Chaparral Energy Inc

Chaparral Energy — Wells Fargo Energy Conference 2011

38 slides from Chaparral Energy's conference presentation, Dec 7, 2011

  1. Slide 1: Wells Fargo Energy Conference December 7, 2011

    Slide 1: Wells Fargo Energy Conference December 7, 2011

    Wells Fargo Energy Conference December 7, 2011

  2. Slide 2: Chaparral Overview

    Slide 2: Chaparral Overview

    Chaparral Overview  Founded in 1988, Based in Oklahoma City  Core areas — Mid-Continent (Oklahoma) and Permian Basin (W. Texas)  Oil-weighted producer (63% oil; 37% gas); R/P ratio 18 years  Third largest oil producer in Oklahoma  Stable 1P base with large 2P and 3P Upside  Near-term growth po

  3. Slide 3: Operating Areas

    Slide 3: Operating Areas

    3 Operating Areas As of December 31, 2010 (SEC) Core Area Growth Area Acreage Field Offices Headquarters North Texas Reserves: 3.9 MMBoe, 3% of total Production: 0.5 MBoe/d, 2% of total Permian Basin Reserves: 19.6 MMBoe, 13% of total Production: 4.1 MBoe/d, 19% of total Rocky Mountains Reserves: 2.

  4. Slide 4: Strong Record of Reserve and Production Growth

    Slide 4: Strong Record of Reserve and Production Growth

    Strong Record of Reserve and Production Growth Year-End SEC Reserves (MMBoe) (1)(2)(3)(4) 2003 – 2010 CAGR = 17% Annual Production (MMBoe) 2003 – 2010 CAGR = 18% 142 113 164 151 103 73 51 0 25 50 75 100 125 150 175 2003 2004 2005 2006 2007 2008 2009 2010 149 Note: 1) Reserves as of December 31, 2007

  5. Slide 5: Financial Position to Execute Strategy

    Slide 5: Financial Position to Execute Strategy

    Net Debt / EBITDA Liquidity ($ in mm) 5.6x 4.4x 4.9x 3.2x 3.3x 2.3x 2.0x 2.0x 0.0x 0.0x 2007 2008 2009 2010 9/30/2011 Total net debt to EBITDA Net secured debt to EBITDA $88.0 $55.4 $76.6 $429.2 $390.8 2007 2008 2009 2010 9/30/2011 Financial Position to Execute Strategy 5 1) Note: Debt balances do n

  6. Slide 6: Resource Potential

    Slide 6: Resource Potential

    Resource Potential Chaparra

  7. Slide 7: Substantial Resource Potential for both Near Term and Long Term Growth

    Slide 7: Substantial Resource Potential for both Near Term and Long Term Growth

    Substantial Resource Potential for both Near Term and Long Term Growth 7 Near Term  Conventional Drilling (ROR 50% - 75%)  Anadarko Granite Wash  Anadarko Cleveland Sand  Leading Emerging Plays (ROR 35% - 75%)  Northern Oklahoma Mississippi Play (NOMP) ~244,000 acres  Developing Emerging Play

  8. Slide 8: Capital Budget

    Slide 8: Capital Budget

    Capital Budget ($millions) Component 2008 2009 2010 2011 Budget 2011 % Drilling $176 $83 $207 $177 55% Tertiary Recovery 25 15 38 93 29% Enhancements 55 35 41 32 10% Acquisitions 46 18 41 18 6% Total $302 $151 $327 $320 100% 85% 7% Play Drilling Northern OK Mississippi Horizontal $34 Anadarko Clevel

  9. Slide 9: Well Positioned for Near-Term and Long Term Growth

    Slide 9: Well Positioned for Near-Term and Long Term Growth

    9 Well Positioned for Near-Term and Long Term Growth NOMP 120 Million Barrels EOR 200 Million Barrels  Key near-term growth driver  Shallow oil target  Attractive F&D costs  Extensive history of vertical drilling  Long-term growth driver  Low-risk, stable production  Expertise to execute stra

  10. Slide 10: NOMP: A Key Near-Term Focus Area

    Slide 10: NOMP: A Key Near-Term Focus Area

    10 NOMP: A Key Near-Term Focus Area  244,000 Net Acres  Wildhorse Concession gives Chaparral exclusive rights to 138,000 acres  Drilled 9 wells to date  17 wells planned in 2012  Play Economics:  IP rates: 200 – 500 Boe/d  EURs: 200 – 400 MBOE  Well costs: $2.5 - $4 Million  Percent Oil: 60

  11. Slide 11: Northern Oklahoma Mississippi Play (NOMP)

    Slide 11: Northern Oklahoma Mississippi Play (NOMP)

    Northern Oklahoma Mississippi Play (NOMP) 11 Mississippi Horizontals CEI Leasehold 244,000 Net Acres Anadarko Basin Anadarko Shelf Chaparral NOMP Outline Sandridge NOMP Outline Osage Concession Area 217,000 Gross Acres 138,000 Net Available Oil Acres Plymouth Expl Sebranek 1-3H 4/28/11 IP 1021 bopd

  12. Slide 12: Northern Oklahoma Mississippi Type Curve Comparison

    Slide 12: Northern Oklahoma Mississippi Type Curve Comparison

    Northern Oklahoma Mississippi Type Curve Comparison IP Dei H Sandridge Energy Mississippi: 263 80 1.5 Cum at 50 Yrs = 406,852 Chesapeake Energy Mississippi: 300 82 1.2 Cum at 50 Yrs = 349,081 CELLC – NOMP West: 291 94 1.3 Cum at 50 Yrs = 271,421 CELLC – NOMP East: 215 94 1.3 Cum at 50 Yrs = 200,449

  13. Slide 13: Chaparral: A Growing Mid-Continent CO2 EOR Company

    Slide 13: Chaparral: A Growing Mid-Continent CO2 EOR Company

    13 Chaparral: A Growing Mid-Continent CO2 EOR Company

  14. Slide 14: Advantages of CO2 EOR

    Slide 14: Advantages of CO2 EOR

    Advantages of CO2 EOR  Lower risks than most other oil field projects  Can be deployed faster if the infrastructure is in place  Large reserves associated with its application can be booked  Only 1 in 81 CO2 projects have failed in the last 35 years Most oil companies are exploration-oriented an

  15. Slide 15: Long Life EOR Assets in Four Key Growth Areas

    Slide 15: Long Life EOR Assets in Four Key Growth Areas

    15 Long Life EOR Assets in Four Key Growth Areas Panhandle Area Permian Basin Central Oklahoma Area Burbank Area  200+ MMBOe Potential Reserves  Low Geologic Risk  Attractive Economics  ROR – 25% to 40%  ROI – 2.5:1 to 3.5:1  Capital Requirements - $75-$125 MM/yr  Long-term growth potential -

  16. Slide 16: Currently Owned CO2 Development Potential and Infrastructure

    Slide 16: Currently Owned CO2 Development Potential and Infrastructure

    16 Currently Owned CO2 Development Potential and Infrastructure Total OOIP 3,735 MMBO Primary Production 628 MMBO Secondary Recovery 597 MMBO Tertiary Potential 410 MMBO Net Tertiary Potential 197 MMBO Existing CELLC CO2 Pipelines Existing Third Party CO2 Pipelines Planned CELLC CO2 Pipelines Propos

  17. Slide 17: EOR 2011 Capital Budget

    Slide 17: EOR 2011 Capital Budget

    EOR 2011 Capital Budget 17 Budget by Category ($millions) Infrastructure / Pipelines $42 Drilling 24 Enhancements / CO2 Purchases 27 Total $93  Panhandle Area  Camrick Area $17 MM  Farnsworth Unit 27 MM  NE Hardesty (Non-op) 8 MM  Booker Area 3 MM  Other 1 MM $56 MM  Burbank Area  North Burb

  18. Slide 18: Processing Rate: The Key to Improved Rate of Return

    Slide 18: Processing Rate: The Key to Improved Rate of Return

    PROCESSING RATE: The Key to Improved Rate of Return 18 Hovey Morrow Unit (HMU) Time BO P D 25% hcpv Inj./Yr 10% hcpv Inj./Yr HMU Model: Processing Rate v. Reserve Recovery • CO2 Injection initiated Sep’07 • Processing Rates Average 25% hcpv Inj./Yr

  19. Slide 19: Contracted CO2 Supply

    Slide 19: Contracted CO2 Supply

    Contracted CO2 Supply 19 Source MMcfCO2/D Serving… Coffeyville 47 Burbank Enid 10 S. Central OK Arkalon 15* Agrium 23* Misc. 5 OBO 100 * Includes future CapEx upgrades Panhandle Area

  20. Slide 20: CO2 Infrastructure & Resource Potential

    Slide 20: CO2 Infrastructure & Resource Potential

    CO2 Infrastructure & Resource Potential 20 Chaparral CO2 Pipelines Planned Chaparral Pipelines Proposed Chaparral Pipelines Third Party Pipelines Cum. Recovered 1-3 MMBO Cum. Recovered 3-5 MMBO Cum. Recovered 5-10 MMBO Cum. Recovered 10+ MMBO Coffeyville Fertilizer Plant

  21. Slide 21: DOE CO2-EOR Technically Recoverable Resource Potential

    Slide 21: DOE CO2-EOR Technically Recoverable Resource Potential

    U.S. Department of Energy – Office of Fossil Energy – Office of Oil and Natural Gas CO2 – EOR Technically Recoverable Resource Potential Basin / Area No. Large Reservoirs Assessed All Reservoirs (Ten Basins / Areas Assessed) OOIP (Billion Barrels) ROIP (Billion Barrels) Technically Recoverable (Bill

  22. Slide 22: North Burbank CO2 Development

    Slide 22: North Burbank CO2 Development

    22 North Burbank CO2 Development

  23. Slide 23: Burbank Area Potential CO2 Projects

    Slide 23: Burbank Area Potential CO2 Projects

    23 Burbank Area Potential CO2 Projects Total OOIP 1,163 MMBO Primary Production 239 MMBO Secondary Recovery 211 MMBO Tertiary Potential 119 MMBO Net Tertiary Potential 100 MMBO Burbank Area: Net Potential: 100 MMBoe, 51% of total

  24. Slide 24: Business Plan: Economic Indices – Risk/Sensitivity

    Slide 24: Business Plan: Economic Indices – Risk/Sensitivity

    BUSINESS PLAN: Economic Indices – Risk/Sensitivity “BURBANK” in Perspective 24 Secondary Development Primary Development B O P D Tertiary Development “Business Plan”

  25. Slide 25: Farnsworth Unit CO2 Development

    Slide 25: Farnsworth Unit CO2 Development

    25 Farnsworth Unit CO2 Development

  26. Slide 26: Farnsworth Area Map

    Slide 26: Farnsworth Area Map

    Farnsworth is largest of several CO2 floods in Oklahoma and Texas Panhandle area CO2 injection initiated late 2010 26 Farnsworth Area Map

  27. Slide 27: Farnsworth Production Response

    Slide 27: Farnsworth Production Response

    27 Farnsworth Production Response Actual Budget Forecast YTD Actual + Remaining Forecast 62,859 Bbl

  28. Slide 28: Other Developing Drilling Plays

    Slide 28: Other Developing Drilling Plays

    28 Other Developing Drilling Plays

  29. Slide 29: Anadarko Basin - Woodford Shale

    Slide 29: Anadarko Basin - Woodford Shale

    Anadarko Basin - Woodford Shale 29 Woodford Shale Geology  Unconventional Shale Gas Play  NE flank of the Anadarko Basin  Gas and Oil Production  Successful Horizontal Drilling  Depth, Thickness, & Maturity Constraints Chaparral’s Acreage  23,000 (+/-) Net Acres including 2,100 Non-Producing 

  30. Slide 30: West Texas – Delaware Basin

    Slide 30: West Texas – Delaware Basin

    West Texas – Delaware Basin 30 Tunstill Acreage Block Haley Acreage Block

  31. Slide 31: Avalon Shale Position

    Slide 31: Avalon Shale Position

    Chaparral Energy, LLC Avalon Shale Position 17,000 Net Acres in West and Central Loving County, TX Upper and Lower Avalon Production Surrounding Acreage Block Over 80 Potential Avalon Drill Sites  Oil & NGL Rich Play  High Initial Production  Prime Acreage Position  Large Development Opportun

  32. Slide 32: Panhandle Marmaton

    Slide 32: Panhandle Marmaton

    • Unit’s average 30 day IP + 238 BOE/D • Unit’s average reserves 130 MBOE (76% oil, 14% NGL, 10% gas) • Unit’s average CWC: $2.8 MM Chaparral continues to lease in the play and currently has ~24,000 confirmed net acres in the Emerging Marmaton Play Avg Depth to Marmaton 6600’ Marmaton Vertical Produ

  33. Slide 33: Near-term + Long-term strategy yields significant value increase

    Slide 33: Near-term + Long-term strategy yields significant value increase

    33 More than 700 Million BOE Potential  Near-term + Long-term strategy yields significant value increase  ~ 70% Oil  Near-term focus on NOMP  De-risk play, unlock value  Production growth  Long-term focus on EOR  Low-risk production upside  Long-life, stable production * Woodford, Bone Sprin

  34. Slide 34: Financial Overview

    Slide 34: Financial Overview

    Financial Overview Chaparra

  35. Slide 35: Financials

    Slide 35: Financials

    Financials 2009 2010 YTD 09/30/2011 Production (MMBoe) 7.6 8.1 6.5 Oil (MMBbls) 3.5 3.7 3.2 Gas (Bcf) 22.6 23.7 16.5 NGL (MMBbls) 0.4 0.4 .5 Revenue Including Cash Settled Derivatives ($MM) $348.0 $448.5 382.4 Lease Operating Expenses $94.2 $106.1 $91.1 Production and Ad Valorem Taxes 20.3 26.5 26.7

  36. Slide 36: Financial Metrics per BOE

    Slide 36: Financial Metrics per BOE

    Financial Metrics per BOE Production (BOE) / Day LOE / BOE EBITDA / BOE G&A / BOE 19,323 20,926 22,055 23,732 15,000 20,000 25,000 2008 2009 2010 YTD Sep 2011 $17.05 $12.33 $13.18 $14.07 $0.00 $5.00 $10.0 $15.00 $20.00 2008 2009 2010 YTD Sep 2011$3.16 $3.11 $3.72 $4.42 $0.00 $1.00 $2.00 $3.00 $4.00

  37. Slide 37: 2010 Results and 2011 Guidance

    Slide 37: 2010 Results and 2011 Guidance

    Operating Statistics 2010 Results 2011 “Revised” Guidance Oil & Gas CAPEX $327 million $320 million Production 8.1 MMBoe 8.6 - 8.9 MMBoe General and Administrative $3.72/Boe $4.25 - $4.75/Boe Lease Operating Expense $13.18/Boe $13.75 - $14.25/Boe 2010 Results and 2011 Guidance 37

  38. Slide 38: Hedge Portfolio

    Slide 38: Hedge Portfolio

    Hedge Portfolio Note: 1) Dollars represent average strike price of hedges (includes all derivative instruments) Gas Basis Hedges Price % Gas PDP Nov-Dec 2011 $0.65 62% Jan-Dec 2012 $0.30 43% $7.02 $7.24 $7.34 $69.10 $69.94 $68.40 $10.00 % of Proved Developed Producing Hedged (As of Dec. 1, 2011) $90

Source: SEC EDGAR · 8-K filed Dec 7, 2011