Rockhaven Resources Ltd. · TSXV:RK

Rockhaven Resources — Investor Presentation (July 2020)

20 slides from Rockhaven Resources's investor presentation, July 2020

  1. Slide 1: Klaza: The Yukon's Next Big Gold Story

    Shee Klaza: The-Yu July 2020 TSX-V: RK Re, ed kon’s Next Big Gold Story ie en Rockhaven RESOURCES LTD.

  2. Slide 2: Forward Looking Statements

    FORWARD LOOKING STATEMENTS Certain information contained herein may constitute forward-looking statements within the meaning of applicable securities laws. Forward-looking statements may include estimates, plans, expectations, opinions, forecasts, projections, guidance or other statements that are n

  3. Slide 3: Why Invest in Rockhaven?

    WHY INVEST IN ROCKHAVEN? • Rockhaven’s road accessible Klaza project is one of Yukon’s highest grade, plus one million ounce gold deposits • Robust PEA with a Post-Tax NPV(5%) of C$378 million and an IRR of 37% • Klaza Deposit is 100% owned and royalty free • District scale land position with signif

  4. Slide 4: Corporate & Capital Structure

    CORPORATE & CAPITAL STRUCTURE Number of Warrants Price Expiry Date Outstanding SHARES OUTSTANDING: 187,635,593 500,000 $0.165 August 5, 2020 SHARES FULLY DILUTED: 229,228,413 2,000,000 $0.20 August 31, 2020 3,333,333 $0.20 Nov 12, 2022 MARKET CAPITALIZATION: $32,000,000 26,684,487 $0.20 August 30, 2

  5. Slide 5: Northern Cordilleran Gold Province

    NORTHERN CORDILLERAN GOLD PROVINCE SENIOR GOLD PRODUCERS ACTIVE • May 2016 – Goldcorp (now NEM) acquires KAM Coffee Deposit for C$520M • June 2018 – Kinross announces US$100M investment in Ft. Knox • July 2018 – Newmont acquires 50% of Galore for US$275M • Aug 2018 – Northern Star acquires Pogo for

  6. Slide 6: >15 Million Gold Oz Identified in Dawson Gold Belt

    >15 MILLION GOLD OZ IDENTIFIED IN DAWSON GOLD BELT Access Road to Klaza Camp Klaza Deposit TSX-V:RK OTC:RKHNF 6

  7. Slide 7: Klaza Deposit Plan View

    KLAZA DEPOSIT PLAN VIEW • Upper portions of only 3 out of 11 known zones are in resources • Excellent potential to expand along strike, down dip and on other known zones on the camp scale property 1,000 m *Gold equivalent values for mining purposes assume base case metal prices and recoveries are ca

  8. Slide 8: June 2018 Mineral Resource Estimate

    JUNE 2018 MINERAL RESOURCE ESTIMATE Grade Contained Metal Tonnes Au Ag Pb Zn AuEQ4 Au Ag Pb Zn AuEQ4 (kt) (g/t) (g/t) (%) (%) (g/t) (koz) (koz) (klb) (klb) (koz) Indicated3 4,457 4.8 98 0.7 0.9 6.3 686 14,071 73,268 92,107 907 Inferred3 5,714 2.8 76 0.6 0.7 3.9 507 13,901 77,544 89,176 725 Central K

  9. Slide 9: Klaza Deposit Analogs

    KLAZA DEPOSIT ANALOGS • Similar deposit model to Buriticá, Porgera and Kelian; all major global gold deposits > 5 million ounces • Buriticá (Colombia) is now owned by Zijin Mining after purchase of Continental Gold for $1.4 billion in 2019; Porgera (PNG) is owned and operated by Barrick Gold and Zij

  10. Slide 10: 2020 PEA Highlights

    2020 PEA HIGHLIGHTS • Pre-tax NPV(5%) of $529 million and IRR of 45%, and a post-tax NPV(5%) of $378 million and IRR of 37% • Exceptional value at $1,740 gold price: post-tax NPV(5%) of $540 million and IRR of 49% • Avg LOM operating cash cost of US$613/oz AuEQ* and total all-in sustaining cost of U

  11. Slide 11: 2020 PEA Summary

    2020 PEA SUMMARY Unit July 2020 Unit July 2020 PEA PEA Total mineralized rock kt 7,464 Total net revenue C$M 1,975 Total waste production kt 10,130 Initial capital costs C$M 244 Gold grade1 g/t 3.4 Sustaining capital costs C$M 114 Silver grade1 g/t 79 Operating costs (total) C$M 834 Lead grade 1 % 0

  12. Slide 12: 2020 PEA Details

    2020 PEA DETAILS • A combination of contractor open pit and owner-operator underground • U/G mining will use mechanized longhole open stoping on 25 m sub-levels with min. widths of 3 m • Twelve year mine life • Two years open pit mining • Peak annual production of 688 kt in years 2 thru 7 (1,900 tpd

  13. Slide 13: Klaza Project – PEA Surface Overview

    KLAZA PROJECT – PEA SURFACE OVERVIEW BRX Western BRX Portal Mill Area KLAZA Tailings Storage Open Pits: 1.2 Mt mined containing approximately: 90,000 oz gold, 1.3 Moz silver, 11.1 Mlbs lead, and 18.1 Mlbs zinc *Project wide average mined grades are 3.40 g/t Au, 78.88 g/t Ag, 0.61% Pb, and 0.73% zinc

  14. Slide 14: Klaza 2020 PEA – Mine Plan

    KLAZA 2020 PEA – MINE PLAN Open Pits: 1.2 Mt mined containing approximately: 90,000 oz gold, 1.3 Moz silver, 11.1 Mlbs lead, and 18.1 Mlbs zinc Central BRX UG, 1.3 Mt mined containing approximately: 69,000 oz gold, 4.0 Moz silver, 25.6 Mlbs lead, and 26.4 Mlbs zinc Western BRX UG, 2.4Mt mined contai

  15. Slide 15: Production Summary

    PRODUCTION SUMMARY Annual Payable Metal Production TOTAL 1 2 3 4 5 6 7 8 9 10 11 12 Gold (oz) 751,472 48,656 58,572 93,011 98,195 93,775 82,318 80,087 62,401 49,947 45,485 26,433 12,592 Silver (oz) 13,799,820 588,268 765,112 1,645,459 1,499,457 1,544,120 1,430,480 1,560,272 1,145,208 1,031,574 1,133

  16. Slide 16: 2020 PEA Sensitivities

    2020 PEA SENSITIVITIES Post-Tax Sensitivities -20% Base Case +20% Variable Unit Value NPV IRR Value NPV IRR Value NPV IRR Gold US$/oz $1,160 $211 24% $1,450 $1,740 $540 49% Silver US$/oz $13.60 $343 35% $17.00 $20.40 $407 39% $378 37% Mining Cost $/t $44.1 $417 39% $55.14 $66.2 $334 34% Processing C

  17. Slide 17: Simplified Processing Flow Sheet

    SIMPLIFIED PROCESSING FLOW SHEET Lead (1.1% Mass Pull) Acacia Leach 59.8% Pb 60% Pb Crushing & Grinding 5,957 g/t Ag 4,815 g/t Ag 129.9 g/t Au 15.7 g/t Au 1,900 tpd Sequential Flotation Zinc 95% Au Recovery • High recovery of all metals to (2.2% Mass Pull) 86% to Doré three separate concentrates 48.

  18. Slide 18: New Discoveries for Resource Expansion

    NEW DISCOVERIES FOR RESOURCE EXPANSION New mineralized zones discovered in recent exploration drilling at Central and Western Klaza Resource Pearl Zone Victoria • 5.28 g/t gold and 1,054 g/t silver over 1.60 m (drill) • 12.60 g/t gold and 312 g/t silver over 0.46 m (drill) • 9.43 g/t gold and 180 g/

  19. Slide 19: Klaza Project Next Steps

    KLAZA PROJECT NEXT STEPS • 2020/21 Work – Aggressive in-fill drilling to convert remaining inferred ounces to indicated; discovery drilling on outboard targets • Accelerated engineering, metallurgy & permitting studies • Pre-feasibility study and advancement into permitting TSX-V:RK OTC:RKHNF 19

  20. Slide 20: Contact Info

    Contact Info: Matt Turner Phone: 604-688-2568 E-mail: mturner@rockhavenresources.com Website: www.rockhavenresources.com TSX-V:RK Appendices to follow

Rockhaven Resources — Investor Presentation (July 2020) on 6ix