For personal use only IIR CSG 2010 Conference - Brisbane David Johnson – Managing Director 29-31 March 2010
Slide 2: Disclaimer
Disclaimer For personal use only This presentation is being provided for the sole purpose of providing the recipients with background information about Metgasco Ltd (Metgasco). No representation, express or implied, is made as to the fairness, accuracy, completeness or correctness of information con
Slide 3: Metgasco
Metgasco For personal use only Some history – EVG Metgasco CSG operations Acreage Resources and reserves Production capability Development considerations Forward plan Metgasco corporate details Market data & financials Board and management Competitive position
Slide 4: Some history – the EVG story
For personal use only Some history – the EVG story
Slide 5: Back to the future : EVG
Back to the future : EVG For personal use only Evergreen Resources (Raton Basin CSG) 2003 SEC 10k Filing Total Cost $ 1.86 1.92 1.62 1.39 1.36 P&L Margin $ 1.00 1.97 1.41 0.57 0.79 5 year average realised price of $US 2.77Mcf
Slide 6: Back to the future : EVG
Back to the future : EVG For personal use only Evergreen Resources (Raton Basin CSG) 2003 SEC 10k Filing Number of wells 837 681 491 252 159 Daily Production/Well (Mcf/d) 127 123 108 148 172 5 year average realised daily sales price of $US 2.77Mcf* 5 year daily average production/well of 135Mc
Slide 7: Back to the future : EVG - Some of the lessons
Back to the future : EVG For personal use only Some of the lessons… Acreage Good acreage position 271,234 net acres Extensive Vermejo coals, a large resource Resource capability Production A low cost producer, internalised cost Capability structures, basin focus Steady production ramp up Development
Slide 8: Metgasco CSG Operations
For personal use only Metgasco CSG Operations
Slide 9: Acreage
Acreage For personal use only Tenements PEL 16 826 km² PEL 13 900 km² PEL 426 4,023 km² Total 5,749 km² 1,420,000 acres, mostly contiguous, 100% MEL - a basin focused player All covering the highly prospective Walloon Coal Measures
Slide 10: Resources & reserves
Resources & reserves Extensive occurrence of Walloon Coal Measures For personal use only From outcrop to 800m depth, most in the 200-600m depth range Net coal thickness 14-44m, average 29m Generally fully gas saturated Mainly clean +95% CH4/C2H6, little or no impurities Permeability test
Slide 11: Resources & reserves
Resources & reserves Consistent and steady 2,500 For personal use only 2,153 buildup of reserves associated with core drilling and testing 2,000 1P 2P 3P 1,479 3P reserves 2,153 Bcf 1,336 1,500 2P reserves 381 Bcf 1,084 Richmond 201 Bcf Bcf I/J/K 180 Bcf 1,000 All in PEL 16 Productivit
Slide 12: Production Capability
Production Capability For personal use only Activity Purpose Trial production & pre development objectives: NPV/well Optimised expected ultimate recovery (EUR)/well Likely cost/well Where are the productive fairways/hotspots Appraisal activities to date have identified CSG reservoirs wit
Slide 13: Richmond seam reservoir
Richmond seam reservoir For personal use only 1000 Activity Purpose > 2 years of production CP-11 Production Profile history Initial 1P certification 2.7PJ Single leg lateral, 680m 100 inseam length Approaching 0.1Bcf recovery, no decline Gas composition still +97% 10 CH4 Only modest wat
Slide 14: Richmond seam reservoir
Richmond seam reservoir For personal use only Optimised EUR more in seam exposure to the coal Underbalanced to reduce formation damage More efficient water extraction CP-18 in progress Inseam completion remaining Likely cost structure/well Time on well - CNX Virginia operations 7 day
Slide 15: I/J/K Reservoirs
I/J/K Reservoirs For personal use only Activity Purpose Banded sequence coal-carb shale Estimated equivalent lower Taroom in Surat Basin Laterally very extensive Average 14m thick Gas content average 527scf/t daf Gas composition 92% CH4 5% C2H6 Current 2P reserves 180 Bcf 15
Slide 16: I/J/K Reservoirs
I/J/K Reservoirs For personal use only Activity Purpose Banded nature of coal carbonaceous shale Suitable frac candidate What is the EUR ? Frac design Intervals to be fracced Fluid type & quantity Proppant type and quantity Likely cost structure/well Design improvements Scale of
Slide 17: Full Section dry coal (Wyan)
Full Section dry coal (Wyan) WYAN E-1: Full Section Flow Test For personal use only Activity 1000 PEL 13, south west of Casino 18/6 22/6 24/6 Drilled using air (Air Drill Flow Rates (Mscf/d) Vertical – ADV) 100 Stabilised flow rate on test of 170Mcf/d Gas signature is CSG, NO WATER ! reservo
Slide 18: Full section dry coal (Wyan)
Full section dry coal (Wyan) For personal use only Activity Purpose Initial rate comparable to Horseshoe * Canyon production well Horseshoe Canyon (Canada) Prolific play in western canadian sedimentary basin Drill and complete 3 wells per day Dry – no or little water Wyan E1 - potentially
Slide 19: Development Considerations
Development Considerations For personal use only Activity Purpose Metgasco is assessing optimised EUR/well and likely cost structures (NPV/well) for different reservoirs For development - where and what are the productive fairways/hotspots to commence activities ? One only example: The Eden Cr
Slide 20: Eden Creek Trend
5km Eden Creek Trend Potential emerging fairway For personal use only Activity Broad anticline covering 193km² Sitting on previously known conventional structure (Dyraaba lead) A Major East Richmond fault Walloon outcrop updip to west Isotope data showing biogenic recharge A regional s
Slide 21: Eden Creek Trend
Eden Creek Trend For personal use only A B WALLOON COAL MEASURES
Slide 22: CSG 2010 Forward Plan
CSG 2010 Forward Plan Eden Creek Trend (PEL’s 16 &13) pre For personal use only Activity development activities Purpose Bowerbird E2 core well Likely follow up stratigraphic drilling Complete CP-18 I/J frac well design and completion 30km new 2D seismic BE-2 ☼ Reservoir data and NPV/we
Slide 23: CSG 2010 Forward Plan
CSG 2010 Forward Plan For personal use only Activity Purpose Basin Exploration Program – Fairway identification Seek to highgrade prospectivity Air drill vertical program PEL 426 Banyabba, Tullymorgan ADV’s 30km new 2D seismic PEL 13 Wyan ADV, other areas 60km new 2D seismic 23
Slide 24: Metgasco corporate details
For personal use only Metgasco corporate details
Slide 25: Market Data & Financials
Market Data & Financials ASX code MEL Activity Share price (25 MarchPurpose 2010) $0.59 For personal use only Market Capitalisation $147 m Shares on Issue 250 m Options on Issue 6m Cash at 31 Dec 09 $29.0 m Debt nil 100 500000 90 450000 80 400000 70 350000 Share Price (cents) 60 300000 Share Price 5
Slide 26: Board and Management
Board and Management Board Management & Technical Team For personal use only DR PETER POWER Chairman MICK O’BRIEN Chief Operating Officer Geologist with 50 years experience in hydrocarbon Over 30 years experience in senior engineering roles exploration worldwide in senior roles. Previously previousl
Slide 27: MEL : CSG Competitive Advantages
MEL : CSG Competitive Advantages SignificantActivity acreage, large resource and Purpose reserve position For personal use only Significant resource understanding with developed knowledge of reservoirs and drilling and completion methods Can be cost competitive Single operations base, lean c