Kingsrose Mining — RIU Resources Round Up Conference 2014

21 slides from Kingsrose Mining's conference presentation, May 13, 2014

  1. Slide 1: ASX Announcement: Corporate Presentation

    ASX Announcement 13 May 2014 For personal use only CORPORATE PRESENTATION Kingsrose Mining Limited (ASX:KRM) is pleased to provide a copy of the presentation to be given by Managing Director, Scott Huffadine at the RIU Resources Round Up Conference being held in Sydney this week. The presentation wi

  2. Slide 2: The Way Linggo Project: High Grades, Low Costs & Robust Margins

    For personal use only The Way Linggo Project High Grades, Low Costs & Robust Margins RIU Conference, May 2014 ASX:KRM www.kingsrosemining.com.au

  3. Slide 3: Disclaimer & Competent Persons Statement

    Disclaimer & Competent Persons Statement The information contained in this document (“Presentation”) has been prepared by Kingsrose Mining Limited (“Kingsrose” or the “Company”). This Presentation does not constitute an offer or invitation to any person to subscribe for or apply for any securities i

  4. Slide 4: Kingsrose Mining Limited – A Snapshot

    For personal use only Kingsrose Mining Limited – A Snapshot Corporate Snapshot (ASX:KRM)1 Board of Directors Shares on issue 359 million John Morris Chairman Share Price ~42c Scott Huffadine Managing Director Market Cap ~$150 million Bill Phillips Non Exec Director Av. Daily Volume ~230,000 Andrew S

  5. Slide 5: The Value Proposition

    For personal use only The Value Proposition Low cost, high grade, high margin gold production 1 Established Project and infrastructure 2 Board and Management with significant in-country and operating 3 experience Project pipeline with advanced exploration via shaft at Talang Samin & 4 significant ex

  6. Slide 6: Project Location – "Rim of Fire"

    Project Location – “Rim of Fire” Located on the prolifically mineralised Trans-Sumatran Fault For personal use only • Extensive and strategic landholding located in the “Rim of Fire” on the Trans-Sumatran Fault Zone • World’s second most significant source of Tertiary Age gold deposits • +1Moz Au pr

  7. Slide 7: Way Linggo Project - Highlights

    Way Linggo Project - Highlights The Way Linggo Mine produced ~65Koz @ 13.1 g/t Au at an average C1 cost of USD$207/oz and C3 cost of USD$491/oz and generated EBITDA of USD$83M1 For personal use only • 2 mines – Way Linggo Mine & Talang Santo Mine on 100km2 of proven and highly prospective geology •

  8. Slide 8: Current Status – Talang Santo

    For personal use only Current Status – Talang Santo • Final regulatory steps: final approval for extension to existing Project environmental assessment (AMDAL) and forestry permit ‘pinjam pakai’ • KRM & PTNM have now met all obligations in relation to the submission and review of the required regula

  9. Slide 9: The Talang Santo Mine

    The Talang Santo Mine • Located 17km by established haul road from the processing For personal use only plant • Phase 1 of current mine plan – 6 Levels at 50m spacing • 3 Levels already established and preparations for an internal shaft to 4 Level completed • Installed hoisting capacity for 500tpd •

  10. Slide 10: Talang Santo – Significant Upside

    For personal use only Talang Santo – Significant Upside • A much larger system by virtue of the entire mineralised system being preserved, drilled and open to 500m depth • Multiple vein orientations • Grades from development continue to exceed mine modelling • Grade from recent mill trial indicates

  11. Slide 11: Talang Santo – The Mineralised Zone

    For personal use only Talang Santo – The Mineralised Zone 10

  12. Slide 12: Talang Santo – The Splay Vein

    For personal use only Talang Santo – The Splay Vein • Weighted average grade across 75 metres of development is 23.2 g/t Au and 99.6 g/t Ag and remains open in all directions • The Splay vein was previously interpreted from limited surface drill intercepts in the initial Talang Santo geological mode

  13. Slide 13: The Splay Vein – New Mineralised Orientation

    For personal use only The Splay Vein – New Mineralised Orientation 12

  14. Slide 14: Growth Strategy – Tiered Approach

    For personal use only Growth Strategy – 3 Tiered Approach • Immediate focus on near mine resource development opportunities within development range Near Mine from existing Talang Santo infrastructure • Evaluate the advanced exploration play at the Talang Samin Shaft Advanced • Recovery of remnant r

  15. Slide 15: Talang Santo Mine

    Talang Santo Mine Mine adit For personal use only 2L winze Main Shaft Limit of current mine plan OPEN NSA NSA Talang Santo 14

  16. Slide 16: Talang Cluster – Talang Samin

    Talang Cluster – Talang Samin Talang Samin represents an advanced exploration prospect with the potential to add production tonnes to support a mill expansion For personal use only • The “Talang Cluster” – multiple structures out cropping at surface within a 2km radius of the Talang Santo Mine • Exp

  17. Slide 17: Contract of Work – Organic Growth by Exploration

    Contract of Work – Organic Growth by Exploration • Numerous defined epithermal targets For personal use only within the 100km2 Project area • Complete infill of project scale dataset with surface mapping of alteration, structure and geochemistry and integrate with geophysics • Back analyse the known

  18. Slide 18: Health, Safety & the Environment

    Health, Safety & the Environment Recipient of “Golden Flag’ certificate in recognition for the creation of a safe and responsible work environment For personal use only Occupational Health & Safety • Site is currently 12 months Lost Time Injury (LTI) Free • Ongoing review and improvement of Site Saf

  19. Slide 19: Community - Cooperation & Engagement

    Community - Cooperation & Engagement Health Initiatives For personal use only • Food & equipment donations • Subsidised medical care, including malaria control & prevention Education Initiatives • Student scholarships & teacher allowances • School building renovations Economic Stimulus • Employment

  20. Slide 20: Contact Details

    Contact Details: For personal use only Scott Huffadine – Managing Director +61 8 9486 1149 info@kingsrosemining.com.au www.kingsrosemining.com.au ASX:KRM ACN 112 389 910 19

  21. Slide 21: Appendix – Way Linggo Project Mineral Resource Statement

    Appendix 1 – Way Linggo Project Mineral Resource Statement As at 30 June 2013 Classification Tonnes Gold (Au) g/t Silver (Ag) g/t Au ounces Ag ounces For personal use only Talang Santo Measured Indicated 863,625 6.2 16 171,873 451,200 Inferred 797,355 4.5 17 115,616 443,751 Subtotal 1,660,980 5.4 17