  1. Slide 1: Presentation to the capital market Q1-2026

    Presentation to the capital market Q1-2026 Accessible Slide 1 - Header Build the Future Q1 - 2026 Slide 2 - Disclaimer This presentation was prepared by Danya Cebus Ltd. as a general overview of the company and the companies in the Group (the “Company”). The presentation does not constitute an offer

  2. Slide 2: One-stop Shop; Post-War Growth Opportunities

    Slide 3 – One-stop Shop  Infrastructure and Concessions o PPP Mega Projects in Infrastructure, Building & Transport o Geotechnology & Subsurface Expertise  Residential Construction o Prefabricated modular buildings expertise o Mega projects in Israel  Non-Residential Construction o M&E intensive

  3. Slide 3: Financial Strength as of March 31, 2026; Building Israel

     5 Lanes  6 Road  Jerusalem construction projects  Megiddo Security Complex o National Transport Plan 65 Tenders o Gaza strip Reconstruction Projects o Ahuza Interchange & Leisure Road o Security Barrier Construction Project o Development Projects o Defense system facilities Slide 5 - Financial

  4. Slide 4: Financial Growth (In NIS million)

    Slide 7 - Financial Growth (In NIS million) BAR graph - Turnover Period NIS Million 2023 5,415 2024 6,026 2025 6,510 1-3/25 1,634 1-3/26 1,622 BAR graph - EBITDA Period NIS Million 2023 298 2024 278 2025 309 1-3/25 74 1-3/26 78 BAR graph – Net Profit Period NIS Million 2023 196 2024 174 2025 * 173 1

  5. Slide 5: Consolidated Orders backlog by Activities segments

    Slide 8 - Consolidated Orders backlog – by Activities segments (Million NIS) Backlog Backlog Backlog Backlog 31.3.26 2025 2024 2023 Residential Construction 12,262 10,420 6,118 6,362 Non-Residential Construction 4,414 3,716 4,054 4,289 Infrastructure and Concessions 7,660 7,350 2,010 2,523 Residenti

  6. Slide 6: Residential Construction - Backlog, Turnover & Profitability

    Slide 11 – Residential Construction - Backlog, Turnover & Profitability (Million NIS) Turnover – Bar Graph Period Turnover 2024 2,343 2025 2,367 Q1-2025 624 Q1-2026 573 Gross Profit – Bar Graph Period Gross Profit 2024 92 2025 78 Q1-2025 27 Q1-2026 7 Backlog – Bar Graph Period Backlog 2024 6,118 202

  7. Slide 7: Residential Construction Projects (Cont.); Non-Residential Construction

    Slide 13 – Residential Construction – Significant Projects (Cont.) Name of the Project Estimated Completion Estimated Financial Rate Completion Value Date (NIS Million) Ha’Savyon - Beit Shemesh 547 0% Q4, 2029 Aura Ramat Ha’Sharon – Phase B 510 38% Q3, 2027 Azorim – Ben Shemen 415 7% Q3, 2028 Carass

  8. Slide 8: Non-Residential Construction Projects; Infrastructure and Concessions

    Slide 15 - Non-Residential Construction – Significant Projects Name of the Project Estimated Completion Estimated Financial Rate Completion Value (NIS Million) Kiryat Magen David Adom, Ramla 455 0% Q2, 2029 Mediterranean towers 551 2% Q4, 2028 Government Headquarters - 600 95% Q2, 2026 Jerusalem ToH

  9. Slide 9: Infrastructure and Concessions – Significant Projects

    Slide 17 – Infrastructure and Concessions – Significant Projects  Fourth Track - Ayalon section Estimated Financial Value – NIS 908 Million Completion Rate – 26% Estimated Completion – Q4, 2032  Fast Lanes - Shefayim parking lot & 541 Road Estimated Financial Value – NIS 1,107 Million Completion R

  10. Slide 10: Residential Development & Construction

    Slide 18 - Residential Development & Construction Projects Under Construction Project Name Location Country Company's Total Sold (as Units for Share No. of the sale of reporting (as of the Units date) reporting date) Denya Spring View C Warsaw Poland 100% 26 25 1 Denya Spring View D Warsaw Poland 10

  11. Slide 11: Denya Lake and other Romanian projects

     Denya Lake A plot of land in Pipera neighborhood for construction of 87 townhouses o Location: Bucharest o Project Scope: 87 Residential Units o Land cost: NIS 21 Million o Under Construction (Project Under Construction)  Denya Home Construction of 928 residential units in 49 buildings next to th

  12. Slide 12: Balance Sheet Liabilities and Equity Capital

     Denya Forest - Bloc F Seventh building out of 7, 12 floors and 113 residential units. Construction commenced in 2025, scheduled for completion in 2028 o Location: Timisoara o Project Scope: 113 Residential Units o Land cost: NIS 3 Million o Under Construction (Project Under Construction) Developer