Highfield Resources Limited · ASX:HFR

Highfield Resources — Investor Presentation (March 2022)

27 slides from Highfield Resources's investor presentation, March 2022

  1. Slide 1: Constructing the Next European Potash Mine

    Constructing the Next European Potash Mine Corporate Presentation March 2022 ASX: HFR

  2. Slide 2: Competent Persons Statement for Muga Ore Reserves and Mineral Resources

    COMPETENT PERSONS STATEMENT FOR MUGA ORE RESERVES, MUGA MINERAL RESOURCES and EXPLORATION TARGET This update was prepared by Mr. Ignacio Salazar Director of Highfield Resources. The information in this update that relates to Ore Reserves is based on information prepared under the direction of Dr Mik

  3. Slide 3: Global Potash Prices on the Move at the Right Time

    Global Potash Prices on the Move at the Right Time Strong market fundamentals Upward price forecasts 700 2.0 10.0 8.0 600 Soybean prices are the Billions of tonnes 1.5 Billion 6.0 highest in 5 years USD/t 1.0 500 4.0 0.5 2.0 400 0.0 0.0 1980 1983 1986 1989 1992 1995 1998 2001 2004 2007 2010 2013 201

  4. Slide 4: An Investment Opportunity in the Next Major European Potash Mine

    An Investment Opportunity in the Next Major European Potash Mine Muga Potash Mine Highfield Resources Strong market fundamentals Strong financial position and Global potash prices on the move financial markets support Location is a major strategic advantage Experienced Management Shallow mineralizat

  5. Slide 5: Corporate Snapshot

    Corporate Snapshot Capital Structure Share Price (30 March 2022) $1.03 1.20 60 Shares on Issue 364.4 million 1.00 50 Options & Performance Rights - Volume (100,000 shares) Market Capitalisation $375.33 million 0.80 40 Share price (A$) Cash (31 December 2021) $22.24 million Drawn Debt* - 0.60 30 Ente

  6. Slide 6: Strong Board with Global Mining Industry Experience and Robust Governance Processes

    Strong Board with Global Mining Industry Experience and Robust Governance Processes Paul Harris Ignacio Salazar Independent Non-Executive Director MD & Chief Executive Officer Chairman Paul has over 25 years’ experience in financial markets Ignacio has over 30 years’ experience, most of which and in

  7. Slide 7: Management with strong mining experience and local background

    Management with strong mining experience and local background Javier Aguado Susana Bieberach Chief Financial Officer Public Affairs Javier has over 20 years’ accounting and financial 15 years of experience in communication and CSR Ignacio Salazar experience. He has worked for Ernst and Young and fie

  8. Slide 8: Muga Project Overview

    Highfield 7 Resources MUGA PROJECT OVERVIEW

  9. Slide 9: Highfield Resources and the Muga Project

    Highfield Resources and the Muga Project Conventional Underground A potash developer listed on Muga is a two phase project Room and Pillar mining. Conventional Flotation and the ASX (HFR) with projects which will produce a total of Declines accessing shallow Crystallisation processing in Northern Sp

  10. Slide 10: A Major Industrial Project

    A Major Industrial Project GEOLOGY: The geological characterisation of Muga has been determined from 40 drillholes, separated approximately 1 km from each other UNDERGROUND MINE - Access to mineralisation at 350m depth through two ramps (6m wide x 5m high) of 2.6km length - 50km of rooms - Undergrou

  11. Slide 11: Shallow Mineralization, Conventional Mining, with Tier-One Infrastructure in Place

    Shallow Mineralization, Conventional Mining, with Tier-One Infrastructure in Place 350m Decline access to shallow mineralization; Close to the Port of Bilbao (~220km), underground Room and Pillar mining. No aquifers Spain’s largest port First class infrastructure and National Electricity Grid Substa

  12. Slide 12: Significant Logistical Competitive Advantage

    Significant Logistical Competitive Advantage Extremely competitive and versatile export options ~1,750km from mines to port ~1,700km from mines to port Muga will be one of only two potash mines located in Southern Europe ~130- 220km from ~6,800 nautical miles mine to ports ~8,700 nautical miles ~5,0

  13. Slide 13: MOU signed for more than phase 1 production

    MOU signed for more than phase 1 production MOP sales (pa) Wider Europe: Salt sales (pa) • ~250-300 kt MOP • ~200-250 kt salt US East Coast: • ~50 kt MOP Local: • ~200-250 kt salt Potash MOUs signed • ~450-500 kt MOP • ~400-500 kt salt MOP Ameropa 250,000 tpa Africa: Keytrade 300,000 tpa • ~50 kt MO

  14. Slide 14: Project Economics

    Highfield 7 Resources PROJECT ECONOMICS

  15. Slide 15: Top Quartile Margins in the Industry

    Top Quartile Margins in the Industry European prices continue to trade at a premium to Margin curve forecast for 2024 (real US$) other markets​ 750.0 200 650.0 150 550.0 100 450.0 50 US$/t 350.0 00 250.0 0 10 20 30 40 50 60 70 150.0 -50 2016 2017 2018 2019 2020 2021 2022 -100 Millions of tonnes of M

  16. Slide 16: Low Capex Intensity and Strong Project Economics

    Low Capex Intensity and Strong Project Economics Phase 1 capex of €398 million + Phase 2 capex of €209 million MUGA: HALF THE CAPEX INTENSITY OF OTHER GLOBAL DEVELOPMENT PROJECTS (US$ per tonne of potash) 2,000 Capex intensity $/t 1,500 1,000 500 - BHP (Jansen) Canadian mine BHP (Jansen) Eurochem K+

  17. Slide 17: Updated Feasibility Study Reconfirms Muga's Strong Economics

    Updated Feasibility Study Reconfirms Muga’s Strong Economics Updated capex numbers with NPV8 of €1.89 Billion More advanced engineering higher degree of accuracy: 25% IRR reconfirming a 30-year mine life1 phase 1 €398 million phase 2 of €209 million At current spot price Debt term sheet agreed for A

  18. Slide 18: Muga Mine – Key Physicals and Financials

    Muga Mine – Key Physicals and Financials 2 December 2021 CAPEX phase 1 (500,000 tpa MOP) €398 million CAPEX phase 2 (Additional 500,000 tpa MOP) €209 million Total CAPEX €607 million ROM tonnes 173.7 million tonnes Average plant tonnage feed rate 400 tph K2O grade 10.5% KCl recovery 91% LOM MOP prod

  19. Slide 19: Status and Next Steps

    Highfield 7 Resources STATUS AND NEXT STEPS

  20. Slide 20: Muga Moving to Construction

    Muga Moving to Construction 2021 2022 2023 2024 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Contract with construction partner Finalise procurement of process plant long-lead items Electricity line Authorisation Mining Concession Local town hall construction licenses Equity Debt term raise sheet agreed Finalise funding

  21. Slide 21: Sustainability

    Highfield 7 Resources SUSTAINABILITY

  22. Slide 22: Industry Leading ESG Credentials

    Industry Leading ESG Credentials • Environmental compliance and commitment through DIA award Environmental • Progressively rehabilitate mine: Backfilling and salt sales • Muga will be the only mine not to leave residue on the surface after production Factors • Strong local support in favour of the M

  23. Slide 23: Appendix

    Highfield 7 Resources Appendix

  24. Slide 24: Current supply restriction making Muga even more strategically important

    Current supply restriction making Muga even more strategically important % of Global Production • Russia and Belarus accounted for 38% of worldwide production in 2021, or about 27 Mt of potash. • With sanctions on Belarus starting to come into effect, and new measures targeting Russia’s economy due

  25. Slide 25: Differential between MOP and SOP prices

    MOP has performed strongly recently 900 250 Differential between MOP and SOP prices 800 • SOP has historically traded at a premium to MOP 200 700 • SOP is a ~7Mt market vs ~70Mt MOP market • SOP is used for speciality crops where as MOP is US$/t 150 600 used for stable bulk crops like corn, wheat an

  26. Slide 26: Ore Reserve Statement

    Ore Reserve Statement Highfield Resources Investor Presentation 26

  27. Slide 27: ASX:HFR

    ASX:HFR REGISTERED OFFICE 169 Fullarton Road Dulwich SA 5065 Australia SPAIN HEAD OFFICE Avenida Carlos III, 13-15, 1B, 31002 Pamplona, Spain T: +34 948 050 577 | F: +34 948 050 578 FURTHER INFORMATION Ignacio Salazar CEO T: +34 948 050 577 Olivier Vadillo Investor Relations T: +34 609 811 257