Nordic Mining ASA · OSL:NOM

Nordic Mining ASA — Q4 2008 Earnings Presentation

34 slides from Nordic Mining ASA's earnings presentation, Feb 27, 2009

  1. Slide 1: Q4 2008

    Q4, 2008 February 27th, 2009 Ivar S. Fossum, CEO Exploration and production of high-end minerals and metals Nordic Mining ASA | N-0250 Oslo | Norway | Tel +47 22 94 77 90 | Fax +47 22 94 77 01 | Org. no 989 796 739 | post@nordicmining.com

  2. Slide 2: Disclaimer

    Disclaimer This document has been used by Nordic Mining during an oral presentation. Therfore, this document is incomplete without the oral explanations, comments and supporting instruments that were submitted during the referred presentation. To the extent permitted by law, no representation or war

  3. Slide 3: Agenda

    1. Highlights 2. Preliminary report per 31.12.08 3. Projects and plans

  4. Slide 4: Highlights

    Highlights Plan for development and operation and EIA for Engebø completed and filed Scoping study completed, confirming combined mining scenario Production of high quality garnet verified Significant downturn in the market for anorthosite products Anorthosite qualified as capping material for conta

  5. Slide 5: 2. Preliminary report per 31.12.08

    2. Preliminary report per 31.12.08

  6. Slide 6: Preliminary P&L per December 2008

    Preliminary P & L per 31 December 2008 Year Year Q4-08 Q4-07 Amounts in NOK million 2008 2007 Unaudited Unaudited Unaudited Audited 5.7 5.3 Sales 17.8 12.1 0.1 0.2 Other income 0.2 0.5 0 (0.8) Cost of sales (1.4) (3.5) (4.1) (1.9) Payroll and related costs (11.8) (5.4) (2.0) (0.7) Business service/M

  7. Slide 7: Preliminary Balance Sheet per December 2008

    Preliminary Balance Sheet per 31 December 2008 Amounts in NOK million 31.12.08 31.12.07 Unaudited Audited Non-current assets 98.1 50.9 Cash 39.8 23.7 Other current assets 7.6 6.1 Total assets 145.6 80.8 Equity 78.5 46.0 Non-current liabilities 47.6 22.1 Current liabilities 19.5 12.7 Total equity and

  8. Slide 8: Financial position

    Financial position • Financial flexibility for planned activities into 2010 • Limited financial committments in 2009 • Focus on value driving milestones • Strategic position constitutes a solid base for industrial and future partnerships

  9. Slide 9: Stable shareholder base

    Stable shareholder base *) *) As per 23.02.09

  10. Slide 10: 3. Projects and plans: Engebø - Ti

    3. Projects and plans Engebø - Ti

  11. Slide 11: Engebøfjellet, Europe's new titanium source

    Engebø rutile project Engebøfjellet, Europe’s new titanium source Target: To position Engebø as a long term supplier to the European pigment industry and producers of Ti metal

  12. Slide 12: Industrial area permit and EIA

    Industrial area permit and EIA • All important environmental and social aspects covered through: Industrial area permit Waste disposal permit Environmental impact analysis • Filed with municipalities on February 19th • Largest EIA in Norwegian mining industry – 30 sub analysis • Comprehensive analys

  13. Slide 13: Plan for mining and operation

    Plan for mining and operation Open pit with subsequent underground operation 40-50 yrs

  14. Slide 14: NRK Sogn og Fjordane 27.02.2009

    NRK Sogn og Fjordane 27.02.2009 Har tru pa gruvedrift Gruvedrift i Engebofjellet vil f4 omfattande konsekvensar for miljoet i Vevring og Naustdal. Det syner konsekvensanalysen. ASGEIR REKSNES VEGAR ERSTAD asgeir.reksnes@nrk.no vegar.erstad@nrk.no Publisert 24.02.2009 13:39. Nordic Mining planlegg ei

  15. Slide 15: Visual impact and open pit lay-out

    Visual impact and open pit lay-out

  16. Slide 16: Slide 16

  17. Slide 17: Slide 17

  18. Slide 18: Slide 18

  19. Slide 19: Produksjon av rutil og granat

    Produksjon av rutil og granat

  20. Slide 20: Geological model – scoping study

    Geological model – scoping study Further drilling planned in Q4 Resource Mill. TiO2 % ƒ 50 drill holes (15,000 meters) class JORC tons ƒ >1000 surface samples ƒ 5000 drill hole samples Measured - - ƒ Resource estimate of 382 Mill Indicated 31.7 3.77 tons @ 3.96% TiO2 in situ Inferred 122.6 3.75

  21. Slide 21: Engebø rutile project competitive advantages

    The Engebø rutile project has significant competetive advantages: • Free of radioactive elements • High grade 94 – 96% TiO2 • Simple export logistics • Close to market Feedstock selection factors: Location Cost of consumables Waste disposal costs Freight costs Rel. Economic value Technology Ore comp

  22. Slide 22: Garnet

    Garnet - Capable of making a 95% pure garnet concentrate - 80 mesh waterjet grade (> 150 microns and < 350 microns) - Cutting performance within the range of successful current garnet products on the world market

  23. Slide 23: Silica legislation is driving the garnet market

    “Silica legislation” is driving the garnet market Main applications: Supply/demand: Sandblasting World production: 450 – 500 000 tons Waterjet cutting Expected growth: 3-5% per annum Glass polishing Hard rock garnet Pool filtration Main producers: Alluvial garnet Coated abrasives Water filtration Au

  24. Slide 24: 3. Projects and plans: Gudvangen - anorthosite

    3. Projects and plans Gudvangen - anorthosite

  25. Slide 25: Gudvangen Stein hit by the halt in the building industry

    Gudvangen Stein hit by the halt in the building industry • Sales in January down 50% from December 2008, and 50% down from January 08. • Temporary lay-offs as from February 1st • EU – directives on greenhouse gases will contribute to a regain in the insulation market.

  26. Slide 26: StatoilHydro & Nordic Mining joint cooperation

    Gudvangen anorthosite StatoilHydro & Nordic Mining joint cooperation ”Enhancing value from anorthosite and rutile-eclogite by CO2 based mineral reactions” Target reaction: CO2 (110 kg) Anorthosite 1 tonne Alumina Silica (300 kg) CaCO3 (490 kg) (250 kg)

  27. Slide 27: Enhancing mineral value, binding CO2

    Gudvangen anorthosite Enhancing mineral value, binding CO2 Natural gas Anorthosite 5 mill. tpa CO2 Benchmark figures: 0,55 mill tpa Carbonisation process $mill 1 800 CAPEX $mill 600 REV/YR Recent alumina plant, Hydro Silica Alumina < 2,45 mill tpa 1,5 mill tpa Calcium carbonate < 0,7 mill tpa Tailin

  28. Slide 28: Overall progress plan

    Gudvangen anorthosite Overall progress plan Technical Technical Process design Pilot feasibility feasibility Pilot design & construction lab scale lab pilot engineering & production 2009 2010 • Commercialization strategy • Licensing • IPR strategy • Ensure sufficient rights in contracts

  29. Slide 29: Capping of contaminated sediments

    Capping of contaminated sediments

  30. Slide 30: 3. Projects and plans: Keliber - Li

    3. Projects and plans Keliber - Li

  31. Slide 31: Substantial activity from Nordic players with international partners

    Keliber lithium project Substantial activity from Nordic players – with international partners Lithium Battery Li-batteries Electric / carbonate chemicals hybride vehicles Keliber (Fi) OMG (Fi / US) Miljø Innovasjon (N) / Miljøbil Grenland (N) / Kemira (Fi) Electrovaya (Can) Tata Motors (India) Euro

  32. Slide 32: High-end minerals, an interesting hedge

    Company overview High-end minerals, an interesting hedge Metals and minerals price development 600 500 Gold Nickel 400 Index Zink 300 Iron ore 200 TiO2 100 LiCO3 0 00 Q 0 Q 1 02 Q 3 03 04 Q 5 Q 6 06 07 08 0 0 0 0 0 1- 4- 3- 2- 1- 4- 3- 2- 1- 4- 3- 2- Q Q Q Q Q Q Q Years

  33. Slide 33: Value driving milestones ahead

    Investment highlights Value driving milestones ahead ENGEBØ: 11 Pilot production 20 ENGEBØ: Partner and offtake agreements 10 20 GUDVANGEN: KELIBER: Pilot plant design Project partner and and engineering downstream integration KELIBER: ENGEBØ: Project financing Permits for Project & Waste disposal E

  34. Slide 34: Thank you!

    Thank you ! www.nordicmining.com

Nordic Mining — Q4 2008 Earnings Presentation on 6ix