Kinder Morgan, Inc. · NYSE:KMI

Kinder Morgan — Kinder Morgan 2015 Analyst Conference

54 slides from Kinder Morgan's conference presentation, Jan 28, 2015

  1. Slide 1: Natural Gas Pipelines

    Natural Gas Pipelines Tom Martin President, Natural Gas Pipeline Group

  2. Slide 2: Natural Gas Segment

    Natural Gas Segment Growth Drivers:  Shale-driven expansions / extensions  LNG exports — Liquefaction facilities — Pipeline infrastructure  Gas demand for power generation — Coal plant retirements — Regional demand growth  Industrial demand growth  Exports to Mexico  Repurposing opportunities

  3. Slide 3: Contracted Capacity and Term by Region

    Contracted Capacity and Term by Region Contracted Average Term Region Capacity Remaining Storage 132 Bcf 3 yr, 4 mo East Transport 18.9 Bcf/d 8 yr, 7 mo LNG 18 Bcf 17 yr, 5 mo Interstate Storage 46 Bcf 5 yr, 11 mo Transport Contracts West Transport 18.4 Bcf/d 5 yr, 8 mo Avg. = 6 yr, 8 mo Storage 255

  4. Slide 4: Projects Placed Into Service - 2014

    Projects Placed Into Service - 2014 4

  5. Slide 5: New Firm Transport Capacity

    New Firm Transport Capacity 5

  6. Slide 6: Natural Gas Segment in a Low Oil Price Environment

    Natural Gas Segment in a Low Oil Price Environment Risk Assessment Opportunity Assessment  Price sensitivity mainly in Midstream  Acquisition opportunities — $0.10/Dth gas price change — Lower oil price environment expected to • $2.8 MM/yr (excluding hedges) lead to greater acquisition opportuniti

  7. Slide 7: Gas Pipeline Group Project Backlog

    Gas Pipeline Group Project Backlog Approximate $1.9 billion increase from 2014 7

  8. Slide 8: Region Asset Reviews

    KINDERMORGAN Region Asset Reviews

  9. Slide 9: East Region Assets

    East Region Assets Growth Drivers:  Asset footprint provides a base for serving growing and supply-constrained markets from both traditional and developing supply regions  TGP uniquely positioned in growing Marcellus and Utica shale plays to provide region-wide access to both Gulf Coast and Northe

  10. Slide 10: East Region Project Backlog

    East Region Project Backlog 10

  11. Slide 11: TGP - Broad Run Flexibility and Expansion

    TGP - Broad Run Flexibility and Expansion  Capacity: 790 MDth/d  Capital: $751.0 MM  Estimated In-service: 11/2015 and 11/2017  Project Scope: — Piping/compression modifications to 7 existing stations — Horsepower at 3 greenfield stations  Commercial Benefit: Moves gas north- to-south from a re

  12. Slide 12: TGP - Susquehanna West

    TGP - Susquehanna West  Capacity: 145 MDth/d  Capital: $143.0 MM  Estimated In-service: November 2017  Project Scope: — 8.2 miles of 36” pipeline loop — Compressor relocation — Upsize existing compressor  Commercial Benefit: Northeast Marcellus to points of liquidity  Avg. Contract Term: 15 ye

  13. Slide 13: TGP - Niagara Expansion

    TGP - Niagara Expansion  Capacity: 158 MDth/d  Capital: $26.0 MM  Estimated In-service: November 2015  Project Scope: — 3.1 miles of 30-inch pipe looping — Station 229 meter facilities — Lease on National Fuel Gas (140 MDth/d)  Commercial Benefit: Provides additional market for Marcellus gas an

  14. Slide 14: TGP - South System Flexibility

    TGP - South System Flexibility  Capacity: 500 MDth/d  Capital: $187.3 MM  Estimated In-service: 1/2015-12/2016  Project Scope: — Station modifications at 7 stations — Horsepower replacement at 1 station  Commercial Benefit: Provides more than 900 miles of north-to-south transportation capacity

  15. Slide 15: TGP - Marcellus to Milford

    TGP - Marcellus to Milford  Capacity: 135 MDth/d  Capital: $129.3 MM  Estimated In-service: June 2018  Project Scope: — 12.9 miles of 36” looping — Station upgrades  Commercial Benefit: Provides firm transportation to Milford (TCO)  Avg. Contract Term: 15 years  Current Status: — PAs executed

  16. Slide 16: TGP - Connecticut Expansion

    TGP - Connecticut Expansion  Capacity: 72.1 MDth/d  Capital: $82.2 MM  Estimated In-service: November 2016  Project Scope: — 13.3 miles of pipeline loop — Acquisition of Thompsonville Lateral  Commercial Benefit: Additional capacity to serve New England market  Avg. Contract Term: 15 years  C

  17. Slide 17: TGP - Cameron LNG

    TGP - Cameron LNG  Capacity: 900 MDth/d  Capital: $138.4 MM  Estimated In-service: 2Q-4Q 2018  Project Scope: — Compressor station modifications to accommodate bi-directional flow — 18,000 HP of new compression — New pipeline laterals for enhanced supply access to the Perryville Hub  Commercial

  18. Slide 18: TGP - Lone Star

    TGP - Lone Star  Capacity: 300 MDth/d  Capital: $122.8 MM  Estimated In-service: July 2019  Project Scope: — 2 greenfield compressor stations  Commercial Benefit: Provide supply to Corpus Christi LNG liquefaction project  Avg. Contract Term: 20 years  Current Status: — PA fully executed — Ser

  19. Slide 19: SNG / Elba Express Expansion

    SNG / Elba Express Expansion  Capacity: 417 MDth/d (a)  Capital: $179.6 MM (a)  Estimated In-service: June 2016  Project Scope: — Compression on SNG and EEC — Additional pipeline and other facilities  Commercial Benefit: Additional access to Marcellus/Utica shale gas for existing and new SNG cu

  20. Slide 20: Liquefaction at Elba Island

    Liquefaction at Elba Island Elba Liquefaction Company (ELC) / SLNG  Capacity: 350 MMcf/d  Capital (KM-share, $MM): ELC (KM 51%) $884 SLNG (KM 100%) 446 Total $1,330  Estimated In-service: 2017 - 2018  Project Scope: — ELC: Facilities for liquefaction — SLNG: Ship loading facilities; boil-off gas

  21. Slide 21: East Region Additional Potential Growth Projects

    East Region Additional Potential Growth Projects  Additional Marcellus / Utica Project Opportunities — Large production increases in these two areas will provide expansion and greenfield opportunities to move more gas into the Northeast and significant quantities south to the demand centers on the

  22. Slide 22: East Region Growth Opportunity

    East Region Growth Opportunity TGP Northeast Energy Direct (NED) Project  Market Path: — From Wright to Dracut — 30” mainline • 0.8 - 1.2 Bcf/d • $2.9 - $3.5 billion — Potential upside, 36” mainline • Up to 2.2 Bcf/d • $3.8 - $4.4 billion  Supply Path: — From Marcellus to Wright — 30” mainline • 0

  23. Slide 23: West Region Assets

    West Region Assets Growth Drivers:  Large asset footprint provides numerous opportunities for expansion capital investment  West Region pipelines reach back to all Rockies basins — Diverse geology, and hydrocarbon mix, coupled with changes in technology, create the opportunity for new builds and c

  24. Slide 24: West Region Project Backlog

    West Region Project Backlog 24

  25. Slide 25: EPNG - Upstream of Sierrita

    EPNG - Upstream of Sierrita  Capacity: Phase II, 350 MDth/d  Capital: Phase II, $525.9 MM  Estimated In-service: October 2020  Project Scope: — Phase II:  New Franconia compressor station – 10,300 HP  100 mile, 36” Havasu Loop  Reverse Casa Grande ‘A’ and ‘C’ and Cimarron compressor stations

  26. Slide 26: West Region Additional Potential Growth Projects

    West Region Additional Potential Growth Projects  Growth in exports to Mexico — Total incremental Mexico growth by 2025 projected up to 2.2 Bcf/d that can be served from the EPNG footprint • Incremental power generation demand growth on Willcox, Samalayuca laterals and Sierrita • Creates opportunit

  27. Slide 27: West Region Growth Opportunity

    West Region Growth Opportunity Mexico Incremental Gas Demand Potential Est. Avg. Daily Gas Capacity Demand Key Demand Type (MW) (MDth/d) Electric Gen Conversions1 3,000 380 Electric Gen New Builds2 ~10,000 1,300 Industrial Potential 500 Total Incremental Mexico Demand Potential 2,180  Capital (KM s

  28. Slide 28: West Region Growth Opportunity - Freedom Pipeline

    West Region Growth Opportunity Conversion Opportunity - Freedom Pipeline  Capacity: − 200,000 Bbl/d of 30o API crude − 100,000 Bbl/d of condensate  Capital: $2.0 B - $2.5 B  Estimated In-service: 2019  Project Scope: − Converts underutilized EPNG Lines 2000 and 1903/04 to crude oil/condensate se

  29. Slide 29: Central Region Assets

    Central Region Assets Growth Drivers:  Large and strategic asset footprint near major shale plays and supply basins provides opportunities to attach new supply — Developing NGPL Gulf Coast Line expansion projects related to growing NE production  Potential to serve 11 Bcf/d of transportation deman

  30. Slide 30: Central Region Project Backlog

    Central Region Project Backlog 30

  31. Slide 31: KMLP - Magnolia LNG Liquefaction Transport Project

    KMLP - Magnolia LNG Liquefaction Transport Project  Capacity: 700 MDth/d  Capital: $142.7 MM  Estimated In-service: 3Q 2018  Project Scope: — Construct 32,000 HP at a new compressor station in Acadia Parish, Louisiana — Modify existing meter facilities located in Evangeline and Acadia Parishes,

  32. Slide 32: KMLP - LNG Liquefaction Transport Project

    KMLP - LNG Liquefaction Transport Project  Capacity: 1,200 MDth/d  Capital: $190.3 MM  Estimated In-service: 3Q 2019  Project Scope: — Construct 82,000 HP at a compressor station in Acadia Parish, LA — Modify existing meter facilities located in Evangeline Parish, LA for bi-directional flow — Co

  33. Slide 33: Central Region Additional Potential Growth Projects

    Central Region Additional Potential Growth Projects  Growth in Marcellus and Utica supply — Continue to develop expansion opportunities related to growing Marcellus and Utica supply seeking Midwest and Gulf Coast markets  LNG Liquefaction Opportunities — LNG liquefaction projects moving forward in

  34. Slide 34: Midstream Assets

    Midstream Assets Growth Drivers:  Large asset footprint provides continued expansion capital investment  Competitive expandability and connectivity for increased deliveries into Mexico for its growing reliance on natural gas (Texas Intrastate)  Significant storage positions and connectivity provi

  35. Slide 35: Midstream Project Backlog

    Midstream Project Backlog 35

  36. Slide 36: Cheniere Corpus Christi LNG

    Cheniere Corpus Christi LNG  Capacity: 250 MDth/d  Capital: $77.1 MM  Estimated In-Service: 4Q 2018  Project Scope: — Crossover pipeline from KMTP Index 50 to Tejas mainlines  Commercial Benefit: — Increase receipt capacity from Katy and HCP plant tailgate for delivery to Cheniere Corpus Christ

  37. Slide 37: SK Freeport LNG

    SK Freeport LNG  Capacity: 440 MDth/d  Capital: $153.3 MM  Estimated In-Service: 3Q 2019  Project Scope: — New 30” lateral from Tejas mainline to Stratton Ridge — Additional upstream compression on existing mainlines  Commercial Benefit: — Deliver gas to Freeport LNG terminal and capture additi

  38. Slide 38: Midstream Additional Potential Growth Projects

    Midstream Additional Potential Growth Projects  Exports — Electric generators in Mexico are looking towards natural gas to fuel new plants to meet growth and replace other fuels such as oil — Additional pipeline expansions to serve Texas LNG liquefaction projects  Processing and Gathering — Contin

  39. Slide 39: Midstream Growth Opportunities

    Midstream Growth Opportunities Gulf Coast Expansion Projects  In addition to LNG gas exports, KM Midstream has opportunities to provide more gas to Mexico and to power and chemical plants that are expected to come on-line in 2015-2019 along the Texas Gulf Coast  Capital: $200 MM - $750 MM  Opport

  40. Slide 40: Gas Pipeline Group Growth Outlook

    Gas Pipeline Group Growth Outlook 40

  41. Slide 41: Natural Gas Pipelines Appendix

    Natural Gas Pipelines Appendix

  42. Slide 42: EPNG - Washington Ranch Expansion Project

    EPNG - Washington Ranch Expansion Project  Capacity: Increases operational capacity by 4 Bcf Uinta Basin Piceance Basin  Capital: $7.9 MM Anadarko Basin UTAH COLORADO  Estimated In-service: December 2015 NEVADA CALIFORNIA ARIZONA Blanco  Project Scope: San Juan — Drill and connect 2 wells (one c

  43. Slide 43: EPNG - TGS Line 20121 Extension

    EPNG - TGS Line 20121 Extension  Capacity: 33 MDth/d  Capital: $8.8 MM  Estimated In-Service Date: July 1, 2015  Project Scope: — Trans Mountain meter station & regulation — 3.6 miles of 12” Pipeline extension of Line 20121 to Three Hills meter station  Commercial Benefit: Additional capacity t

  44. Slide 44: West Region Growth Opportunity - West Coast LNG

    West Region Growth Opportunity West Coast LNG Liquefaction Transportation Jordan Cove LNG would be beneficial to western gas pipelines via higher throughput Incremental volumes (MMcf/d) 2013-2023 volumes. if Jordan Cove is built Based on the Brent forward prices, North GTN American LNG export projec

  45. Slide 45: KMLP - Additional Magnolia LNG Liquefaction Transport

    Central Region Growth Opportunity KMLP - Additional Magnolia LNG Liquefaction Transport  Capacity: 700 MDth/d  Capital: $57 MM - $172 MM  Estimated In-service: Late 2019  Project Scope: — Construct 30,000 HP at a new compressor station in Calcasieu Parish, LA — Construct 64,000 HP at a compresso

  46. Slide 46: Chicago Market Expansion Project (CMEP)

    Central Region Growth Opportunity Chicago Market Expansion Project (CMEP)  Capacity: 240 MDth/d  Capital: $14.5 MM (KM 20% share)  Estimated In-service: Late 2016  Project Scope: — Construct 30,000 HP at a new intermediate compressor station in Livingston County, IL  Commercial Benefit: Provide

  47. Slide 47: Midstream - Hill Country Pipeline Expansion

    Midstream - Hill Country Pipeline Expansion  Capacity: 160 MDth/d  Capital: $9.7 MM  Estimated In-Service: 2Q 2015  Project Scope: — Extension of Hill Country Pipeline by purchase of EPNG pipeline and new construction  Commercial Benefit: — Plant dedication with volume commitment — Provides low

  48. Slide 48: Midstream - DCP Goliad Plant Residue Lateral

    Midstream - DCP Goliad Plant Residue Lateral  Capacity: 160 MDth/d  Capital: $33.1 MM  Estimated In-Service: 3Q 2015  Project Scope: — Construction of 34 miles of 16” pipeline from Goliad plant tailgate to Tejas mainline  Commercial Benefit: — Demand fee based contract — Expands existing Tejas

  49. Slide 49: Midstream - Boardwalk to Liberty Y Grade Pipeline

    Midstream - Boardwalk to Liberty Y Grade Pipeline  Capacity: 15 MBbl/d  Capital: $14.8 MM  Expected In-Service Date: 1Q 2015  Project Scope: 15 miles of 8” y- grade pipeline connecting Boardwalk’s Flag City Plant to Liberty Pipeline (KM/ETC JV)  Commercial Benefits: — Enables KM to take NGLs in

  50. Slide 50: Midstream - Altamont Bluebell Loop and East Station Expansion

    Midstream - Altamont Bluebell Loop and East Station Expansion  Capacity: 6 MDth/d  Capital: $9.4 MM  Expected In-Service Date: 1Q 2015  Project Scope: — 6 miles of 12” pipeline — Discharge piping and treating capacity upgrades at East Station — Compressor installed at East station  Commercial B

  51. Slide 51: Midstream - Oklahoma Processing Optimization

    Midstream - Oklahoma Processing Optimization  Capacity Increase: 14.3 MDth/d  Capital: $10.9 MM  Expected In-Service Date: — Paden Plant optimization: 2Q 2015 — Harrah Plant optimization: 1Q 2015  Project Scope: — Paden Plant optimization: Installation of heat exchangers, Sulfa Treat tower and c

  52. Slide 52: Midstream - Eagle Ford Fractionation Outlet

    Midstream - Eagle Ford Fractionation Outlet  Capacity: 30 MBbl/d  Capital: $22.2 MM  Expected In-Service Date: 4Q 2015  Project Scope: ~26 miles of 12-inch pipeline from Markham, TX to a new NGL fractionator being constructed near Sweeny, TX  Commercial Benefits: — Provides economic outlet for

  53. Slide 53: Midstream West Region Growth Opportunity

    Midstream West Region Growth Opportunity Powder River Lateral Abandonment & Conversion to NGL Service  Initial Capacity: 20 MBbl/d, expandable up to 70 to 100 MBbl/d with future pump station additions  Estimated In-Service: 2016  Project Scope: — Conversion of 16-inch lateral to NGL service — New

  54. Slide 54: Kinder Morgan

    KINDERJMORGAN

Kinder Morgan — Kinder Morgan 2015 Analyst Conference on 6ix