide 1: Community Consultation Meeting
Community Consultation Meeting Oakdale West Estate June 2021 1
Slide 2: Overview
Overview Welcome and Introductions Upcoming Developments Project Update – OWE Project Update – Building 1A & 2B Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman SLR Consulting Ersed Role Proponent Stakeholder Engagement Environmental Representative Key Contacts Stephanie Partridge Dan Thompson Carl Vincent Kym Dracopoulos Kate McKinnon Alasdair Cameron Lachlan O’Reilly Luke Ridley Stakeholder Repr
Slide 4: Upcoming Developments
Upcoming Developments • Current Development Application Status – Modification 7 to SSD 7348 - Submitted to DPIE – PCC DA for Building 3B - Submitted to Council – New SSD for building 4E – To be submitted June 2021 • Construction Environmental Management Plans & Upcoming Construction Activities – Bui
Slide 5: Oakdale West Estate - MOD 7 Estate Masterplan
[REFER TO DRAWING OAK MPC3 FOR CONTINUATION PRELIMINARY. Oakdale West Estate - MOD 7 Estate Masterplan ( global environmental and advisory solutions S | Re wu
Slide 6: Building 3A
Building 3A q i: Sy LUT L ay i = sence ty Fy (LLLP LL OO: » Tr) LLLP Vr SOON x EE! LULL LEN LTP LLL iS Emmaus Catholle Ist PUTT] Development Area Schedule College i ~~ | site Area 21,283. sqm i = +} Warehouse 10,000. sqm = Office (2 levels) 506 sqm | Ht Total Buling Area 10,508 sam 0 =| Awning 4,155
Slide 7: Building 1B & 1C
Building 1B & 1C Fen i / as a = — ee a ooo q i i o> an ji meacve soiiwe A cae 2 - - = H : F H mine rors a NEW ZONE SUBSTATION 4 ’ global environmental and advisory solutions
Slide 8: Building 4E
Building 4E PRELIMINARY nouse Plan SLR® global environmental and advisory solutions
Slide 9: Building 3B
\\\Beezertyuee \s\ Wee yer Yat “als yr we “ut ee yy eee \ ss \, yy 7 a a {0000s Legend x ‘ke Boundery Lot Boundary __ Building 7.5m Setback (For Estate Road Only) ~ Landscape 3.75m Setback (For Estate Road Only) FNC-_ Chalawhe Fencing 2 Pallsade Fenclng BULL. Retalning Wall Development Area Schedule
Slide 10: Progress To Date & Upcoming Works - OWIE
Progress To Date & Upcoming Works - OWIE • Road 3 Asphalt now finished • Precinct 4 retaining walls under construction with a completion date in Q3 2021 • Precinct 5 earthworks complete with construction of the precinct 5 estate road to commence shortly. 10
Slide 11: Progress To Date – Building 1A
Progress To Date – Building 1A • High Bay Steel Erection; • External Hardstand Concrete Pours; • In-ground service installation; • CTSR installation; • Energy Complex Groundworks; • Retaining Wall Installation; • Office Structural Pile Installation; • Precast Panel installation; 11
Slide 12: Upcoming Works – Building 1A
Upcoming Works – Building 1A • High Bay Steel Erection; • Low Bay Steel Erection; • External Hardstand Concrete Pours; • In-ground service installation; • CTSR installation; • Energy Complex Groundworks; • Precast Panel installation; 12
Slide 13: Progress To Date – Building 2B
Progress To Date – Building 2B • External Hardstand Installation; • Window Glazing installation; • Mechanical Ventilation Unit Installation; • External Carpark installation; • Landscaping works; • Customer Fit-out works; • Office Fit-out works; • Internal Service Installation; • Site Compound Reloca
Slide 14: Upcoming Works – Building 2B
Upcoming Works – Building 2B • External Hardstand Installation; • Window Glazing installation; • Mechanical Ventilation Unit Installation; • External Carpark installation; • Landscaping works; • Customer Fit-out works; • Office Fit-out works; • Internal Service Installation; • Site Compound Relocati
Slide 15: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER INSPECTIONS 2019 TOTAL 3 2020 QTR1 (JAN-MARCH) 16 2020 QTR 2(APRIL-JUNE) 10 2020 QTR 3 (JULY-SEPT) 9 2020 QTR 4 (OCT-DEC) 7 2021 QTR 5 (JAN-MAR) 6 2021 QTR 6 (APR – JUN Part) 10 TOTAL TO DATE 61 Copyright © ErSed 2011
Slide 16: ER Inspections and Audits: SSD7348
ER INSPECTIONS AND AUDITS: SSD7348 ER AUDITS THIS PERIOD JUNE 21 • LOT 1A • AQMP • SWMP • FIP • WASTE MANAGEMENT • CHEM AND DANGEROUS GOODS • MONITORING AND REPORTING Copyright © ErSed 2011
Slide 17: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 NON COMPLIANCES, QUARTER 6 21/04/21 Issue Resident contacted Goodman to reported noise from the Project at approximately 11pm 20 April 2021. Condition D71(a) provides Works outside of the hours identified in Condition D70 may be undertaken in the following circumst
Slide 18: Environmental Performance: SSD7348
ENVIRONMENTAL PERFORMANCE: SSD7348 COMPLAINTS, QUARTER 6 21/04/21 Issue Resident (20 Aldington Road) contacted Goodman to reported noise from the Oakdale West Estate at approximately 11pm on the evening of 20 April 2021. Resolution Investigation confirmed that the contractor was carrying out minor l
Slide 19: EC Inspections and Audits - SSD10397
EC INSPECTIONS AND AUDITS- SSD10397 INSPECTIONS AUDITS THIS PERIOD JULY 20 3 AUGUST 20 0 SEPTEMBER 20 1 OCTOBER 20 1 NOVEMBER 20 1 DECEMBER 20 1 JANUARY 21 0 FEBRUARY 21 1 MARCH 21 5 APRIL 21 1 MAY 1 JUNE (Part) NIL Inspection + 1 Audit TOTAL 16 Copyright © ErSed 2011
Slide 20: Environmental Performance - SSD10397
ENVIRONMENTAL PERFORMANCE- SSD10397 INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS INCIDENTS QUARTER 6 MINOR ELECTRIC SHOCK – CUSTOMER FIT OUT ELECTRICIAN NON COMPLIANCES NIL Copyright © ErSed 2011
Slide 21: Safety
Safety • Third Party WHS Inspections of the Contractors are continuing; • There was a WHS Incident on the Lot 2B Project. The worker returned to work the next day; • Minor first aid injuries are being tracked and managed by each of the Contractors; 21
Slide 22: Consultation and Community Interactions
Consultation and Community Interactions • Notification and communication with adjacent residential neighbour regarding Endeavour Energy out of hours work • Thankyou email received from Principal Emmaus College for providing contacts between the school and future tenant of the estate and general than
Slide 23: Communications and Consultation Channels
Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E
Slide 24: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 24