Corporate presentation August 2018 Exhibit 99.1
Slide 2: Cautionary statements
Cautionary statements Forward-looking statements on in this P "within he meaning of pro Section 278 ites Act of 1933, ded i the projects Act of 1934 os amended ingly the nature statements. The words" onysipoe sume, ‘e fi “torecast.” “nol” "intend “model.” “plan, would.” i ‘the forword- fs i tic nong
Slide 3: Global call on U.S. natural gas
Global call on U.S. natural gas Fundamentals U.S. supply push… …and global demand pull Source: Wood Mackenzie, Tellurian Research. Notes:(1) Includes the Permian, Haynesville, Utica, Marcellus, Anadarko, Eagle Ford. (2) Based on a demand growth estimate of 4.5% post-2020. (3) Capacity required to me
Slide 4: Global commodity requires low-cost solutions
Sources:Kpler, Maran Gas, IHS, Wood Mackenzie. Notes: LNG storage assumes half of fleet is in ballast, 2.9 Bcf capacity per vessel. Average cargo size ~2.9 Bcf, assuming 150,000 m3 ship. In 2017, approximately a third of all LNG cargoes are estimated to be spot volumes. Based on line of sight supply
Slide 5: Managing three risks
Managing three risks Business model Basin Basis Construction Adequate natural gas supply Reliable access to pipelines Site selection and execution Successful projects require a sophisticated strategy to manage complex risks
Slide 6: Building a low-cost global gas business
Building a low-cost global gas business 6 Pipeline Liquefaction Marketing Upstream 11,620 acres in the Haynesville with 1.4 Tcf resource ~$7 billion(1) of pipeline infrastructure projects in development ~$15 billion of liquefaction infrastructure in development International delivery of LNG cargoes
Slide 7: Tellurian will offer equity interests in Driftwood Holdings
Tellurian will offer equity interests in Driftwood Holdings Driftwood Holdings will consist of a Production Company, a Pipeline Network and an LNG Terminal (~27.6 mtpa) Equity will cost ~$1,500 per tonne Customer/Partner will receive equity LNG at tailgate of Driftwood LNG terminal at cost Variable
Slide 8: Tellurian's differentiating factors
Tellurian’s differentiating factors Business model Management track record at Cheniere and BG Group 43% of Tellurian owned by founders and management Guaranteed lump sum turnkey contract with Bechtel $15.2 billion for 27.6 mtpa capacity FERC scheduling notice indicates permits will be received by Ja
Slide 9: Driftwood LNG terminal
Driftwood LNG terminal Note:(1) Engineering, procurement and construction costs before owners’ costs, financing costs and contingencies. Driftwood LNG terminal Land ~1,000 acres near Lake Charles, LA Capacity ~27.6 mtpa Trains Up to 20 trains of ~1.38 mtpa each Chart heat exchangers GE LM6000 PF+ co
Slide 10: LNG projects require supply optionality
LNG projects require supply optionality Basin Source:IHS, DrillingInfo, EIA, Tellurian analysis. 10 mtpa plant with 1.5 bcf/d feedgas requirement stresses basin supply
Slide 11: Pipeline network
Pipeline network Notes: (1) Included in Driftwood Holdings at full development; commercial and regulatory processes in progress and financial structuring under review. Pipeline network Driftwood Pipeline(1) Capacity (Bcf/d) 4.0 Cost ($ billions) $2.2 Length (miles) 96 Diameter (inches) 48 Compressio
Slide 12: Driftwood Holdings' financing
Driftwood Holdings’ financing Business model Notes:(1) Based on engineering, procurement, and construction agreements executed with Bechtel. (2) Approximately half of owners’ costs represent contingency; the remaining amounts consist of cost estimates related to staffing prior to commissioning, esti
Slide 13: Driftwood Holdings' operating costs
Driftwood Holdings’ operating costs Business model Total cost of ~$3/mmBtu locks in low cost of supply Sources: Wood Mackenzie, Tellurian Research. Notes: (1) Drilling and completion based on well cost of $10.2 million, 15.5 Bcf EUR, and 75.00% net revenue interest (“NRI”) (8/8ths). (2) Gathering, p
Slide 14: Margins and price signals
Margins and price signals Business model Netback prices to the Gulf Coast(1) Sources: Platts, CME, Tellurian Research. Notes: (1) Forward prices for 2018 assuming $2.00/mmBtu shipping cost from USGC to East Asia using Platts JKM. (2) Platts Gulf Coast Marker. 2018 JKM forward prices up $2.33 since N
Slide 15: Returns to Driftwood Holdings' partners
Returns to Driftwood Holdings’ partners(1) Business model U.S. Gulf Coast netback price ($/mmBtu) $6.00 $10.00 $15.00 Driftwood LNG, FOB U.S. Gulf Coast $(3.00) $(3.00) $(3.00) Margin ($/mmBtu) 3.00 7.00 12.00 Annual partner cash flow ($ millions)(2) 156 364 624 Cash on cash return 10% 24% 42% Payba
Slide 16: Value to Tellurian Inc.
Value to Tellurian Inc. Business model Notes: (1) $3.00/mmBtu cost of LNG FOB Gulf Coast. (2) Annual cash flow equals the margin multiplied by 52 mmBtu per tonne; does not reflect potential impact of management fees paid to Tellurian nor G&A. (3) Includes Seaport Global, Stifel, Cowen and Tuohy Brot
Slide 17: Marketing process – Driftwood Holdings
Marketing process – Driftwood Holdings Business model Activity 2018 Q1 Q2 Q3 Q4 Launch marketing Narrow candidates Negotiate agreements ~25 customer/partners in data room Feb 15 Commercialize Phase 1 by Q3 or Q4 2018
Slide 18: Conclusions
A global LNG demand pull has coincided with a supply push from the U.S., signaling the need for additional liquefaction capacity Successful projects manage risks related to construction of infrastructure, supply basin optionality, and transportation basis Tellurian’s business model provides investor
Slide 19: Contact us
Contact us Amit Marwaha Director, Investor Relations & Finance +1 832 485 2004 amit.marwaha@tellurianinc.com Joi Lecznar SVP, Public Affairs & Communication +1 832 962 4044 joi.lecznar@tellurianinc.com @TellurianLNG Contacts
Slide 20: Additional detail
2017 Additional detail
Slide 21: Site characteristics determine long-run costs
Site characteristics determine long-run costs Additional detail Access to power and water Berth over 45’ depth with access to high seas Support from local communities Access to pipeline infrastructure Site size over 1,000 acres Insulated from surge, wind, and local populations
Slide 22: Construction budget breakdown
Construction budget breakdown(1) Additional detail Notes:(1) Based on Driftwood LNG full development. (2) Includes additional contingency by developer and staffing prior to commencement of operations. (3) Provisional sum includes escalation factor for inflation, insurance, foreign exchange, and othe
Slide 23: Owning pipeline infrastructure mitigates basis risk
Owning pipeline infrastructure mitigates basis risk Additional detail Can you reach your selected basin? For how long? Tolling model SPA model Equity model Customer incurs risk Competition between customers for pipeline access leads to hidden costs and higher cost of LNG on the water Developer incur
Slide 24: Low-cost LNG is built before the fence line
Low-cost LNG is built before the fence line Additional detail Pipeline access and control of infrastructure is key Adequacy and reliability of supply is critical All-in cost is predictable, but execution and scale matter Basin Basis Construction Illustrative cost inflation +$1-$2/mmBtu in costs from
Slide 25: Corpus Christi LNG and Driftwood LNG examples
Corpus Christi LNG and Driftwood LNG examples Additional detail Source:Cheniere Analyst Day presentation (2018) and Tellurian analysis. Notes:(1) Includes approximately $0.4 billion in costs for additional compression on Driftwood pipeline in 3-plant case. (2) For Corpus Christi LNG, combined owners
Slide 26: Driftwood Holdings' financing
Driftwood Holdings’ financing Additional detail Notes:(1) Based on engineering, procurement, and construction agreements executed with Bechtel. (2) Approximately half of owners’ costs represent contingency; the remaining amounts consist of cost estimates related to staffing prior to commissioning, e
Slide 27: Regulatory and cost certainty
Regulatory and cost certainty Additional detail Regulatory schedule clarity Guaranteed lump sum turnkey contract with Bechtel Catalyst Estimated timeline Final Environmental Impact Statement 12 October 2018 FERC order and Federal Authorization Deadline 10 January 2019 Driftwood final investment deci
Slide 28: Production Company strategy
Production Company strategy Acquire and develop long-life, low-cost natural gas resources Low geological risk Scalable position Production of ~1.5 Bcf/d starting in 2022 Total resources of ~15 Tcf for Phase 1 Operatorship Low operating costs Flexible development Initially focused on Haynesville basi
Slide 29: >100 Tcf available resources in Haynesville
>100 Tcf available resources in Haynesville Additional detail Sources: IHS Enerdeq; 1Derrick; investor presentations; Tellurian research. Note: (1) Estimated resources based on acreage. Driftwood Holdings plans to fund and purchase 15 Tcf Potential acquisition targets: Range of resources per target
Slide 30: Demand pull
Demand pull Additional detail Demand outlook Sources: Wood Mackenzie, Tellurian Research. Notes:(1) Assumes 85% utilization rate. (2) Based on assumption that LNG demand grows at 4.5% p.a. post-2020. 127 mtpa of new liquefaction capacity required by 2025(1) mtpa Under construction In operation Deman
Slide 31: U.S. natural gas needs global market access
13 Bcf/d 6 1 8 1 4 U.S. natural gas needs global market access Additional detail 13 Bcf/d of incremental production; associated gas at risk of flaring without infrastructure investment Sources: EIA; ARI; Tellurian analysis. Note:(1) $1,000 per tonne average. LNG export capacity required: At least 10
Slide 32: Building a low-cost global gas business timeline
$25 million 2018 Pipeline open seasons $50 million $207 million Merger $100 million Upstream acquisition LSTK April/ December January February June November December Feb/March March June Management, friends and family invest $60 million in Tellurian in April/GE invests $25 million in Tellurian TOTAL
Slide 33: Funding and ownership
Funding and ownership Sources (1) ($ million) Notes:(1) As of July 31, 2018. (2) Excludes 6.1 million preferred shares outstanding. Ownership(1)(2) (%) $576 million 241 million shares Additional detail
Slide 34: Driftwood vs. competitors – cost per tonne
Driftwood vs. competitors – cost per tonne Sources:Wood Mackenzie, The World Bank, Tellurian Research. Note:(1) The World Bank bases the Logistics Performance Index (LPI) on surveys of operators to measure logistics “friendliness” in respective countries which is supplemented by quantitative data on
Slide 35: Integrated model prevalent internationally
Integrated model prevalent internationally Source:IHS. Projects include: Australasia APLNG, Darwin, GLNG, Gorgon, Ichthys, NWS, Pluto, Northwest Shelf, QCLNG, Wheatstone, PNG LNG, Tangguh, Brunei LNG, Donggi-Senoro, MLNG, Yamal LNG Mideast/Africa Angola LNG, EG LNG, Damietta, ELNG, Yemen LNG, Mozamb
Slide 36: Driftwood schedule
Driftwood schedule Additional detail Note:(1) Projects under Environmental Assessment (EA), all other projects required an Environmental Impact Statement (EIS), which entails a longer review process with FERC. Second wave First wave Months (1) (1) (1)
Slide 37: Key terms of EPC agreements with Bechtel
Key terms of EPC agreements with Bechtel Additional detail Trains 8 4 4 4 20 Storage facilities 2 0 1 0 3 Berths 1 1 1 0 3 Phase 1 Phase 2 Phase 3 Phase 4 Total 11.0 5.5 5.5 5.5 27.6 Capacity
Slide 38: Pipeline Network
Pipeline Network Gillis Market Area KMPL TETCO Trunkline Transco Tenn Gas CTPL Cameron FGT DWPL EGAN Texas Gas Pine Prairie ANR CGT Interconnects Permian Supply Area ETC –Comanche Trail ETC – Trans-Pecos ETC – Oasis Vaquero OneOK WesTex OXY Enterprise Jal El Paso WhiteWater NGPL Northern Natural Gas
Slide 39: PGAP connects constrained gas to SWLA
PGAP connects constrained gas to SWLA Additional detail Takeaway constraints in the Permian Southwest Louisiana demand Sources:Company data, Goldman Sachs, Wells Fargo Equity Research, RBN Energy, Tellurian estimates. Notes:(1) LNG demand based on ambient capacity. (2) Includes Driftwood LNG, Sabine
Slide 40: Haynesville type curve comparison
Haynesville type curve comparison Comparative type curve statistics Cumulative production normalized to 7,500’(3) Source:Company investor presentations. Notes:(1) Assumes 75.00% net revenue interest (“NRI”) (8/8ths). (2) Assumes gas prices of $3.00/mcf based on NRI and returns published specific to