Kinder Morgan, Inc. · NYSE:KMI
Kinder Morgan — Corporate Update (July 2024)
26 slides from Kinder Morgan's corporate update, Jul 17, 2024
Slide 1: Southern Natural Gas Company 2024 Outage Review
Southern Natural Gas Company 2024 Outage Review July 17th , 2024
Slide 2: Welcome
Welcome 2
Slide 3: Agenda
Agenda • Review of current and upcoming notable Outages • July/August/September/October • Unscheduled outages • North System • South System • South Louisiana System • EEC • The next outage meeting will be on August 21st , at 1:30 CST • Contacts 3
Slide 4: Disclaimers
Disclaimers • Anticipated Impacts are estimates. Actual nominations, market demand, weather and pipeline conditions, etc. will determine if, and through what level, restrictions become necessary. • Unless otherwise stated, all scheduled dates represent gas days as defined in the Southern Natural Gas
Slide 5: Color Key for Maps
Color Key for Maps • Yellow • Restrictions are possible • With extended duration, restrictions could be necessary from time to time • Lower than normal pressures may be experienced • Meter(s) affected are noted with (PIN #) • Red • Restrictions are probable 5
Slide 6: Southern Natural Gas Pipeline
Southern Natural Gas Pipeline Chattanooga Rome Hartwell SC Muldon North System GA MS Tarrant Bell Mills Aiken McConnells Atlanta Pell City DeArmanville Louisville Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Selma Elmore Holy Trinity Bie
Slide 7: Unscheduled Outage Update
Southern Natural Gas Pipeline Unscheduled Outage Update Chattanooga Rome Hartwell SC Muldon North System GA MS Tarrant Bell Mills Aiken McConnells Atlanta Pell City DeArmanville Louisville Wrens Providence Ocmulgee Pickens Reform Ellerslie Hall Gate Bear Creek Onward Auburn Thomaston Elba Rankin Sel
Slide 8: SNG North System Pigging Review
SNG North System Pigging Review July/August/September/October Chattanooga Huntsville Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville GA Pickens Onward Pigging on NMLL Bear Creek Storage 10-8-24 to 10-9-24 AL Pro. 15346-east of Tarra
Slide 9: SNG North System Maintenance Review
SNG North System Maintenance Review July/August/September/October Muldon Shut-in test 10-1-24 to 10-7-24 Restrictions first into ISS then Chattanooga CSS-not to exceed 36% of CSS DIQ /DWQ Huntsville Rome AL Muldon unit maintenance Muldon Storage 9-9-24 to 11-8-24 Atlanta Tarrant Bell Mills MS McConn
Slide 10: SNG North System Maint. Review Cont.
SNG North System Maint. Review Cont. July/August/September/October Chattanooga Pipeline maintenance Rome Huntsville Calhoun loop line 8-2-24 to 8-9-24 Rome Pro.15374 AL north of Bell Mills Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pic
Slide 11: SNG South System Pigging Review
SNG South System Pigging Review July/August/September/October MS Hartwell Pigging on Ocmulgee Pigging on SMLL Atlanta line-Ocmulgee to Aiken Atlanta 7-16-24 to 7-18-24 Bass Junction Pro. 18931 west of Ellerslie 9-17-24 to 9-18-24 Wrens GA Pigging on SMLL Ocmulgee 8-5-24 to 8-8-24 Pro. 18926 east of
Slide 12: SNG South System Maintenance Review
SNG South System Maintenance Review July/August/September/October Pipeline remediation SML Pipeline remediation SML 7-15-24 to 7-19-24 7-8-24 to 7-17-24 Pro. 21236 MS Segment 490 capacity of 1,663 east of Thomaston Mdth/d impacted 33 Mdth/d Hartwell Pro. 34908 west of Thomaston Aiken Atlanta Wrens G
Slide 13: SNG South System Maint. Review cont.
SNG South System Maint. Review cont. July/August/September/October Thomaston Griffin 2nd loop line MS Pipeline maintenance 10-7-24 to 10-16-24 Hartwell Elmore unit maintenance North of Thomaston 10-17-24 Pro. 231009 Aiken Atlanta Seg. 460 capacity of 2,293 Mdth/d impacted 450 Mdth/d Wrens Gallion un
Slide 14: SNG South Louisiana System Pigging Review
SNG South Louisiana System Pigging Review July/August/September/October Gwinville Pearl River MS LA Franklinton Pigging on SS28 line 7-15-24 to 7-19-24 Pro. 28751-south of White Castle Pigging on MPFLL 7-15-24 to 7-19-24 Pro. 5942-south of Franklinton West Leg White Castle Toca East Leg Shadyside Co
Slide 15: SNG South Louisiana System Maint. Review
SNG South Louisiana System Maint. Review July/August/September/October Pipeline maintenance FGL 7-5-24 to 8-8-24 Seg. 370 cap. 1,123 Mdth/d impacted 20 Mdth/d SESH pipeline maintenance South of Gwinville 8-10-24 to 8-11-24 Gwinville Meters affected 606610 SESH - SESH TO Pipeline maintenance SNG FGLL
Slide 16: SNG South Louisiana System Maint. Review Cont.
SNG South Louisiana System Maint. Review Cont. July/August/September/October Pipeline maintenance on WCFLL 10-4-24 to 11-1-24 Seg. 350 cap. 735 Mdth/d impacted 200 Mdth/d Gwinville Pro. 2861-north of White Castle Pearl River Pipeline maintenance DLFL 9-4-24 to 9-14-24 MS LA Seg. 350 cap. 735 Mdth/d
Slide 17: EEC Line
EEC Line July/August/September/October Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Elba Rankin Bay Springs Selma Elmore Gallion
Slide 18: SNG North System Pigging Review - Remainder of year
SNG North System Pigging Review Remainder of year Chattanooga Huntsville Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Bear Creek Storage AL Logansport Bienville Rankin LA Compressor Station Storage Field Souther
Slide 19: SNG North System Maint. Review - Remainder of year
SNG North System Maint. Review Remainder of year Huntsville Rome AL Muldon Storage Atlanta Tarrant Bell Mills MS McConnells Pell City Reform DeArmanville Providence Louisville Pickens GA Onward Bear Creek Storage AL Logansport Bienville Rankin LA Compressor Station Storage Field LNG Southern will be
Slide 20: SNG South System Pigging Review - Remainder of year
SNG South System Pigging Review Remainder of year MS Hartwell Aiken Atlanta Wrens GA Ocmulgee AL Ellerslie Hallgate Auburn Thomaston Elba Riceboro Gallion Selma Elmore Holy Trinity York Enterprise Bay Springs Gwinville Albany Brookman Pavo Compressor Station Storage Field LNG Southern will be conduc
Slide 21: SNG South System Maint. Review - Remainder of year
SNG South System Maint. Review Remainder of year MS Hartwell Aiken Atlanta Wrens GA Ocmulgee Hallgate AL Ellerslie Auburn Thomaston Elba Gallion Selma Elmore Riceboro York Holy Trinity Enterprise Bay Springs Gwinville Albany Brookman Pavo Compressor Station Storage Field LNG Southern will be conduct
Slide 22: SNG South Louisiana System Pigging Review - Remainder of year
SNG South Louisiana System Pigging Review Remainder of year Gwinville Pearl River MS LA Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station Storage Field Southern will be conducting other general maintenance during this period 22
Slide 23: SNG South Louisiana System Maint. Review - Remainder of year
SNG South Louisiana System Maint. Review Remainder of year Gwinville Pearl River Pipeline maintenance on WCFLL 11-4-24 to 11-30-24 Stopple bypass to be used MS Proj-2861-north of White Castle LA Franklinton West Leg White Castle Toca East Leg Shadyside Compressor Station Storage Field Southern will
Slide 24: EEC Line - Remainder of year
EEC Line Remainder of year Chattanooga Rome Hartwell SC Muldon North System Bell Mills GA MS McConnells Tarrant Atlanta Aiken Reform DeArmanville Providence Pell City Hall Gate Wrens Louisville Ocmulgee Pickens Ellerslie Bear Creek Onward Auburn Thomaston Elba Rankin Bay Springs Selma Elmore Gallion
Slide 25: Gas Control Contacts
Gas Control Contacts Skyler Spyker – Manager • (713) – 420 – 2386 (office) • (806)-470-7743 (cell) • skyler_spyker@kindermorgan.com Kal Dankovich – Outage Coordinator • (205) – 533 – 4795 (cell) • kalman_dankovich@kindermorgan.com Mario Murillo – Outage Coordinator • (281) – 753 – 6530 (cell) • mari
Slide 26: Questions?
Questions? 26