Vhm Limited · ASX:VHM

Vhm — Investor Presentation (September 2023)

27 slides from Vhm's investor presentation, Sep 29, 2023

  1. Slide 1: Relodged Presentation

    29 September 2023 Company Announcements Office ASX Limited PO Box H224 Australia Square SYDNEY NSW 2000 Dear Sir/Madam RELODGED PRESENTATION VHM Ltd (ASX:VHM) advises it retracts the presentation lodged with ASX on 21 September 2023. The reason for the retraction is to delete slide on page 26 with t

  2. Slide 2: VHM Limited

    VHM Limited Emerging Tier 1, Australian project with globally significant mineral assemblage September 2023 ASX:VHM Acknowledgement of Country VHM acknowledges the Australian Aboriginal and Torres Strait Islander peoples as the first inhabitants of the nation and the traditional custodians of the la

  3. Slide 3: Disclaimer and forward-looking statements

    Disclaimer and forward-looking statements Important Information Forward looking statements are based on numerous assumptions regarding VHM Limited’s present and future business strategies and the environment in which VHM Limited will operate in the future. Among the important This presentation has b

  4. Slide 4: Contents

    Contents 1 Company Overview 2 Goschen Project Highlights 3 Cannie Project 4 Area 4 Orion Strandline Appendix A JORC Tables 3

  5. Slide 5: VHM Limited (ASX:VHM) overview

    VHM Limited (ASX:VHM) overview Australian owned rare earths and mineral sands Corporate Snapshot1 mine and processing developer Market Cap GOSCHEN PROJECT Goschen Project 198.7Mt ORE @ 3.7% THM, A$111.70M MRE 629 Mt, 413 Kt TREO, DFS complete Zircon 21.4%, Rutile 9.7%, Share Price Targeting producti

  6. Slide 6: Board and management team

    Board and management team Don Runge, BE (Mining), MAusIMM Maree Arnason, BA, FAID Non-Executive Chairman Non-Executive Director (August 2023) • 40+ years’ operational and project experience including industrial minerals where he managed the • 35 years’ experience across the resources, energy and man

  7. Slide 7: Premium Rare Earths and Mineral Sands Projects

    Premium Rare Earths and Mineral Sands Projects Located on freehold land in North West Victoria Three distinct Projects have been defined: The flagship, Goschen Project with compelling economics defined by the DFS Refresh1: ▪ NPV of $1.5 billion ▪ IRR of 44% ▪ payback of 2.8 years2 Advanced approvals

  8. Slide 8: Company asset overview

    Company asset overview Location of deposits ▪ The Goschen Project is located within Retention Licence (RL) 6806 and Exploration Licence (EL) 6419 in north west Victoria • 280km north west of Melbourne • 30km south west of Swan Hill • 4km east of Lalbert ▪ The different project areas • Area 1 • Area

  9. Slide 9: Global energy transition targets

    Global energy transition targets The catalyst driving demand for rare earth elements and commercialisation of Australia’s critical minerals 87% of Goschen basket value is derived from the critical rare earths crucial for electric vehicles and the green energy transition1. Notes: (1) Rare Earth Marke

  10. Slide 10: Goschen Project

    Goschen Project VHM’s near-term rare earths and mineral sands project

  11. Slide 11: Development plan and offtake strategy considerations

    Development plan and offtake strategy considerations VHM seeks to achieve the ultimate objective of its offtake strategy by aligning with its phased production development Near-term Mid-term Long-term Secure additional offtake Expand offtake into Asian, Complete phased production partner who can off

  12. Slide 12: Goschen Project overview

    Goschen Project overview Phase 1 and Phase 1A (Hydromet Circuit) process flowsheet Phase 1 ▪ High recoveries likely at Goschen Mine: Continuous improvements achieved through testwork has delivered high recoveries of valuable rare earth, zircon and titanium products. ▪ Final products: Zircon and tita

  13. Slide 13: Goschen Hydromet Pilot Plant test results

    Goschen Hydromet Pilot Plant test results Exceptional recoveries meet specifications required by Western strategic offtake partners ▪ Market leading recoveries achieved by ANSTO Pilot Hydromet Plant producing a high purity mixed rare earth carbonate (MREC) product ▪ >97% critical light rare earths N

  14. Slide 14: Goschen Project highlights

    Goschen Project highlights The DFS Refresh1 demonstrates the Goschen Project economics to be compelling 5Mtpa 9.4ktpa >20 years REMC Conventional open cut Target annual production rates for mining methods rare earth mineral concentrate excavation, load and haul 8.5ktpa 134.5ktpa MREC HMC Target annu

  15. Slide 15: Goschen Project permitting and approval pathway

    Goschen Project permitting and approval pathway Planning Approvals & Construction Operation Closure 2018 – 2020 2021 – 2022 2023 2024 2024– 2026 2026 – 2044 2045 ▪ Continue studies ▪ Prepare EES ▪ EES Inquiry & Advisory ▪ Production ▪ Phase 1A ▪ End of mining ▪ Feasibility studies ▪ Preliminary to i

  16. Slide 16: Cannie Project

    Cannie Project Impact of the new Cannie Mineral Resource

  17. Slide 17: A major critical mineral inventory of a global scale is in the making

    A major critical mineral inventory of a global scale is in the making With the discovery of the Cannie and Nowie Projects1 the Company confirms a major new critical minerals province centred on top and west of the Lake Boga granite. A significant Critical Minerals inventory that has the potential to

  18. Slide 18: VHM Limited geological overview

    VHM Limited geological overview Confirming a major new critical minerals province in Victoria1 The addition of Cannie Project maiden Mineral Resource estimate raises total Company Mineral Inventory to: 43% 39% 95% 51% 590 Kt 5.1 Mt 2.9 Mt 2.7 Mt TREO +Y2O3 Zircon Leucoxene Rutile Total Company Total

  19. Slide 19: Area 4 Orion Strandline

    Area 4 Orion Strand Ne lin

  20. Slide 20: Area 4 Orion Strandline

    Area 4 Orion Strandline Maiden Probable Ore Reserve (September 2023) 11.5 million tonnes (Mt) @ 5.6% THM1. Within this Ore Reserve a high-grade minable horizon of 2.6 Mt @ 9.6% THM exists at the top of the ore body, including: ▪ 245,500 tonnes of mineable THM ▪ 67,700 tonnes of zircon at an in-situ

  21. Slide 21: Area 4 Orion Strandline

    Area 4 Orion Strandline ▪ Sand hosted REM +HMS 100m ▪ 6.5m to the top of mineralisation ▪ Zone 5 is 4.5m thick ▪ Zone 4 is 4.5m thick 6.5m ▪ Metallurgy results demonstrate higher grade ▪ Mineral Resource complete 20

  22. Slide 22: Area 4 Orion Strandline

    Area 4 Orion Strandline Mineral Resource understated vs 2023 Metallurgy Testwork ▪ A 1600kg ROM sample was used to conduct a variability study on zones 2, 3, 4, and 5 in Area 41. ▪ Metallurgy results confirm higher grades than forecast by Mineral Resource and Ore Reserve. ▪ 7.5% higher grade in uppe

  23. Slide 23: High-grade strandlines opportunity

    High-grade strandlines opportunity ▪ 21 strandlines identified by processing historic data. ▪ Cygnus strandline 7km east of Goschen Project has returned from VHM drilling very high-grade, 6m below surface 2m >60%THM containing 2.9% in-situ zircon + titanium dioxide and rare earth minerals. ▪ Nowie d

  24. Slide 24: APPENDIX A JORC Tables

    APPENDIX A __..JORC Tables We ws ‘

  25. Slide 25: Company Ore Reserves

    Company Ore Reserves 210Mt Ore Reserve Note: The Ore Reserve was disclosed under the JORC Code (2012) in the Company ASX announcement published 18 September 2023. 24

  26. Slide 26: Company Mineral Resources

    Company Mineral Resources 820Mt Mineral Resource estimate Total Heavy Oversize THM Assemblage(3) Rare Earth Oxides Mineral Material In Situ THM Bulk Density Mineral Slimes material Area Resource TREO + (THM) >2mm Zircon Rutile Leucoxene Ilmenite Monazite Xenotime La2O3 CeO2 Pr6O11 Nd2O3 Sm2O3 Eu2O3

  27. Slide 27: vhmltd.com.au

    vhmltd.com.au Level 11, 330 Collins Street, Victoria 3000 For further information contact: Graham Howard Managing Director graham.howard@vhmltd.com.au Carly O’Regan Executive General Manager carly.oregan@vhmltd.com.au