Duke Energy Corporation (Holding Company) · NYSE:DUK

Duke Energy Corporation (Holding Company) — Corporate Update (April 2014)

17 slides from Duke Energy Corporation (Holding Company)'s corporate update, Apr 22, 2014

  1. Slide 1: Coal Ash Update

    Coal Ash Update Environmental Review Commission – April 22, 2014

  2. Slide 2: Update on Dan River

    Update on Primary Ash Basin Stormwater Pipe Outlet Approximate location of pipe break Stormwater Pipe Outlet Stormwater Secondary FH Pine inlet Ash Basin 3 Duke Energy Property Rough diagram; for illustrative purposes only

  3. Slide 3: Update on Dan River

    Update on Dan River 3

  4. Slide 4: Cape Fear Plant

    Other coal ash-related actions Cape Fear Plant 4

  5. Slide 5: Update on coal ash management plan

    Update on coal ash management plan 5

  6. Slide 6: Update on coal ash management plan

    Update on coal ash management plan 6

  7. Slide 7: Update on coal ash management plan

    Update on coal ash management plan 7

  8. Slide 8: Update on coal ash management plan

    Update on coal ash management plan 8

  9. Slide 9: Update on coal ash management plan

    Update on coal ash management plan 9

  10. Slide 10: Update on coal ash management plan

    Update on coal ash management plan 10

  11. Slide 11: Task force, Engineering review, Comprehensive long-term plan

    Update on coal ash management plan Comprehensive Task force Engineering review long-term plan • Internal strategic • Third-party, • Intensive analysis team independent review and closure • Reports directly to of all ash basin strategies for each CEO Lynn Good facilities site • Complete by May • Comp

  12. Slide 12: Sutton, Riverbend and Cliffside

    Update on coal ash management plan – Sutton, Riverbend and Cliffside Retired Sutton Plant Retired Riverbend Plant Cliffside Plant 12

  13. Slide 13: Update on coal ash management plan – Asheville Plant

    Update on coal ash management plan – Asheville Plant 13

  14. Slide 14: Reuse options: Bridges, Roadways, Structural Fill

    Reuse options Bridges Roadways Structural Fill 14

  15. Slide 15: Solutions take time

    Solutions take time am{j,, 1 TRUCK | EVERY 3 MINUTES | 12 HOURS A DAY | 6 DAYS A WEEK 1O'—'O 1.2 MILLION TONS OF ASH 22 MILLION MARSHALL TONS OF ASH YEARS YEARS

  16. Slide 16: Solutions take funding

    Solutions take funding Notes: Assumes non-hazardous designation by the U.S. EPA All costs expressed are rough order of magnitude estimates. These are subject to detailed engineering studies and do not include financing, inflation and increased operations and maintenance costs. 16

  17. Slide 17: fa DUKE

    fa DUKE Se” ENERGY.

Duke Energy — Corporate Update (April 2014) on 6ix