  1. Slide 1: Stratford Coal CCC Meeting Presentation – Company Report & Overview of Activities

    Stratford Coal CCC Meeting Presentation – Company Report & Overview of Activities February 2020 Alarna Bristow Acting Environment & Community Superintendent

  2. Slide 2: Table of Contents

    Table of Contents 1. Agenda Item 7a (Progress at the Mine) 2. Agenda Item 7b (Environmental Reporting) 3. Agenda Item 7c (Environmental Management Plans and Monitoring) 4. Agenda Item 7d (Community Complaints) 5. Agenda Item 7e (Community Programs) 2

  3. Slide 3: 1. Progress at the Mine

    1. Progress at the Mine Mining 3rd Quarter 2019  Waste BCM 1,465,656 BCM  Stratford ROM Coal 406,142 tonnes (Includes Codam)  Total CHPP product 279,256 tonnes  Mining in BRN continued during the quarter. Dayshift only.  Mining in Avon North continued during the quarter. Day and evening shift.

  4. Slide 4: 2. Environmental Reporting & Regulators

    2. Environmental Reporting & Regulators Management Area Project Status Reporting • Stratford Mining Complex • The Stratford Mining Complex 2019 Annual Review is currently being prepared. Annual Review 2019 The AR is due by the end of March 2020. Copies will be made available to the CCC. Regulator •

  5. Slide 5: Water Access Modification

    Water Access Modification Stratford Water Access Modification • The NSW Department of Planning, Industry and Environment granted the Stratford Extension Project modification to allow offsite water transfer by a public authority. • This Modification permits Council to access Stratford’s surplus mine

  6. Slide 6: 3. Environmental Management Plans & Monitoring

    3. Environmental Management Plans & Monitoring a) Air Quality Management b) Blast Management c) Noise Management d) Water Management e) Rehabilitation Management f) Biodiversity Management 6

  7. Slide 7: 3a. Air Quality Management

    3a. Air Quality Management Management Area Project Status Air quality monitoring • Real-time air quality • The real-time air quality TEOM monitors in Stratford and Craven villages monitoring continue to operate. • SCPL has established alarming and a response protocol for the real-time dust monitorin

  8. Slide 8: 3a. Air Quality Management

    3a. Air Quality Management Stratford Dust Deposition - Annual Rolling Average Stratford HVAS Monitoring - Particulate Matter (PM10) 12 Months to January 2020 12 Months to January 2020 5.0 200 Dust (g/m2/month) 4.0 PM10 (µg/m³) 150 3.0 100 2.0 50 1.0 0 0.0 2-Jan-19 2-Mar-19 2-May-19 2-Jul-19 2-Sep-19

  9. Slide 9: 3b. Blast Management

    3b. Blast Management Management Area Project Status Blasting • Blast Monitoring • Blasting activities continued in both the Avon North, BRN open cuts with blasting commencing again in Roseville West pit from November. • Blast Results • 1 blast exceeded 115dB(L) during the quarter. For the annual rep

  10. Slide 10: 3b. Blast Management

    3b. Blast Management Clarke (B5) (Mine- Overpressure Isaac (B1) Ex-Judge (B2) Atkins (B6) owned) Overpressure Site Shot # Location Date Time "Cumulative Fume Rating 7432 7441 7434 7433 Exceedance 1 Exceedance" 1 (previously 7377) 24hr mm/s dBL mm/s dBL mm/s dBL mm/s dBL % AN090 Avon North Friday, 4

  11. Slide 11: 3c. Noise Management

    3c. Noise Management Management Area Project Status Monitoring • Monthly Noise Survey • Monthly attended noise monitoring was undertaken during Q4 2019. • No non-compliant results were recorded during the surveys. Reports will be made available on the Stratford Coal website. The next monitoring is s

  12. Slide 12: 3d. Water Management

    3d. Water Management Management Area Project Status Water management • Avon North Pit Flood • The Avon Pit North Pit Flood Bund is currently under construction. The flood bund Structures Bund design is based on the updated flood model for the Avondale Creek catchment. • Stratford East clean • The St

  13. Slide 13: 3d. Water Management

    3d. Water Management Stratford Monthly Rainfall pH - Avon River & Avondale Creek 300 12 Months to January 2020 9 Rainfall (mm) 200 8 100 7 pH 0 6 5 2019 05-Jan-1905-Apr-19 04-Jul-19 02-Oct-1931-Dec-1930-Mar-20 2018 2017 Month W1 W2 W3A W4 W5 W6 EC - Avon River & Avondale Creek Surface Water Monitori

  14. Slide 14: 3d. Water Management

    3d. Water Management Stratford Main Pit Water Quality 5000 12 months to January 2020 10.0 EC (uS/cm) , Sulphate 4000 9.0 8.0 3000 (mg/L) pH 7.0 2000 6.0 1000 5.0 0 4.0 16-Dec-18 04-Feb-19 26-Mar-19 15-May-19 04-Jul-19 23-Aug-19 12-Oct-19 01-Dec-19 20-Jan-20 EC (uS/cm) Sulphate (mg/L) pH Stratford Ma

  15. Slide 15: 3e. Rehabilitation Management

    3e. Rehabilitation Management Management Area Project Status Rehabilitated Waste • Avon North waste • Bulk shaping of the Avon North waste emplacement has continued focusing on Emplacements emplacement areas with offsite visual impact. Topsoil spreading has commenced and will be followed by ground p

  16. Slide 16: 3f. Biodiversity Management

    3f. Biodiversity Management Management Area Project Status Mining Lease Areas • Vegetation Clearance • Clearing permits were prepared for works in Stratford East and Avon North. The clearing permits address the management of vegetation, fauna trapping and spotter-catcher work, heritage sites and top

  17. Slide 17: 3f. Biodiversity Management

    3f. Biodiversity Management Management Area Project Status Biodiversity Offset • Revegetation • Tubestock planting in the biodiversity offset area will commence in March 2020, ground Area Works preparations began January 2020. Approximately 45 000 tube stocks are to be planted . Biodiversity Offset

  18. Slide 18: 3f. Biodiversity Management

    3f. Biodiversity Management Management Area Project Status Nest Box Program • Nest Box Installation • 78 Nest boxes are scheduled to be installed in the Stratford Biodiversity Area and Biodiversity Enhancement Area in February 2020. 60 of these boxes are to specifically target the Squirrel glider an

  19. Slide 19: 4. Community Complaints - Summary

    4. Community Complaints - Summary Stratford Complaint Summary Period: 31/10/2019 - 31/01/2020 Period: 3 Months Total No. of Complaints: 2 Total No. of Complainants: 2 Date/Time of Complaint Complainant Location Method of Complaint Nature of Complaint Investigation/Outcome 10/12/2019 12:50hrs Approx.

  20. Slide 20: 5. Community Programs

    5. Community Programs Management Area Project Status Support Programs Stratford Coal • The application period for the 2020 Stratford Coal Community Support Program is closed. Community Support • Applications have been reviewed with the outcomes announced in February 2020. Program • Stratford Coal •