Slide 1: ALSTOM T&D India Limited Quarter ended September 2013 Results
ALSTOM T&D India Limited Quarter ended September 2013 Results 6th November 2013
Slide 2: Disclaimer
Disclaimer • Forward-looking statements •This document contains forward-looking statements and information. These statements include financial forecasts and estimates as well as the assumptions on which they are based, statements related to projects, objectives and expectations concerning future ope
Slide 3: Indian Economy and T&D Market
Indian Economy and T&D Market Indian Economy Overall mood of Indian economy is yet to be positive. Large Private Industrial groups are not fully ready for new investments Many of the large Private Industrial groups are highly leveraged; have increased their debt over last year. Several Loan reschedu
Slide 4: Financial Highlights & Key Events
Financial Highlights & Key Events Orders / Backlog Won major contracts to the tune of 9.4 BINR during the quarter ended 30th September,2013 despite prevailing tough market conditions . Order Backlog at a stronger level of 64.7 BINR, Up 6% over H1 of FY 2012-13. Sales Sales for the quarter ended 30th
Slide 5: Main Orders
Main Orders MINR HPPTCL 400/220/66 kV GIS Package at Wangtoo a/c L&T 1550 PGCIL 765 kV Reactor package at Kanpur and Jatikara 765 GETCO 400 kV AIS Sub-station at Charanka 765 GETCO 400 kV AIS Sub-station at Sankhari Park 750 PGCIL 220 kV GIS Sub-station at Melli 510 BSPTCL 220 kV AIS Sub-station at
Slide 6: Order Intake
Order Intake MINR 18,000 17,464 15,000 10,554 12,000 +37% HVDC 9,433 9,000 6,000 6,910 3,000 0 Sep'12 Sep'13 Excluding HVDC, YOY increase of 37% in order inflow (Sept’12 include HVDC of 10,554) Presentation title - 06/11/2013 – P 6 © ALSTOM 2013. All rights reserved. Information contained in this do
Slide 7: Order Backlog
Order Backlog + Stronger Order Backlog despite challenging market Presentation title - 06/11/2013 – P 7 © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be relied on 7 that it is complete or correct or wil
Slide 8: Sales
Sales MINR 10,000 8,022 8,000 6,780 6,000 4,000 2,000 0 Sep'12 Sep'13 18% Increase due to better execution and customer support Presentation title - 06/11/2013 – P 8 © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given
Slide 9: Profit After Tax
Profit After Tax MINR 480 380 280 208 180 ` 80 -20 -18 Sep'12 Sep'13 Higher sales supported improvement in profit Presentation title - 06/11/2013 – P 9 © ALSTOM 2013. All rights reserved. Information contained in this document is indicative only. No representation or warranty is given or should be r
Slide 10: Key Data for 3 months ended 30th September, 2013
Key Data for 3 months ended 30th September, 2013 Sales Revenue 6,780 8,022 18.3% Operating Profit 98 541 As % of Sales 1.5% 6.7% 5.2 pts Profit After Tax -18 208 As % of Sales -0.3% 2.6% 2.9 pts Presentation title - 06/11/2013 – P 10 © ALSTOM 2013. All rights reserved. Information contained in this