Aurelia Metals — Corporate Update (August 2024)

15 slides from Aurelia Metals's corporate update, Aug 20, 2024

  1. Slide 1: CCC Presentation Hera-Federation Complex Project Update

    CCC Presentation Hera-Federation Complex Project Update 20 August 2024 ASX Code: AMI

  2. Slide 2: Acknowledgement of Country

    Acknowledgement of Country • Aurelia Metals Ltd respectfully acknowledges the Ngiyampaa Nation as the Traditional Custodians of this land – both past and present. • We know this land has history, custodians and stories, spanning tens of thousands of years, that endure to this day. • We pay our respe

  3. Slide 3: Federation Hera Complex Progress

    3 Federation Hera Complex Progress Tracking Key Dates of Interest: • Stage 2 Civil works set to commenced in May 2024. This involves the area of the Rom pad, paste plant, heavy vehicle access road and new explosives magazine. Works are ongoing and being carried out by Neill Earthmoving, Nyngan. Wet

  4. Slide 4: Federation Hera Complex Progress: Water Management Dam Construction

    4 Federation Hera Complex Progress Water Management Dam Construction:

  5. Slide 5: Federation Hera Complex Progress: Water Treatment Plant

    5 Federation Hera Complex Progress Water Treatment Plant and location of Back Tank east :

  6. Slide 6: Federation Mine Development

    6 Federation Mine Development Mine development November 2023 mining achieved 217.7m advance Federation development 27 April 2024

  7. Slide 7: Federation Mine Development

    7 Federation Mine Development Mine development November 2023 mining achieved 217.7m advance Federation development 2 August 2024

  8. Slide 8: Federation Mine Development

    8 Federation Mine Development Recommissioning of the Hera workshop to service all light vehicles at Hera Federation

  9. Slide 9: Environment and Community

    Environment and Community 20 August 2024 ASX Code: AMI

  10. Slide 10: Environment and Community: Modification 2 to the Project Approval

    10 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Modification 2 to the Project Approval As communicated at the May CCC, The company has issued a letter to the Department of Planning, Housing and Infrastructure to commence “Mod 2” to the Project Approval S

  11. Slide 11: Environment and Community: Priorities, Initiatives and Complaints

    11 Environment and Community Environmental Priorities, Improvement Initiatives and Complaints Priorities and improvement initiatives • Approval to carry out road works on the Kidman is a key priority to enable ore to be transported to the Peak. The company's consultant is progressing a works deed wi

  12. Slide 12: Rehabilitation Strategy

    12 Environment and Community Rehabilitation Strategy – Hard copy provided • The company must prepare a Rehabilitation Strategy for the development to the satisfaction of the Planning Secretary • be prepared in consultation with Resources Regulator, DPE Water, BCD, CSC and the CCC • The company must

  13. Slide 13: Environment and Community: Rehabilitation Strategy

    13 Environment and Community Rehabilitation Strategy –

  14. Slide 14: Exploration

    Exploration 20 August 2024 ASX Code: AMI

  15. Slide 15: Federation Exploration

    15 Exploration Federation Exploration • Since the May meeting there has been an auger program completed on Four Corners (between Hera and Federation) and on Lyell. • Works on Iron Bark were suspended due to the rain and wet access. • No results have been communicated as yet