National Grid Plc · LSE:NG.

National Grid — Flexibility Forum 11 January 2018

10 slides from National Grid's conference presentation, Jan 11, 2018

  1. Slide 1: Unlocking Future Potential – Pan-European Services

    Unlocking Future Potential – Pan-European Services Project TERRE Status Demand Connection Code Rachel Woodbridge-Stocks 0

  2. Slide 2: Project TERRE Status and Upcoming Events

    Project TERRE Status and Upcoming Events National Implementation European Implementation • Grid Code mod (GC 0097) and BSC mod • New TERRE members including Czech (P344) for TERRE implementation are Project TERRE Republic, Romania, Poland (Now 10 full progressing members) • GC0097: workgroup consult

  3. Slide 3: Demand Connection Code – Chapter Summary

    Demand Connection Code – Chapter Summary Chapter 1: General Provisions – Sets out the scope, defines key terms, timescales, who it applies to and how to implement the code. Key points Only applies to “New”: – Transmission-connected demand facilities – Transmission-connected distribution facilities a

  4. Slide 4: What do we mean by “New”?

    What do we mean by “New”? You aren’t “New” if you either: Connect to the Network September September March September 2016 2018 2019 2019 Or alternatively: Conclude contract Notify relevant SO of contract Both actions in this box must be completed to follow existing GB arrangements 3

  5. Slide 5: Demand Connection Code – Chapter Summary (Chapter 2)

    Demand Connection Code – Chapter Summary Chapter 2: Connection of transmission-connected demand facilities, transmission-connected distribution facilities and distribution systems Sets out a number of technical requirements for the facilities/systems mentioned above. Requirements such as:  Frequenc

  6. Slide 6: Demand Connection Code – Chapter Summary (Chapter 3)

    Demand Connection Code – Chapter Summary  Chapter 3: Connection of demand units used by a demand facility or a closed distribution system to provide demand response services to system operators Lists five categories that demand services should be grouped into: Remotely Controlled Autonomously contr

  7. Slide 7: Demand Connection Code – Points to Note in Chapter 3

    Demand Connection Code – Chapter Summary Points to note in Chapter 3  Applies to distribution-connected and transmission-connect demand  The categories listed aren’t exclusive and don’t prevent other categories existing/being developed  Chapter 3 lists the technical requirements associated with e

  8. Slide 8: Demand Connection Code – Chapter 3 Question

    Demand Connection Code – Chapter 3 Question  The categories in Chapter 3 can be listed in C16 and the technical requirements can be specified in standard contract terms; or  categories and technical requirements can be included in the Grid Code and/or Distribution Code  Do you have a preference?

  9. Slide 9: Demand Connection Code – Chapter 4: Compliance

    Demand Connection Code – Chapter Summary Chapter 4: Compliance  Covers compliance testing of: – Transmission-connected demand – Demand units providing demand response services – Includes simulations, monitoring and testing of equipment Chapters 5-7 relate mostly to implementation and derogations 8

  10. Slide 10: What can you do?

    What can you do? Get involved! Join the GC0104/DC0104 joint working group – keep up with the discussions and have your voice heard  Email grid.code@nationalgrid.com for more information and request a nomination form Respond to the GC0104/DC0104 consultations when they come out (the first is expecte

National Grid — Flexibility Forum 11 January 2018 on 6ix