  1. Slide 1: Pipeline and Storage Update

    Slide 1: Pipeline and Storage Update

    Privileged & Confidential Pipeline and Storage Update Jeffrey Miller Facilities Engineer, Interstate Marketing National Fuel Gas Supply Corp. Empire Pipeline, Inc. IOGA – NY 2019 Presentation

  2. Slide 2: Safe Harbor For Forward Looking Statements

    Slide 2: Safe Harbor For Forward Looking Statements

    Privileged & Confidential October 2019 National Fuel Gas Company Safe Harbor For Forward Looking Statements This presentation may contain “forward-looking statements” as defined by the Private Securities Litigation Reform Act of 1995, including statements regarding future prospects, plans, objective

  3. Slide 3: Pipeline & Storage Segment Overview

    Slide 3: Pipeline & Storage Segment Overview

    Privileged & Confidential October 2019 Pipeline & Storage Segment Overview National Fuel Gas Supply Corporation (NFGSC) Empire Pipeline  Current Supply assets include: − Pipeline totaling 2,384 miles − 32 Compressor Stations totaling 154,610 HP NFGSC − 31 Storage fields totaling 72 Bcf of top gas s

  4. Slide 4: NFGSC / Empire Infrastructure Plans

    Slide 4: NFGSC / Empire Infrastructure Plans

    Privileged & Confidential NFGSC / Empire Infrastructure Plans IOGA – NY 2019 Presentation

  5. Slide 5: Supply - Shell Cracker

    Slide 5: Supply - Shell Cracker

    Privileged & Confidential October 2019 Supply - Shell Cracker  Contracted capacity: 133,000 Dth/day  Facilities: ‒ 4.4-mile lateral of 12” pipe off Line N ‒ Other minor Line N enhancements  Target in-service: Fall 2019 5

  6. Slide 6: Supply - Shell Cracker

    Slide 6: Supply - Shell Cracker

    Privileged & Confidential October 2019 Supply - Shell Cracker 6

  7. Slide 7: Empire - Empire North Expansion

    Slide 7: Empire - Empire North Expansion

    Privileged & Confidential October 2019 Empire - Empire North Expansion 7

  8. Slide 8: Empire - Empire North Expansion

    Slide 8: Empire - Empire North Expansion

    Privileged & Confidential October 2019 Empire - Empire North Expansion  Contracted capacity: 205,000 Dth/day  Facilities: − 2 new compressor stations in NY & PA (54,000 horsepower) − No new pipeline construction  Target in-service: 2nd half of FY 2020 8

  9. Slide 9: Supply - FM100 Project

    Slide 9: Supply - FM100 Project

    Privileged & Confidential October 2019 Supply - FM100 Project  Expansion capacity: 330,000 Dth/day  Facilities (all in Pennsylvania): ‒ Approximately 30 miles of new 20’’/24’’ pipeline Marvindale CS ‒ 2 new compressor stations (totaling C approximately 37,000 HP) Clermont Gathering ‒ Abandonment o

  10. Slide 10: Supply - Line N Expansion Opportunities

    Slide 10: Supply - Line N Expansion Opportunities

    Privileged & Confidential October 2019 Supply - Line N Expansion Opportunities Open Season – OS 251 Mercer  Expansion capacity: Up to 500,000 Dth/d  Facilities: − Potential Ohio River crossing − Replacement of older-vintage pipe − Increasing system pressures − Lateral pipeline builds − Some modern

  11. Slide 11: Supply & Empire – Northern Access Project

    Slide 11: Supply & Empire – Northern Access Project

    Privileged & Confidential October 2019 Supply & Empire – Northern Access Project  Expansion capacity: 490,000 Dth/d  Facilities: ‒ Approximately 98 miles of new 16’’/24’’ pipeline ‒ Approximately 27,500 HP of additional compression  Target in-service: As early as FY 2022 11

  12. Slide 12: Supply Modernization Program

    Slide 12: Supply Modernization Program

    Privileged & Confidential Supply Modernization Program IOGA – NY 2019 Presentation

  13. Slide 13: Miles of NFGSC Pipeline by Decade Installed

    Slide 13: Miles of NFGSC Pipeline by Decade Installed

    Privileged & Confidential October 2019 Miles of NFGSC Pipeline by Decade Installed 500 450 400 350 300 250 200 150 100 50 - Pre-1940 1940 - 49 1950 - 59 1960 - 69 1970 - 79 1980 - 89 1990 - 99 2000 - 09 Post - 2010 Based on 2016 DOT Annual Report 13

  14. Slide 14: Supply Modernization Program

    Slide 14: Supply Modernization Program

    Privileged & Confidential October 2019 Supply Modernization Program  Supply continually works to modernize and upgrade its system  Began the modernization program spending in 2013  Supply reviews its system and undertakes modernization to address changing regulations and policies: − Regulations p

  15. Slide 15: Overview of Major Projects from 2013 - 2019

    Slide 15: Overview of Major Projects from 2013 - 2019

    Privileged & Confidential October 2019 Overview of Major Projects from 2013 - 2019 Spending/Yr Miles Miles Install Install Year Line Name Project Name State (MM) Install Retire Size Year L Corry PA 1.1 1.1 12” 1952 2013 $9.1 L Warren PA 1.3 1.3 12” 1950 NM44NY Elma NY 2.7 2.7 16” 1950 RM32 Evans NY

  16. Slide 16: Overview of Major Projects from 2013 – 2019 cont.

    Slide 16: Overview of Major Projects from 2013 – 2019 cont.

    Privileged & Confidential October 2019 Overview of Major Projects from 2013 – 2019 cont. Spending/Yr Miles Miles Install Install Year Line Name Project Name State (MM) Install Retire Size Year C48S Colden Storage NY 2.2 2.2 8” 1954 T2KNY T2K & KNY Abandonment NY 1.3 14.2 20” 1910 2017 $40.3 TNY Nort

  17. Slide 17: Questions

    Slide 17: Questions

    Privileged & Confidential Questions IOGA – NY 2019 Presentation

Source: Internet Archive copy of nationalfuel.com

More decks from National Fuel Gas Company

All 148 National Fuel Gas decks