Gpt Infraprojects Limited · NSE:GPTINFRA

Gpt Infraprojects — Q1 FY25 Earnings Presentation

26 slides from Gpt Infraprojects's earnings presentation, Jul 31, 2024

  1. Slide 1: Exchange cover letter for investor presentation

    GPT Infraprojects Limited Regd. Office: GPT Centre, JC-25, Sector III, Salt Lake, Kolkata – 700 106, India CIN : L20103WB1980PLC032872 Phone : +91-33-4050-7000, Email : info@gptgroup.co.in , Visit us: www.gptgroup.co.in GPTINFRA/CS/SE/2024-25 July 31, 2024 The Department of Corporate Services, Natio

  2. Slide 2: Q1 FY25 Investors' Presentation

    GPT Infraprojects Limited Q1 FY25 Investors’ Presentation NSE : GPTINFRA | BSE : 533761

  3. Slide 3: Safe Harbour

    Safe Harbour This presentation and the accompanying slides (the “Presentation”), which have been prepared by GPT Infraprojects Limited (the “Company”), have been prepared solely for information purposes and do not constitute any offer, recommendation or invitation to purchase or subscribe for any se

  4. Slide 4: Table of Content

    Table of Content 01 Q1 FY25 Key Updates 02 Company Overview 03 Annexure GPT Infraprojects Limited - Investor Presentation Q1FY25 3

  5. Slide 5: Q1 FY25 Key Updates

    Q1 FY25 Key Updates GPT Infraprojects Limited - Investor Presentation Q1FY25 4

  6. Slide 6: Q1FY25 – Result Snapshot (Consolidated)

    Q1FY25 – Result Snapshot (Consolidated) Revenue EBITDA PAT Order Book Order Inflow Rs. 241.7 Cr Rs. 34.3 Cr Rs. 16.8 Cr Rs. 3,669.1 Cr Rs. 811.5 Cr  2.5% YoY  16.3% YoY  27.3% YoY GPT Infraprojects Limited - Investor Presentation Q1FY25 5

  7. Slide 7: Financial Highlights- Consolidated (Q1FY25)

    Financial Highlights- Consolidated (Q1FY25) Share of JCE & Minority; Rs -0.6 Cr __% -3% Finance Costs : Rs 8 Cr 24% 93% Depreciation : Rs 4 Cr 11% Infrastructure: Rs 225 Cr Tax: Rs 6 Cr 16% 14% EBITDA : Net Profit: Rs 17 Cr 49% Rs 34 Cr 7% Concrete Sleeper : Rs 17 Cr 100% 38% Raw Material Costs : Rs

  8. Slide 8: Profit & Loss – Standalone

    Profit & Loss – Standalone Particulars (Rs Cr) Q1FY25 Q1FY24 YoY % Q4FY24 QoQ % FY24 FY23 YoY % Revenue 236.2 234.3 0.8% 294.1 -19.7% 996.1 790.0 26.1% Other Income 3.1 5.2 -40.4% 2.5 24.0% 13.7 7.2 91.2% Net Sales 239.1 239.5 -0.2% 296.6 -19.4% 1,009.8 797.2 26.7% Operating Expenses 204.7 207.0 -1.

  9. Slide 9: Profit & Loss – Consolidated

    Profit & Loss – Consolidated Particulars (Rs Cr) Q1FY25 Q1FY24 YoY % Q4FY24 QoQ % FY24 FY23 YoY % Revenue 241.7 235.9 2.5% 295.0 -18.1% 1,018.3 809.1 25.8% Other Income 1.5 3.8 -60.5% 1.3 15.4% 6.6 4.6 43.9% Net Sales 243.2 239.7 1.5% 296.3 -17.9% 1,024.9 813.7 26.0% Operating Expenses 209.6 210.2 -

  10. Slide 10: Business Segment Update (Consolidated – Q1FY25)

    Business Segment Update (Consolidated – Q1FY25) Revenue EBIT Order Book Concrete Concrete Concrete Sleepers, Sleepers, Sleepers, 5% 7% 7% Rs 241.7 Cr Rs 34.0 Cr Rs 3,669.1 Cr Infrastructure, Infrastructure, Infrastructure, 93% 95% 93% Infrastructure : Rs 225.2 Cr Infrastructure : Rs 32.2 Cr Infrastr

  11. Slide 11: Highest Ever Order Book of Rs 3,669.1 Cr

    Highest Ever Order Book of Rs 3,669.1 Cr 1,841 1,018 3,669 3,099 812 2,276 242 Order Book as on Order Executed New Order Inflow Order Book as on Order Executed New Order Inflow Order Book 31-Mar-23 31-Mar-24 as on Date Robust Order Book of Rs 3,669.1 Cr, forming ~3.6 times FY24 Revenue, provides gro

  12. Slide 12: Key Major Projects Contributing to Revenue

    Key Major Projects Contributing to Revenue Segment Scope of Work Client City/State Value (Rs Cr) Construction of new 4 lane Prayagraj Southern Bypass NHAI Prayagraj, UP 835 Construction of Bridges for Mathura – Jhansi 3rd Line RVNL Rajasthan & UP 727 Construction of Viaduct, Major Bridges for New BG

  13. Slide 13: Company Overview

    Company Overview GPT Infraprojects Limited - Investor Presentation Q1FY25 12

  14. Slide 14: Key Strengths

    Key Strengths 01 02 03 04 Indian Railways: End-To-End Solution Railway Focused Growth Visibility Structural Changes Track record of executing Concrete Sleeper and Robust Order Book of Reforms for Investment & Turnkey Projects creating a Infrastructure ~Rs 3,669.1 Cr, forming better Governance niche

  15. Slide 15: Executive Summary

    Executive Summary The largest single order in The company is maintaining GPT’s history, valued at Rs. dividend policy by rewarding 835 Cr from the NHAI for its share holders. During FY24, construction of new 4 lane company has paid a total Prayagraj Southern Bypass dividend of Rs 3 was paid in Uttar

  16. Slide 16: A Railway Focused Infrastructure Company

    A Railway Focused Infrastructure Company Premier Infrastructure Company: Engaged in Civil Construction and Presence in two Business Segments : Concrete Sleeper manufacturing for Railways 1. Infrastructure Execution Capabilities: With ~40 years of experience, GPT has developed Strong Project Executio

  17. Slide 17: Infrastructure

    Infrastructure Steel Bridges Roads, Bridges Building of mega bridges with & Highways super steel structures across various terrains. Construction of bridges elevated metro structures and concrete pavement for airports. Industrial Construction of railway sidings, merry-go-round railways, roads, indus

  18. Slide 18: Concrete Sleepers

    Concrete Sleepers Among the Pioneers Well Experienced Manufacturing Concrete Sleepers Manufactured more than 15 for mainlines, curves, bridges, Million concrete sleepers for level crossings, and points & Indian Railways crossings. Capacity Manufacturing capacity of 2 Mn units across India & Africa G

  19. Slide 19: Board of Directors

    Board of Directors Vaibhav Tantia Amrit Jyoti Tantia Dwarika Prasad Tantia Shree Gopal Tantia Atul Tantia Director & COO Director (Projects) Chairman Managing Director Executive Director & CFO C C C M M M M Kashi Prasad Khandelwal Arun Kumar Dokania Shankar Jyoti Deb Aditya Kumar Mittal Rashmi Bihan

  20. Slide 20: FY24 – Highest Ever Revenue and Profits (Consolidated)

    FY24 – Highest Ever Revenue and Profits (Consolidated) Total Income (Rs Cr) EBITDA (Rs Cr) & EBITDA Margin (%) PAT (Rs Cr) & PAT Margin (%) 5.6% 140 13.0% 13.5% 12.5% 60 6.0% 130 13.0% 3.9% 50 5.0% 3.6% 120 12.5% 11.3% 40 4.0% 110 12.0% 56 100 1,025 128 30 3.0% 11.5% 814 90 678 31 20 2.0% 11.0% 92 8

  21. Slide 21: Annexure

    Annexure GPT Infraprojects Limited - Investor Presentation Q1FY25 20

  22. Slide 22: Profit & Loss

    Profit & Loss Standalone Consolidated Particulars (Rs Cr) Mar-24 Mar-23 YoY % Mar-24 Mar-23 YoY % Revenue 996.1 790 26.1% 809.1 1,018.3 25.8% Other Income 13.7 7.2 91.2% 4.6 6.6 43.9% Net Sales 1,009.8 797.2 26.7% 813.7 1,024.9 26.0% Operating Expenses 881.9 700.8 25.8% 721.7 897.3 24.3% EBITDA 127.

  23. Slide 23: Balance Sheet

    Balance Sheet Standalone Consolidated Standalone Consolidated Liabilities (Rs Cr) Assets (Rs Cr) Mar-24 Mar-23 Mar-24 Mar-23 Mar-24 Mar-23 Mar-24 Mar-23 Share Capital 58.2 58.2 58.2 58.2 Fixed Assets incl. CWIP 76.6 80.4 126.8 138.4 Reserves 231.7 191.5 218.9 244.5 Investment 72.6 47.3 24.8 23.8 Sha

  24. Slide 24: Cash Flow

    Cash Flow Standalone Consolidated Particulars (Rs Cr) Mar-24 Mar-23 Mar-24 Mar-23 Cash Flow from Operating Activities Profit Before Tax 46.5 81.9 37.2 78.2 Operating Profit before Working Capital 94.9 119 94.7 114.9 (Increase)/decrease in Inventories -12.8 -13.9 -7.0 -16.3 (Increase)/decrease in Tra

  25. Slide 25: Stock Information and Shareholding Pattern

    Stock Information 225 2,000 Shareholding Pattern (Jun’24) 4.5% 0.9% 200 1,800 1,600 175 Bonus 1:1 19.5% 3rd Interim Dividend 1,400 150 of Re.1 /- 1,200 125 2nd Interim 75.0% Volumes in ‘000s Dividend of Re.1 /- 1,000 Price in Rs 1st Interim 100 Dividend 800 Promoters Investors DII FII of Re.1 /- 75

  26. Slide 26: Thank You

    Thank You GPT Infraprojects Limited Stellar IR Advisors Pvt. Ltd. CIN: L20103WB1980PLC032872 Mr. Atul Tantia, Executive Director & CFO Ms. Pooja Sharma atul@gptgroup.co.in pooja.sharma@stellar-ir.com Ms. Mansi Mohta, Executive Assistant to ED & CFO Mr. Vishal Mehta mansi.m@gptgroup.co.in vishal@stel

GPT Infraprojects — Q1 FY25 Earnings Presentation on 6ix