Slide 1: Proposal to initiate Expert Working Group on Grid Supporting FFCI
Proposal to initiate Expert Working Group on Grid Supporting FFCI Place your chosen image here. The four corners must just cover the arrow tips. For covers, the three pictures should be the same size and in a straight line. Ben Marshall - System Operator, National Grid GCDF 12/01/18
Slide 2: Overview
Overview Within the GC0100 consultation it was noted that by Jan 2021 there was a requirement for an Option1-like proposal to maintain compliance with EU code defined Voltage against time profiles for a transmission fault. It was noted in GC0100 consultation that should Options 2 or Options 3 be
Slide 3: The problem statement (1)
The problem statement (1):- Current measurement- led convertor control is unable to deliver the instantaneous support to maintain voltage against time support Only an option 1-like non- measurement dependant approach can achieve this at the point of connection interface. 3
Slide 4: The problem statement (2)
The problem statement (2):- Measurement-less reactive current supplied in phase with the load up to 1.5p.u continuous rating is needed during a fault in order to ensure that voltage against time curves are met from 2021 across all FES scenarios considered. Measurement-less control implies that f
Slide 5: The problem statement (4)
The problem statement (4):- Under CP.A. 3.6. in addition a load rejection test is defined for which the power islands formed either side of the separation must be contained. In the Power island created where a surplus of demand exists, a measurement-less control would become unstable/ trip if un
Slide 6: A range of Options
A range of Options:- Control system modification & development. It is not clear to what extent should the capability of the User convertors be developed with appropriate modification to achieve the above measurement-less control nor where appropriate use of storage or other short term resources
Slide 7: Next Steps proposal
Next Steps proposal We propose to establish a two stage Expert Working Group:- Stage1; framework supporting further focussed engagement across manufacturers and industry on the functional needs for sufficient FFCI, together with further appreciation of those considerations impacting the technolo