Danya Cebus — Q3 2022 Earnings Presentation

9 slides from Danya Cebus's earnings presentation, November 2022

  1. Slide 1: Presentation to the capital market Q3-2022

    Presentation to the capital market Q3-2022 Accessible Slide 1 - Header Q3-2022 Slide 2 - Disclaimer This presentation was prepared by Danya Cebus Ltd. as a general presentation about the company and the companies on the Group (the “Company”). The presentation does not constitute an offer for investm

  2. Slide 2: The Leading Construction and Infrastructure Company in Israel

    Slide 3 The Leading Construction and Infrastructure Company in Israel for more than 80 years ▪ 80 simultaneous projects ▪ 20 Km of tunnels ▪ Hundreds of bridges built ▪ Hundreds of Km of Roads paved ▪ 22,000 residential units delivered in the past decade ▪ 4 Million square meters of commercial, publ

  3. Slide 3: Financial Growth (In NIS million)

    Slide 5 - Financial Growth (In NIS million) The net profit of the company for the report period totaled approximately NIS 127 Million. BAR graph - Profit from Ongoing Operations Period NIS Million 2019 63 2020 105 2021 132 1-9/21 86 1-9/22 127 Q3-2021 30 Q3-2022 45 Increase of 50% compared to the sa

  4. Slide 4: Synergic Revenue Structure Enabling the Distribution of Risks and Growth

    BAR graph - Backlog by Operating Segments Period Residential Non Infrastructure Residential Total Construction Residential Development Construction & Construction 2019 3,427 2,357 1,267 141 7,192 2020 3,926 2,992 2,610 81 9,609 2021 5,323 2,880 2,430 425 11,058 1-9/21 5,557 3,170 2,407 521 11,655 1-

  5. Slide 5: Non Residential Construction

    Prominent Projects Name of the Project Estimated Completion Expected Financial Rate as at Completion Scope Sep. 30, Date (NIS 2022 Million) Bat-Yam Moment (Ha’Shvatim) 695 5% Q2, 2025 Upper House - Yad Eliyahu 594 29% Q3, 2024 Aura Ramat Chen 555 2% Q3, 2026 Carmay Hanadiv Stage A+B 493 0% Q2, 2025

  6. Slide 6: Infrastructure

    Prominent Projects Name of the Project Estimated Completion Expected Financial Rate as at Completion Scope Sep. 30, Date (NIS 2022 Million) TOHA 2 530 2% Q3, 2026 Ministry of Justice 527 90% Q4, 2022 District Government Campus, 477 42% Q2, 2024 Jerusalem Computerization Project * 947 22% Q3, 2024 *

  7. Slide 7: Residential Development & Construction

    Slide 10 - Residential Development & Construction Development Projects • Projects under construction Name of the Project Location Share of No. of No. of Free Expected the Residential Market Completion Company Units Residential Date (Total) Units Narkisim Rishon Lezion 50% 554 160 2022-2023 Savyonei

  8. Slide 8: Balance Sheet Liabilities and Capital and Profit & Loss

    authorities of design; And / or (4) One or more of the risk factors that the company is also exposed to, will occur. Slide 11 - Balance Sheet Liabilities and Capital – 30.9.2022 (NIS Thousands) 30.9.2022 31.12.2021 Total Balance Sheet 2,203,911 2,255,342 Total Current Assets 1,797,206 1,882,933 Inve

  9. Slide 9: Consolidated Order Backlog by Operating Segments

    Line Graph - Backlog Period Backlog 2017 5,720 2018 6,399 2019 7,191 2020 9,608 2021 11,058 Q3-2022 12,659 Slide 14 - Consolidated Order backlog – By Operating segments (NIS M) Backlog Backlog Backlog Backlog Balance Balance Balance Balance 30.9.2022 2021 2020 2019 Residential Construction 6,198 5,3