  1. Slide 1: Natural Gas Pipelines

    ENERGY PARTNERS, L.P. Natural Gas Pipelines Scott Parker President Natural Gas Pipeline Group

  2. Slide 2: Natural Gas Pipelines and Facilities

    ENERGY PARTNERS, L.P. KMP Natural Gas Pipelines and Facilities NATURAL GAS PIPELINES NATURAL GAS STORAGE NATURAL GAS PROCESSING ROCKIES EXPRESS PIPELINE IN-SERVICE ROCKIES EXPRESS PIPELINE MIDCONTINENT EXPRESS PIPELINE KM LOUISIANA PIPELINE INDICATES NUMBER OF (2,3,8) FACILITIES IN AREA KM HEADQUART

  3. Slide 3: KMP Natural Gas Pipelines

    ENERGY PARTNERS, L.P. KMP Natural Gas Pipelines Texas Intrastates Trailblazer Pipeline Kinder Morgan Interstate Gas Transmission TransColorado Midcontinent Express Pipeline Rockies Express Pipeline Kinder Morgan Louisiana Pipeline 3

  4. Slide 4: Texas Intrastate Pipelines

    ENERGY PARTNERS, L.P. Texas Intrastate Pipelines 6,000 miles of pipeline 5 Bcf/d capacity Perryville 123 Bcf on-system storage Carthage 915 MMcf/d processing Waha capacity Katy Henry 250 MMcf/d CO2 treating capacity Kinder Morgan Texas Pipeline KMTP Storage KMTP Gas Processing Kinder Morgan Tejas Pi

  5. Slide 5: Texas Intrastate Pipelines: Continued Growth

    ENERGY PARTNERS, L.P. Texas Intrastate Pipelines Continued Growth Expansion of Existing Assets: Completed in 2007: 13 miles of 24” pipeline, $18 million – East Texas Expansion 7 Bcf, $41 million – Markham storage expansion Under Construction in 2008: 63 miles of 24” pipeline, $70 million - Goodrich

  6. Slide 6: Texas Intrastate Pipelines: Continued Growth

    ENERGY PARTNERS, L.P. Texas Intrastate Pipelines Continued Growth Growth from Existing Assets: Higher premiums for ratable / swing services, end-user gas sales, and transport Value of storage services continues to increase Rollovers of sales contracts at higher margins providing year on year growth

  7. Slide 7: Trailblazer Pipeline Company

    ENERGY PARTNERS, L.P. Trailblazer Pipeline Company Trailblazer 436 Miles of Pipe Wyoming 3 Compressor Locations with 58,000 HP Nebraska Huntsman Max Throughput = 0.878 CheyenneStorage Bcf/d 602 Lincoln 601 Low cost pipeline out of Cheyenne Hub 603 region 106 Long term contracts Denver Colorado 195 K

  8. Slide 8: Kinder Morgan Interstate Gas Transmission (KMIGT)

    ENERGY PARTNERS, L.P. Kinder Morgan Interstate Gas Transmission (KMIGT) 4,500 miles of various diameter pipelines Markets: Wyoming  LDCs, Industrials, & Ag. In NE, KS, & MO  Marketers transporting to mid-continent pipelines Nebraska  End Users including Cheyenne Ethanol Plants Hub Growth:  Color

  9. Slide 9: KMIGT Growth Projects

    ENERGY PARTNERS, L.P. KMIGT Growth Projects… New LDC Connection - Colorado Lateral is a new pipeline along the front range.  KMIGT has a long term binding transport agreement and is moving forward to construct a $29 million pipeline  In-service October 1st, 2008  Potential of future expansions to

  10. Slide 10: TransColorado Pipeline

    ENERGY PARTNERS, L.P. TransColorado Pipeline TransColorado 301 miles of 22” & 24” pipeline Originates at Greasewood CO Terminates at Blanco, NM Bidirectional Flow  Capacity North - 650 MDth/d  Capacity South • Phase I - 150 MDth/d • Phase II - 425 MDth/d 10

  11. Slide 11: TransColorado Growth Projects

    ENERGY PARTNERS, L.P. TransColorado Growth Projects… Completed 250,000/day expansion for northbound capacity from Blanco to REX Pipeline $68 million capital investment Fully subscribed by ConocoPhillips In-service Jan 2008 Potential: New Producer Interconnects for example, Exxon Piceance Creek Trans

  12. Slide 12: Midcontinent Express Pipeline

    ENERGY PARTNERS, L.P. Midcontinent Express Pipeline Waynoka Plant Enogex West Enogex East Project Facilities Summary Diameter Miles Zone Capacity From - To 30” 40 1 850,000 Enogex to 802 42” 262 1 1,400,000 802 to End of Zone 1 36” 197 2 1,000,000 Begin Zone 2 to Transco Total 499 12

  13. Slide 13: Midcontinent Express Pipeline (MEP)

    ENERGY PARTNERS, L.P. Midcontinent Express Pipeline (MEP) 50/50 Joint Venture with ETC  Key driver – Increasing production in Texas and Oklahoma  Kinder Morgan coordinating construction and will operate MEP to Construct: • 40 miles of 30”, 257 miles of 42” and 197 miles of 36” • 70,900 of horsepow

  14. Slide 14: Midcontinent Express Pipeline (MEP)

    ENERGY PARTNERS, L.P. Midcontinent Express Pipeline (MEP) Key Items: Major material acquired within budget (pipe, compression & valves) Agreements executed with construction contractors In-service date for entire system projected March 1, 2009  Schedule going forward: • Draft EIS – Feb ‘08 • Final

  15. Slide 15: Rockies Express Pipeline (REX)

    ENERGY PARTNERS, L.P. Rockies Express Pipeline (REX) OVER- ROCKIES EXPRESS PIPELINE THRUST CAPACITY REX REX EAST LEASE IN-SERVICE 1,500,000 Dth/d - 2/2008 1,600,000 Dth/d - 12/2008 1,800,000 Dth/d - 7/2009 Opal Kanda Wamsutter Cheyenne Lebanon Meeker Greasewood Clarington PIPELINE – 1,679 MILES COMP

  16. Slide 16: REX West Spreads

    ENERGY PARTNERS, L.P. REX West Spreads In-service Jan 12th up to the ANR Interconnect 16

  17. Slide 17: Project Overview – Rockies Express

    ENERGY PARTNERS, L.P. Project Overview – Rockies Express REX West – Construction is winding down:  Commenced Interim Service Deliveries into NNG, NGPL and ANR on January 12, 2008 • 1.4 Bcf of capacity  Expect to Commence Full Service on REX West to include PEPL (Audrain County, Mo.) in mid Februar

  18. Slide 18: REX East Detail

    ENERGY PARTNERS, L.P. REX East Detail 2008 Construction: FERC approval anticipated in Spring 2008. Commencement of construction soon after FERC approval received. Partial in-service date for REX East Dec 31st, 2008 (to Clarington). Full 1.8 Bcf in-service (all compression) June 1st, 2009. Material a

  19. Slide 19: REX Future Opportunities

    ENERGY PARTNERS, L.P. REX Future Opportunities… Significant additional growth potential via other opportunities to be captured… Storage and Park and Loan Service  Development and sale of storage off the pipeline Interruptible and short haul service Hub service at various key locations Extensions an

  20. Slide 20: Proposed REX Northeast Express

    ENERGY PARTNERS, L.P. Proposed REX Northeast Express 1.0 Bcf/d Expansion 1.5 Bcf/d Extension Hub Service 20

  21. Slide 21: Proposed REX / NGPL Chicago Project

    ENERGY PARTNERS, L.P. Proposed REX / NGPL Chicago Project 2121

  22. Slide 22: Kinder Morgan Louisiana Pipeline LLC

    ENERGY PARTNERS, L.P. Kinder Morgan Louisiana Pipeline LLC Texas Louisiana CGT Delivery Point 340 Transco Delivery Point ( ( TETCO Delivery Point ( ANR Delivery Point ( ( ( ( Texas Gas Delivery Point FGT Delivery Point Cypress Delivery Point ( ( Trunkline Delivery Point Lake Charles LNG Lafayette 30

  23. Slide 23: Kinder Morgan Louisiana Pipeline

    ENERGY PARTNERS, L.P. Kinder Morgan Louisiana Pipeline Capital - $510 MM - Construction has commenced!! Project Description NGPL Lateral 1, 597,500 Dth/d Rayne Lateral Rayne Lateral (Leg 1) 2,130,000 Dth/d  137 miles 42” Sabine Pass Facility  2,130,000 Dth/d  In-service Jan 1st, 2009 NGPL Lateral

  24. Slide 24: Kinder Morgan Louisiana Pipeline

    ENERGY PARTNERS, L.P. Kinder Morgan Louisiana Pipeline Initial Project Capacity is Sold Out… Executed Precedent Agreement with Chevron USA MDQ: 1,697,500 Dth Negotiated Rate: Fixed for term of contract Term: 20 years Executed Precedent Agreement with Total Gas & Power North America, Inc MDQ: 1,697,5

  25. Slide 25: Kinder Morgan Louisiana Pipeline

    ENERGY PARTNERS, L.P. Kinder Morgan Louisiana Pipeline Beyond the Initial Project… Future Growth Potential: Continue discussions with multiple parties to potentially expand the capacity of the pipeline (with LNG upstream supply schedules extending discussions have continued)  Potential for an addit

  26. Slide 26: KMP Gas Pipeline Group: The Future

    ENERGY PARTNERS, L.P. KMP Gas Pipeline Group The Future… Base business growth on existing assets… Re-contract existing pipeline and storage capacity Capture margin growth on existing capacity Growth opportunities from new projects focused on… Midcontinent Express, Rockies Express and KM Louisiana Pi