KGHM Polska Miedz S.a. · GPW:KGH

KGHM Polska Miedz — H1 2019 Earnings Presentation

43 slides from KGHM Polska Miedz's earnings presentation, Aug 21, 2019

  1. Slide 1: Layers of possibilities: Results of the KGHM Group for 1H 2019

    Layers of possibilities Results of the KGHM Group for the 1st half of 2019 Lubin, 21 August 2019

  2. Slide 2: Cautionary Statement

    Cautionary Statement This presentation was prepared by KGHM Polska Miedź S.A. (KGHM). The presentation is strictly of an informational nature and should not be construed as containing investment advice. The users of this presentation are solely responsible for their own analysis and assessment of th

  3. Slide 3: Agenda

    Agenda 1. Key issues 2. Production results of the 3. Financial results KGHM Group by segment of the Group 4. Advancement of 5. Supporting slides – 6. Q&A development initiatives KGHM Polska Miedź S.A. 2

  4. Slide 4: Summation of the first half of 2019 in the KGHM Group

    Summation of the first half of 2019 in the KGHM Group Main events and factors affecting the results of the Group Production Stable production in accordance with targets Revenues 19% higher revenues to PLN 11 228 million1) Costs Lower C1 cost EBITDA Higher EBITDA by 6.5% to PLN 2 732 million First is

  5. Slide 5: Key issues

    Key issues

  6. Slide 6: Key production indicators

    Key production indicators H1 2019 Payable copper production by the KGHM Group 19% higher h/h 352 +19% H/H [kt]  KGHM Polska Miedź – Payable copper production Payable copper +19% H/H Sierra Gorda1) [kt] improved availability of production KGHM Polska Miedź [kt] 29 equipment 25 287 13 14  Sierra Gor

  7. Slide 7: Key economic indicators

    Key economic indicators H1 2019 Substantially higher revenues, Group EBITDA1) Group revenues [mn PLN] [mn PLN] +19% H/H EBITDA and net profit by the 2 732 KGHM Group 11 228 9 423 Higher revenues by PLN 1.8 billion 5 157 5 740  Growth in all of the Group’s segments – with the main increase in revenu

  8. Slide 8: Macroeconomic environment

    Macroeconomic environment Commodity and currency prices A stronger USD offset weaker copper prices in USD/t A significant decrease in copper prices in H1 2019 Price (USD/t) Annual av. (USD/t)  The price of copper fell (–11% yoy) compared to the corresponding prior-year Price (PLN/t) Annual av. (PLN

  9. Slide 9: Macroeconomic environment: trade war uncertainty

    Macroeconomic environment Trade war the main source of uncertainty in the global economy Will the trade war become a political instrument in the upcoming Despite escalation of the trade war the trade deficit elections? between the USA and China remains enormous Okres Tradewojny handlowej war period

  10. Slide 10: Consistent advancement of the strategy

    Consistent advancement of the strategy Key areas – 4E Adaptation of the operating  Rational management of the Company’s resources Flexibility  Optimisation of metallurgical production model for the KGHM Group  Exploration projects in Poland to market conditions  Optimisation of the international

  11. Slide 11: Production results of the KGHM Group by segment

    Production results of the KGHM Group by segment

  12. Slide 12: Metals production

    Metals production KGHM Group  Production of electrolytic Silver production Payable copper production copper exceeded the target set [kt] [t] +47% for KGHM Polska Miedź S.A. due 485 713 to improved availability of +19% 352 production equipment 295 29  Lower production by KGHM 36 H1 2018 H1 2019 25

  13. Slide 13: Production results

    Production results KGHM Polska Miedź S.A. Ore extraction Production of copper Electrolytic copper Metallic silver [mn t dry weight] in concentrate [kt] production [kt] production [t] –1.3% H/H –2.3% H/H +26% H/H +47% H/H 287 15,3 15,1 205 200 From 228 purchased 705 79 metal-bearing Silver materials

  14. Slide 14: Change in inventories

    Change in inventories KGHM Polska Miedź S.A. Inventories of copper in concentrate at the smelters –6% Q2/Q1 amount of Cu [t]  The level of inventories of copper in concentrate until now was due to 47 193 the three-month maintenance shutdown at the Głogów II Copper 36 606 34 248 Smelter and Refinery

  15. Slide 15: Production results: Sierra Gorda

    Production results Sierra Gorda1) Payable copper production Silver production [kt] [t] +12% H/H 6,3 7,1 +19% H/H 3,1 3,5  Higher extraction 29 by the Sierra Gorda 25 Q2 2018 Q2 2019 H1 2018 H1 2019 mine led to higher 14 TPM production2) copper, silver and gold 13 [koz t] +55% H/H production 9,3 14,

  16. Slide 16: Production results: KGHM INTERNATIONAL

    Production results KGHM INTERNATIONAL Payable copper production Silver production [kt] [t] +60% H/H  The silver production target was exceeded in 1,13 -16% H/H 0,71 the Sudbury Basin due to 0,40 0,46 a change in the region 43 being mined (different 36 Q2 2018 Q2 2019 H1 2018 H1 2019 nature of the d

  17. Slide 17: Financial results of the Group

    Financial results of the Group

  18. Slide 18: Group sales revenue

    Group sales revenue H1 2019 Revenues from contracts with customers +19% H/H Revenues from contracts with [mn PLN] customers [mn PLN] 11 228 +1 672 +857 +209 9 423 11 228 -933 9 423 983 1 414 936 1 298 Revenues Change in sales Change in prices Change in Other Revenues H1 2018 volumes of basic of basi

  19. Slide 19: C1 unit cost

    C1* unit cost1) KGHM Group C1 – KGHM Polska Miedź S.A. C1 – Group [USD/lb]  The decrease in C1 cost in KGHM [USD/lb] -5% H/H 1,90 1,81 including the minerals Polska Miedź S.A. versus the extraction 0,59 0,54 tax corresponding period of 2018 -3% H/H 1,31 1,27 was mainly due to a weakening of the PLN

  20. Slide 20: Operating results

    Operating results KGHM Group Change in adjusted EBITDA +7% H/H Adjusted EBITDA [mn PLN] [mn PLN] 2 732 2 565 128 +219 +16 2 732 152 2 565 349 333 -44 -24 336 380 1 700 1 919 H1 2018 KGHM KGHM Sierra Other H1 2019 Polska Miedź S.A. INTERNATIONAL Gorda H1 2018 1H 2019  The increase in EBITDA of the G

  21. Slide 21: Financial results: profit for the period

    Financial results KGHM Group 970 mn PLN Profit for the period + 59% H/H [mn PLN] consolidated net profit in H1 2019 The increase in net profit by the Group by PLN 359 million (+59%) was mainly due to: +1 805  improvement in the operating result  a lower loss on involvement in joint ventures accoun

  22. Slide 22: Cash flow

    Cash flow KGHM Group [mn PLN] +2 000 +307 +1 452 -145 1 106 957 -1 623 -107 -131 -1 604 Cash as at 1 Jan Profit/(loss) Change in working Other net cash Acquisition of Proceeds from the Proceeds from / Interest paid and Other Cash as at 30 June 2019 before income tax capital from operating property,

  23. Slide 23: Net debt of the KGHM Group

    Net debt of the KGHM Group As at the end of Q2 2019 Net debt / adjusted EBITDA Impact of change in Main factors affecting interest-bearing debt in H1 2019 IFRS 161) 1,7 (Increases in debt) 1,6 1,8 0,2  Cash expenditures on property, plant and equipment (PLN 1 604 million) 1,6  The minerals extract

  24. Slide 24: Bond issue program (1)

    Bond issue program (1) Parameters of the first issue Issuer KGHM Polska Miedź S.A. Bond type unsecured senior notes Issue program up to PLN 4 billion Total value of issue PLN 2 billion Issue type non-public offer Bookbuilding start 18 June 2019 On 27 May 2019 the Management Board of Bookbuilding end

  25. Slide 25: Bond issue program (2)

    Bond issue program (2) Transaction history Allocation by investor type  On 18 June 2019 the bookbuilding process 5-year bonds (series A) 10-year bonds (series B) commenced for PLN-denominated, unsecured 5-year (series A) and 10-year (series B) bonds 6% 1% 15% 25%  The maximum size of the issue was

  26. Slide 26: Minerals extraction tax

    Minerals extraction tax Key information The Act dated 12 April 2019 on changing the act on the minerals extraction tax was signed by the –15% President of the Republic of Poland and came into force on 1 July 2019 The updated act assumes a decrease in the tax rate by decreasing the co-efficients used

  27. Slide 27: Advancement of development initiatives

    Advancement of development initiatives 26

  28. Slide 28: Selected development projects

    Selected development projects Deposit Access Program Concentrate roasting installation Copper scrap processing furnace at the Legnica Copper Smelter and Refinery Expansion of the Żelazny Most Tailings Storage facility: the Southern Quarter Program to adapt the technological installations to the requ

  29. Slide 29: A consistent and rational investment program

    A consistent and rational investment program H1 2019 Cash expenditures by the KGHM Group in H1 2019 Capital expenditures of KGHM Polska Miedź S.A. +35% H/H [mn PLN] KGHM Polska Miedź S.A. 1 312 1 020 mn PLN2) 754 mn PLN in H1 2019 in H1 2018 KGHM INTERNATIONAL 312 294 Sierra Gorda Capital expenditur

  30. Slide 30: Start-up of the RCR copper scrap processing furnace

    Start-up of the RCR copper scrap processing furnace The largest investment in the history of the Legnica Copper Smelter and Refinery Heating equipment Handover of construction turned on, start of First casting of site to contractor – KGHM 26 February 2018 furnace heating 1 June 2019 anode copper Zan

  31. Slide 31: Start-up of the copper concentrate roasting installation

    Start-up of the copper concentrate roasting installation Głogów Copper Smelter and Refinery Start of flow of roasted concentrate Start of Start of fluidised to flash furnace for construction bed build-up production 25 October 2017 30 November 2017 28 June 2019 18 August 2016 Preliminary 7 November 2

  32. Slide 32: Supporting slides

    * ‘= ae OR a Le ‘ep Te yt oS ae - ae Nat a ; Ls % ‘56 ene * r ae any Ser te gs i ok GHM ¢ Polska HLeD es F Son ge Se DRS ge . ar 52 sapperting slides

  33. Slide 33: Sales revenue

    Sales revenue KGHM Polska Miedź S.A. In H1 2019 revenues from sales were higher by PLN 1 642 million (+23%) Sales revenue compared to the first half of 2018 due to: [mn PLN] +23% H/H  higher sales volumes (copper by 22% and silver by 45%), and  a more favourable USD/PLN exchange rate 8 831 683 alo

  34. Slide 34: Expenses by nature

    Expenses by nature KGHM Polska Miedź S.A.  Expenses by nature were higher by PLN 670 million (10%) mainly due to higher consumption of purchased metal-bearing materials by PLN 511 Expenses by nature million (a higher volume of purchased metal-bearing materials used by [mn PLN] +10% H/H 22 thousand

  35. Slide 35: EBITDA and profit for the period

    EBITDA and profit for the period KGHM Polska Miedź S.A. Higher standalone Adjusted EBITDA Profit for the period EBITDA and profit for [mn PLN] [mn PLN] +13% H/H the period 1 919 +24% H/H 1 700  EBITDA higher by 13% than in 1 227 H1 2018 due to a higher 987 volume of copper sold (higher revenues) 

  36. Slide 36: Profit for the period

    Profit for the period KGHM Polska Miedź S.A. Profit for the period +24% H/H [mn PLN] +1 641 +278 1 227 987 +136 +101 -45 -1 475 -202 -194 Profit for Increase in sales Increase in cost of Impact of Income from Gains (losses) Lower level of Income tax Other Profit for H1 2018 revenue sales, selling co

  37. Slide 37: Market risk management

    Market risk management Hedged positions on the copper market and the USD/PLN (as at 30 June 2019) Hedged position – as at 31 December 2018 Copper Hedged position implemented in H1 2019 The fair value of derivatives in KGHM Polska [tonnes] Miedź S.A. as at 30 June 2019 amounted to 18 000 PLN 507 mill

  38. Slide 38: Additional information

    Additional information Group revenues and EBITDA in Q2 2019 Lower EBITDA Q2/Q2 Revenues from contracts with Adjusted EBITDA mainly due to customers [mn PLN] [mn PLN] international assets: +11% Q/Q 5 740 5 157  KGHM INTERNATIONAL (-PLN 46 487 -8% Q/Q million; -22%) – lower due to higher 485 738 1 39

  39. Slide 39: Main initiatives aimed at improving OHS in the KGHM Group

    Main initiatives aimed at improving OHS in the KGHM Group Consistent advancement of the strategy  In the first half, operationalisation of the Company’s Strategy for the years 2019 – 2023 adopted in 2018 commenced Operationalisation of  In the area People and the Environment, a new initiative was

  40. Slide 40: Main initiatives advanced aimed at improving OHS in the Group

    Main initiatives advanced aimed at improving OHS in the Group Initiatives undertaken by Sierra Gorda and KGHM INTERNATIONAL Sierra Gorda  Advancement continued of the Occupational Health KGHM INTERNATIONAL Program introduced in 2018  Start of the Quality of Life program, consisting of actions aime

  41. Slide 41: Operationalisation of the Company's Strategy

    Operationalisation of the Company’s Strategy Operational goal D1 – Increase in workplace safety, in particular with respect to mining and metallurgy Initiative D1.2. Implementation of a program to overcome the most common workplace hazards by utilising innovative technology 1. Improve workplace safe

  42. Slide 42: Safety

    Safety Our priority LTIFR ratio in KGHM Polska Miedź S.A. 18,6 15,4 12,1 12,9 12,7 11,1 10,4 10,2 10,4 10,3 9,2 2010 2011 2012 2013 2014 2015 2016 2017 2018 H1 2018 H1 2019 In the first half of 2019 the LTIFR1) ratio was impacted by a large number of injuries sustained due to natural causes which oc

  43. Slide 43: Thank you

    Follow us in Thank you social media: Investor Relations Departament kghm.com/en/investors ir@kghm.com +48 76 74 78 280

KGHM Polska Miedź — H1 2019 Earnings Presentation on 6ix