  1. Slide 1: Mosenergo Investor Presentation

    MOSENERGO Investor Presentation March, 2017

  2. Slide 2: Disclaimer

    Disclaimer The information contained herein has been prepared using information available to JSC “Mosenergo” (hereinafter - Mosenergo or the Company) at the time of preparation of the presentation. External or other factors might have impacted the business of Mosenergo and the content of this presen

  3. Slide 3: Mosenergo Profile

    Mosenergo Profile Operational Profile Total electric capacity 13 GW Mitischi Total heat capacity 42.9 thous Gcal/h Elektrogorsk Number of power plants under management 15 2016 Electricity output 59,068 mln kWh 2016 Heat output 81,827 thous Gcal CSA1 capacity in work 2.9 GW Stock Market Profile Total

  4. Slide 4: 12M 2016 Highlights (IFRS)

    12M 2016 Highlights (IFRS) Operational Highlights1 Financial Highlights, mn RUR 12M 2015 12M 2016 Change 12M 2015 12M 2016 Change Revenue 171,163 190,656 +11.4% Electricity Output, mn kWh 54,712 59,068 +8.0% Variable Costs (114,061) (126,240) +10.7% Electricity Sales, mn kWh 56,349 60,858 +8.0% Fixe

  5. Slide 5: Prices and Tariffs in Revenue (IFRS)

    Prices and Tariffs in Revenue (IFRS) Revenue, mn RUR Electricity and Capacity Revenue Structure for 12M 2016, % -66.2% 2,452 7,255 Other Revenue +11.4% 77,879 69,906 35% Electricity Heat +17.4% Capacity 94,002 110,325 Electricity and Capacity 65% 12М 2015 12М 2016 Prices and Tariffs Parameter 12M 20

  6. Slide 6: Investment Program

    Investment Program Mosenergo CSA1 Program • Mosenergo has accomplished all obligations in Capacity, MW Date of launch CSA investment program TPP-27 2x450 01.2011 • 9 units with total capacity more than 2.8 GW have been commissioned from 2011 TPP-21 425 01.2011 Pavlovski Posad (GRES-3) 16 01.2011 • N

  7. Slide 7: New Capacity

    New Capacity CSA Units Production CSA Units Share in Total Electricity Output 16,058 27.2% 14,043 25.7% 11,748 20.7% 11,058 18.9% 10,067 16.4% 3,514 3,915 4,133 3,454 2,811 2012 2013 2014 2015 2016 2012 2013 2014 2015 2016 Electricity Output, mln kWh Heat Output, thous Gcal Average price of CSA capa

  8. Slide 8: Capacity Decommission

    Capacity Decommission Mosenergo Capacity Decommission Program1 • In 2015 Mosenergo has approved capacity Capacity, MW Date of removal decommission program (585 MW to 2020) which was accepted by Energy Ministry TPP-8 25 01.02.2016 and System Operator. • Unit no. 9 at TPP-22 removed from work in TPP-1

  9. Slide 9: Dividends

    Dividends Dividend Payments 2 500 40% 2,244 35% 2 000 30% 1,584 1 500 1,188 1,188 25% • The Dividend Policy of Mosenergo allows 20% 1 000 792 to pay 5-35% of net income (RAS). 15% 500 396 10% • Major shareholder of Mosenergo can 5% decide to change dividends base from RAS 0 0% 2010 2011 2012 2013 20

  10. Slide 10: Debt and Liabilities (IFRS)

    Debt and Liabilities (IFRS) Liabilities Structure, mn RUR Maturity Profile as of December 31, 2016, mn RUR (book value) Total 48,970 -12.2% Total 43,002 Other loans 880 105 0 0 Unsecured bond issues 47,985 -10.4% 43,002 Unsecured bank loans December 31, 2015 December 31, 2016 19,750 3,750 Unsecured

  11. Slide 11: Thank You for Your Attention!

    Thank You for Your Attention! IR contact: Denis Voronchikhin Tel. (495) 957-1-957 (ext. 3457) VoronchikhinDS@mosenergo.ru