Agl Energy Limited · ASX:AGL
Agl Energy — Corporate Update (June 2019)
17 slides from Agl Energy's corporate update, Jun 12, 2019
Slide 1: Coopers Gap Wind Farm Community Meeting No. 31
Coopers Gap Wind Farm Community Meeting No. 31 12 June 2019
Slide 2: Welcome
Welcome Rob Hart, Chairperson
Slide 3: Project Update
Project Update Michael Yeo, AGL Coopers Gap Site Project Manager
Slide 4: Project Update
Project Update Michael Yeo • Emergency Services Training • June 2019 • Not to be alarmed Coopers Gap Wind Farm | 12 June 2019 4
Slide 5: Project Update
Project Update Michael Yeo Coopers Gap Wind Farm | 12 June 2019 5
Slide 6: Construction Update
Construction Update GE-CATCON
Slide 7: Construction Update
Construction Update GE-CATCON • Site progress • Component deliveries • Turbine erection • First generation Coopers Gap Wind Farm | 12 June 2019 7
Slide 8: Construction Update
Construction Update GE-CATCON Coopers Gap Wind Farm | 12 June 2019 8
Slide 9: Blade and Tower deliveries
Blade and Tower deliveries Coopers Gap Wind Farm | 12 June 2019 9
Slide 10: Saren’s LG1750 Lifting Blades onto T68
Saren’s LG1750 Lifting Blades onto T68 Coopers Gap Wind Farm | 12 June 2019 10
Slide 11: Bunya Hwy / Niagara Rd
Bunya Hwy / Niagara Rd Intersection upgrade completed. 11 Coopers Gap Wind Farm | 12 June 2019
Slide 12: Community Update
Community Update Sharyn Garrett, Government and Community Relations Manager
Slide 13: Community Update
Community Update • Mobile phone coverage • Community Fund, Round 4 • Tourism Coopers Gap Wind Farm | 12 June 2019 13
Slide 14: Community Fund, Round 4
Community Fund, Round 4 • 16 Applications received • 12 awarded with funding ✓ Bell RSL Sub Branch (Qld) Inc. ✓ Kumbia Neighbourhood Watch Rural Inc. ✓ Bell Theatre Group Inc. ✓ Jandowae Squash Club Inc. ✓ Kumbia Tennis Association ✓ Ironpot Farmers Hall Association ✓ Ironpot Rural Fire Brigade ✓ Ku
Slide 15: General Business and Q&A
General Business and Q&A Rob Hart, Chairperson
Slide 16: CCC Meeting Schedule 2019
CCC Meeting Schedule 2019 • 11th September • 12th December Coopers Gap Wind Farm | 12 June 2019 16
Slide 17: Contact
Contact Brian McEvoy Construction Project Director (02) 9921 2344 bmcevoy@agl.com.au