AT & S Austria Technologie & Systemtechnik Aktiengesellschaft · VIE:ATS

AT & S Austria Technologie & Systemtechnik Aktiengesellschaft — Corporate Update (April 2015)

8 slides from AT & S Austria Technologie & Systemtechnik Aktiengesellschaft's corporate update, Apr 29, 2015

  1. Slide 1: AT&S Conference Call April 29, 2015

    AT&S first choice for advanced applications Conference Call April 29, 2015 AT & S Austria Technologie & Systemtechnik Aktiengesellschaft | Fabriksgasse 13 | A-8700 Leoben Tel +43 (0) 3842 200-0 | E-mail info@ats.net AT&S, April xx 2015 www.ats.net

  2. Slide 2: Investment Case Chongqing – Substrate-like PCBs: Strong market demand

    Investment Case Chongqing – Substrate-like PCBs Strong market demand in core business – 1 Level of complexity Technology Roadmap in PCB industry is developing faster ▪ Core business with high-end PCBs (HDI Microvia) shows continuous strong market demand: CAGR 2014-20191 of ~ 4 % ▪ Ongoing trend for

  3. Slide 3: Investment Case Chongqing – Expand leading technology position

    Investment Case Chongqing – Substrate-like PCBs 2 Expand leading technology position in core business Level of complexity ▪ To address next level of technology development and expand leading technology position AT&S establishes capabilities and capacities to provide SLPs to the market ▪ Technology s

  4. Slide 4: AT&S Technology Roadmap

    AT&S Technology Roadmap Year PCB Technical Development min. L/S [µm] 1982 Multi Layer 100 1998 Micro Via 60 2005 Any Layer 40 Advanced 2010 15 Packaging 2015 Substrate Like PCB 20-30 2016 IC- Substrate 8 Future All in one Package AT&S, April 29, 2015 4

  5. Slide 5: Layout Chongqing – IC-Substrates & Substrate-like PCBs

    Layout Chongqing – IC-Substrates & Substrate-like PCBs Building 1: IC Substrate plant Building 2: Substrate-like PCB plant Specifications: Specifications: Clean Room Class < 100 Clean Room Class < 10,000 to Process: semi-additive < 1,000 in special areas Process: modified semi-additive AT&S, April 2

  6. Slide 6: Project Status IC Substrate plant Chongqing

    Project Status IC Substrate plant Chongqing IC Substrates – Chongqing I Start Equipment Installation Certification FY 2014/15 FY 2015/16 FY 2016/17 FY 2017/18 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Start of Production up to High Volume Mass Production Start Equipment Characterisation Substr

  7. Slide 7: Financing Chongqing: IC Substrate & Substrate-like PCB

    Financing Chongqing: IC Substrate & Substrate-like PCB ▪ CAPEX Chongqing - Total CAPEX until Fiscal Year 2016/17: EUR 480 million - Already spent as at December 31, 2014: EUR 180 million ▪ Current and estimated gross debt levels - As at December 31, 2014: EUR 404 million (Cash and cash equivalents E

  8. Slide 8: Disclaimer

    Disclaimer This presentation is provided by AT & S Austria Technologie & Systemtechnik Aktiengesellschaft, having its headquarter at Fabriksgasse 13, 8700 Leoben, Austria (“AT&S”), and the contents are proprietary to AT&S and for information only. AT&S does not provide any representations or warrant

AT&S Austria Technologie & Systemtechnik Aktiengesellschaft — Corporate Update (April 2015) on 6ix