Slide 1: Stakeholder Consultation Meeting
Stakeholder Consultation Meeting Oakdale West Estate May 2020 1
Slide 2: Overview
Overview Welcome and Introductions Approvals and Modifications Update Project Update – OWE – Burton Contractors Project Update – WNSLR – Robson Contractors Environmental Performance Safety Update Consultation and Community Interactions Stakeholder Feedback & Questions 2
Slide 3: Welcome and Introductions
Welcome and Introductions Project Team: Organisation Goodman AT&L SLR Consulting Ersed Role Proponent Project Manager & Contract Stakeholder Engagement Environmental Superintendent Representative Key Contacts Stephanie Partridge Alex Lohrisch Dan Thompson Carl Vincent Kym Dracopoulos Dane Segail Kat
Slide 4: Approvals and Modifications Update
Approvals and Modifications Update • Modifications 1-4 to SSD 7348 Approved • SSD 10397 for Stage 2 Warehouse Development Approved • Staging Plan to be discussed 4
Slide 5: Project Progress To Date - OWE
Project Progress To Date - OWE • Earthworks to 2B Pad all but completed. • Precinct 4 Earthworks – 5% completed. • Precinct 1 Earthworks – 60% completed. • Western Bund Earthworks – 100% completed. • Precinct 2 Earthworks – 75% completed. • Sewer Works – 20% completed. • Precinct 3 Earthworks – 90%
Slide 6: May/June Project Program – OWE
May/June Project Program – OWE • Complete 2B Pad for Qanstruct. • Continue with retaining wall works. • Complete bio basin 2/3. • Commence stormwater works. • Continue with earthworks to all Precincts. • Finalise new entry to site from Construction • Trim pads as lots are completed. Access Road. • C
Slide 7: Project Progress To Date - WNSLR
Project Progress To Date - WNSLR North: • Bulk earthworks Stormwater and services installation across Lockwood Road • Power outage electrical works along Lockwood Road Bridge: • Pipeline protection measures and bulk earthworks of both batters • Access consent approvals from WaterNSW received allowin
Slide 8: May/June Project Program – WNSLR
May/June Project Program – WNSLR North: • Complete stormwater and services installation • Commence pavement construction • Commence Lenore Drive intersection works • Commence retaining wall construction Bridge: • Install temporary crossing of Ropes Creek • Construct bridge piles • Commence bridge co
Slide 9: Consultation and Community Interactions
Consultation and Community Interactions • Online consultation meeting undertaken with Emmaus College, Trinity Primary and Mamre Anglican Schools to confirm traffic arrangements associated with the Stage 2 development and specifically to advise that Bakers Lane will not be utilised during peak school
Slide 10: ER Inspections and Audits
ER INSPECTIONS AND AUDITS ER INSPECTIONS NOV 2019 1 – WNSW PIPELINE PRE COMMENCEMENT DEC 2019 2 JAN 2020 4 FEB 2020 5 MAR 2020 7 APRIL 3 MAY (PART) 2 TOTAL TO DATE 24 Copyright © ErSed 2011
Slide 11: Environmental Performance
ENVIRONMENTAL PERFORMANCE INCIDENTS AND COMPLAINTS AS DETAILED IN THE MONTLY REPORTS POTENTIAL INCIDENTS NIL COMPLAINTS 26/04/20 From 20 Aldington Rd Complaint re depositional dust Response to complaint handled in accordance with AQMP and CCS Copyright © ErSed 2011
Slide 12: Environmental Performance
ENVIRONMENTAL PERFORMANCE NON COMPLIANCES, NON COMPLIANCE # 001 09/04/20 : D141 & D143 D141: The Applicant must make each Compliance Report publicly available no later than 60 days after submitting it to the Department and notify the Department in writing at least 7 days before this is done. D143:At
Slide 13: Oakdale West Entry
Oakdale West Entry • Site Entry Point has now been completed with a concrete crossover & a sealed road to the Waratah Development. • Benefits: – Aim to reduce the dust generation on site; – Aim to reduce the dust being tracked onto Bakers Lane; – Consolidate traffic into one single entry to prevent
Slide 14: Safety
Safety • No external safety incidents • Minor internal safety incidents – No injuries 14
Slide 15: Communications and Consultation Channels
Communications and Consultation Channels Sources of information and complaints/enquiries via: • Website: oakdaleopportunities.com • Email: community.oakdalewest@goodman.com • Phone: 1300 002 887 • Post: Level 17, 60 Castlereagh Street, Sydney, NSW 2000 • Community Meetings: Subject to scheduling • E
Slide 16: Stakeholder Feedback & Questions
Stakeholder Feedback & Questions 16