Slide 1: Key Petroleum 2012 AGM Presentation cover letter
Key Petroleum Ltd For personal use only 29 November 2012 The Manager Australian Securities Exchange Company Announcements Office Level 4/20 Bridge Street SYDNEY NSW 2000 Dear Sir RE: 2012 ANNUAL GENERAL MEETING PRESENTATION We attach herewith Presentation for Annual General Meeting to be held on Fri
Slide 2: Annual General Meeting
For personal use only Key Petroleum Limited Annual General Meeting 30 November 2012
Slide 3: Disclaimer
Disclaimer Key Petroleum Limited The information in this presentation is an overview and does not contain all information necessary for For personal use only investment decisions. In making investment decisions, investors should rely on their own examination of Key Petroleum Ltd and consult with the
Slide 4: Strategic Direction
Strategic Direction Key Petroleum Limited Primary re-focus to Australian exploration and development For personal use only opportunities The Company has now exited from all minority small impact international interests New board in place with track record of success as at July 2012 to execute
Slide 5: Goals Achieved 2012
Goals Achieved 2012 Key Petroleum Limited • Divested all non-core assets (Tanzania, Suriname and United Kingdom) For personal use only • Exited Italy • New board in place from August 2012 that have executed the August Key strategic direction for remainder of 2012 • Reduced overheads by moving to sma
Slide 6: Current Board
Current Board Key Petroleum Limited • Mr Kane Marshall – Petroleum Engineer BSc (Geology), BCom (Corp. For personal use only Finance) & MPetEng Appointed Managing Director in April 2012 with over 10 years experience in exploration, production and development internationally and in Australia • Mr Ian
Slide 7: Exploration Interests
Exploration Interests Key Petroleum Limited • Canning Basin - Conventional and Unconventional: For personal use only EP 448 - 70.00% EP 438 - 76.00% EP 104 - 16.44% R1 - 16.44% Production License L15 (West Kora Oil Field) - 49.00% • North Perth Basin Conventional Oil: EP 437 - 50.00%
Slide 8: Canning Basin Interests
Canning Basin Interests Key Petroleum Limited For personal use only
Slide 9: Canning Basin Interests (cont.)
Canning Basin Interests (cont.) Key Petroleum Limited For personal use only • Interests in four million gross acres encompassing conventional and unconventional targets • Liquids focused exploration • Key operates one block (EP 448) and currently operates Cyrene-1 on behalf of the EP 438 Joint Ventu
Slide 10: Exploration Programme
Key Petroleum Limited Exploration Key Petroleum Limited Programme For personal use only Cyrene-1 commitment well targeting both conventional and unconventional plays over a 4 way dip anticlinal structure
Slide 11: Exploration Programme: Cyrene-1, Onshore Canning Basin
Key Petroleum Limited Exploration Key Petroleum Limited Programme For personal use only CYRENE -1, ONSHORE CANNING BASIN, WA • Cyrene-1 farmed out to Buru Energy to earn 75% (Mitsubishi and Buru) in EP 438 by spending $3 million including a well • Key Petroleum (70%) and Indigo Oil Pty Ltd (20%) are
Slide 12: Cyrene-1 Geographic Location
Cyrene-1 Geographic Location Key Petroleum Limited For personal use only LOCATION 100km South of Broome, 1.5km from Great Northern Highway The Cyrene structure consists of a four way dip closed anticline with estimated potential recoverable oil 5MBO Is adjacent to the Hedonia-1 well drilled by Gulf
Slide 13: Cyrene-1 Wellsite Layout
Cyrene-1 Wellsite Layout Key Petroleum Limited For personal use only Store Tools Fuel Tank Tank Tank Tank 1 2 3 F Sump l a 20m x 15m r e L i n e DCA Rig 7 Layout
Slide 14: Cyrene-1 Wellsite Activities
Cyrene-1 Wellsite Activities Key Petroleum Limited WELLSITE ACTIVITIES For personal use only • 30 man drilling camp and tubulars mobilised to site • Last of DCA Rig 7 and equipment on route to site • Site works completed including fencing around lease to protect from cattle on local station • Custom
Slide 15: Cyrene-1 Wellsite Activities (cont.)
Cyrene-1 Wellsite Activities (cont.) Key Petroleum Limited For personal use only A large part of the 30-man Drilling Camp was mobilised from Exmouth in November
Slide 16: Cyrene-1 Wellsite Activities (cont.)
Cyrene-1 Wellsite Activities (cont.) Key Petroleum Limited For personal use only Graded roads into the well location and truck lay down areas (top left), the edge of drilling pad (top middle), drilling pad after fencing fencing (top right), bunding and installation of water well pump (far left) and
Slide 17: Cyrene-1 Personnel
Cyrene-1 Personnel Key Petroleum Limited For personal use only Key Petroleum Wellsite Geologist Mike Harrison (right) at Point Torment in the 1990s (Canning Basin, EP 104) and Drilling Manager Hugh Edwards (below and left) at West Kora (L15) in the 1980s
Slide 18: Canning Basin Conventional & Unconventional Upside Potential
Canning Basin Conventional & Key Petroleum Limited Unconventional Upside Potential For personal use only • Athos 2D seismic survey has identified other conventional and unconventional structures in the EP 437 Buru Energy operated permit. • Core of Goldwyer shale will assist in understanding of uncon
Slide 19: Canning Basin Conventional & Unconventional Upside Potential (cont.)
Canning Basin Conventional & Key Petroleum Limited Unconventional Upside Potential (cont.) For personal use only • Currently seeking farmin partner to drill a well in 2013/14 Canning Basin dry season • Several other conventional structural and stratigraphic leads identified on trend with Ambrose (Wa
Slide 20: North Perth Basin Conventional & Unconventional Potential
North Perth Basin Conventional & Key Petroleum Limited Unconventional Potential For personal use only • Key Petroleum has a 50% interest in EP 437 • The Key technical team has identified two distinct play types: Unconventional carbonaceous shale gas potential of the Cattamarra Coal Formation Con
Slide 21: North Perth Basin Potential (cont.): Waugh-1
North Perth Basin Conventional & Key Petroleum Limited Unconventional Potential (cont.) For personal use only • EP 437 Commitment Waugh-1 is planned to test both unconventional and conventional play types: Dedicated flow test of Cattamara shale intervals Open hole drill stem test planned if good
Slide 22: North Perth Basin Conventional & Unconventional Potential (cont.)
North Perth Basin Conventional & Key Petroleum Limited Unconventional Potential (cont.) For personal use only
Slide 23: Corporate Position
Corporate Position Key Petroleum Limited • Key Petroleum listed in 2007 For personal use only • Market Capitalisation as at 30 1 Year Daily Share Price Movement November 2012 is ~ $13.5 million • Cash ~ $4.4 million • Capital Structure 450,509,417 shares Appointment of new Board • 1610 shareholders